CE Mix Flashcards
(152 cards)
Name some facilities that will require an electrical power commissioning plan…..
Hospital- The hospital will have critical operations power systems (COPS), as defined by the National Electrical Code Article 708, and will need to be commissioned in order to make sure they are operating properly. Critical operations would apply to buildings which must maintain their ability to operate during an emergency.
Bank- The bank will have critical operations power systems (COPS), as defined by the National Electrical Code Article 708, and will need to be commissioned in order to make sure they are operating properly. These systems will most likely be tied to the vault. Critical operations would apply to buildings which must maintain their ability to operate during an emergency.
Name some project closeout tasks and who performs them…..
Prepare Punch List- Contractor
Prepare Record Drawings- Contractor
Perform final inspection- Architect
Pay Final pay application- Owner
Start Building systems- Subcontractor
Check Building Systems- Commissioning agent
Provide building system testing reports- Commissioning agent
Assemble documentation of field changes
Finalize billing and collections
Include Certificate of Substantial Completion
Name some of the costs that must be included in a lifecycle cost analysis….
Initial Costs
Operational Costs
Maintenance Costs
Financing Costs
For what reasons are performance mock-ups (PMU) done?
- to protect the health, safety, and welfare of individuals
- seeing a full-size version would validate a design intent
- to pinpoint any areas of weakness as they pertain to water penetration
Under which design delivery method are submittals streamlined?
Design-Build- Under a design-build project, the designer and builder are in one contract, which streamlines the submittal process. Since the architect and contractor are one entity under design-build, the two parties have open communication. Therefore, the need for formal submittals from the contractor to the architect is streamlined as many issues are typically worked out during the creation of the working drawings
When would a contractor be permitted to request a time extension?
when causes are outside of the contractor’s control (example of acceptable reasons-labor dispute, architect error, owner change)
What are some benefits to straw bale construction?
Higher R-Value- straw bales will have an R-value between 35 and 50 in a typical wall assembly.
Smaller foundations- due to the straw bales weighing less, the foundations could be shallower.
Sound Barrier- given their mass, straw bales are an effective sound barrier.
What are “walers” and where and why are they used?
A waler is a horizontal beam used to support sheathing or concrete formwork. It is an element of support, not a bracing method.
Design Build delivery method is best suited for which type of projects?
projects that have straightforward building types with experienced clients.
Fast Track delivery method is best suited for which type of projects?
projects where design and construction can overlap. Projects that have a need for speed over quality are candidates for fast-tracking. In this scenario, buildings can be built in a series, one right after another
CMAR delivery method is best suited for which type of projects?
projects where the contractor is involved early to help provide input on complex construction matters such as keeping a busy facility operational at a sensitive site.
Integrated Project Delivery method is best suited for which type of projects?
projects where several experts come together at the beginning of a project when goals are set and major building systems are selected. This allows for an integrated project where value is maximized and waste is minimized.
According to the AIA A201, who is responsible for costs incurred for the discovery of hazardous material?
The owner is responsible. But the contractor pays any fines and is reimbursed by the owner.
On what side should flush control for toilets be located to comply with ADA accessibility codes?
the open side, not the wall side.
What is Sound Transmission Class (STC)?
a material’s ability to block airborne sound. STC ratings are given to assemblies that are constructed under ideal conditions. Actual conditions tend to be 5-15 dB less because of leaks and flanking paths.
What does Impact Isolation Class (ISC) measure?
it measures an assembly’s ability to absorb noise caused by impact to a floor/ceiling assembly. To reduce impact noise, the IIC rating of an assembly should be increased
What does Noise Reduction Coefficient (NRC) measure?
it measures the amount of energy absorbed by a material when the sound waves reach a surface
What is the International Code Council (ICC)?
the organization that develops building codes
What are the benefits of a Stipulated Sum Contract?
- the owner compensates the contractor a fixed price for providing work, according to the contract documents
- competitively bid projects most often use this type of contract delivery
- actual construction costs and construction bid difference are absorbed as profit or loss by the contractor
- unit prices are permitted
- alternates are permitted
- the owner knows the cost of construction at the time of the contract execution
How long after occupancy are post occupancy evaluations done?
3-6 months
What are the purposes of AIA G716 RFI?
- obtain information that the requesting party cannot obtain through research, document review, or other reasonable means.
- for an owner, architect, contractor, or other party to request information from each other during construction
- if it concerns a site or construction condition, the sender may provide a recommended solution, including cost and/or schedule considerations
What are are some key commissioning activities that occur during the construction and post-construction phases?
- reviews all contractor submittals during the construction phase
- carries out and documents system verification checks during the construction phase, noting any deficiencies that need to be corrected and retested
- conducts and documents the training of operations and maintenance staff during the project closeout after all systems checks are completed and accepted
Based on AIA A201 Article 3.2.1, who is required to visit the site and become generally familiar with the conditions under which the work is to be performed.
the contractor
True or False?
Based on AIA A201 Section 2.5, if the contractor after 10 days from being notified of non-conforming work, the owner may remedy the work at the cost to the contractor?
True
Section 2.5 -Owners Right to carry out work