Chapter 13 Flashcards

1
Q

Material Requirements Planning (MRP)

A

activity that determines the ordering of dependent-demand items (components of assembled products).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

MRP II

A

second generation MRP, adds broader scope by linking sales and operations planning, MPS, MRP, CRP, and detailed scheduling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Capacity Requirements Planning (CRP)

A

uses the MRP shop order releases and operations times and routings to determine the capacity requirements from each work centre.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Dependent Demand

A

D that depends on the production schedule for the finished goods

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 3 MRP Inputs

A
  • Master Production Schedule
  • BOM
  • Inventory Records
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Low-Level Coding

A

restructuring the BOM so that multiple occurrences of the same component all coincide with lowest level at which said component occurs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

MRP Processing

A

“explodes” end item requirements specified by the master schedule into time-phased requirements for assemblies, parts, and raw materials using the BOM offset by lead times. Figure 13-8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Gross Requirement

A

Total expected demand for an item or raw material in a time period (w/o regard to amount on hand).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Scheduled Receipt

A

open order scheduled to arrive from a vendor or shop floor in the beginning of a period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Projected on-hand

A

amount of inventory that us expected to be on hand at beginning of time period. scheduled receipt + any ending inventory expected from last period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Net requirement

A

actual amount needed in a time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Planned-order receipt

A

quantity planned to be received in the beginning of a period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Planned-order release

A

Quantity planned to be released in the beginning of a period (planned-order receipt offset by lead time).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Pegging

A

MRP processing in reverse - identifying immediate parent items that have generated a given set of requirements for an item such as D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

2 systems used to update MRP records

A
  • Regenerative
  • Net-change
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Regenerative System

A

compiles all changes that occur within the time interval and periodically updates the system.

14
Q

Net-Change System

A

production plan is modified to reflect changes as they occur

if some defective purchased parts had to be returned to a vendor, manager can enter this info into the system right when it becomes known.

only changes are exploded through the system, the entire plan is not regenerated.

15
Q

Regenerative vs Net-Change

A

Regenerative is better for stable situations. It is disadvantageous, especially in situations where changes are frequent, because there is a time lag between receiving info and updating the system.

16
Q

MRP System Nervousness

A

a small change in requirement of an item at the top of the product structure tree can have large effects on items down the tree.

17
Q

Back-flushing

A

exploding an end item’s BOM periodically to determine the quantities of the components that must have been used to make the quantity of the item

18
Q

Primary Reports

A
  1. Planned-order schedules
  2. Order releases
  3. Changes to scheduled receipts
19
Q

Secondary Reports

A
  1. Performance-control reports
  2. Planning reports
  3. Exceptions reports
20
Q

Planning Bill

A

when end products only have minor differences (such as colour), they can be combined into an artificial product to simplify planning process

21
Q

Modular Bill

A

used to reduce the # of BOMs when a product consists many modules, each with a few options.

22
Phantom Bill
for items that are usually not kept in inventory. E.g., suppose that pedals of a specific bike are assembled outside the bike assembly line. A phantom bill is created for the components needed to assemble a pedal.
23
Distribution Resource Planning (DRP)
planning method that determines time-phased replenishment schedules between a manufacturer's facility and distribution centres (DCs), or between a DC and retail stores.
24
Capacity Requirements Planning (CRP)
process of determining detailed capacity requirements of MRP calculation on page 511
25
Manufacturing Resource Planning (MRP II)
MRP expanded into broader system for planning and scheduling. sales and operations planning - MPS - MRP - CRP
26
Load Reports
Department or work centre reports that compare known and expected future capacity requirements with capacity availability.