Chapter 16 Flashcards

North Carolina Mechanics' Lien Law (4 cards)

1
Q

“Any person who performs or furnishes labor or professional design or surveying services or furnishes materials or furnishes rental equipment” and who contracted directly with the owner has lien rights against the property where the construction project was performed. This specifies whom?

A

The person entitled to a Mechanics’ Lien

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How many days must a claim be filed within the last date that labor or materials were furnished?

A

120 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Where must all claims of lien be filed?

A

Clerk of the Superior Court in each county where the property subject to the claim of lien is located.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A lawsuit to foreclose on the lien must be filed within ______ days after the lienor last provided materials or labor for the construction project.

A

180

How well did you know this?
1
Not at all
2
3
4
5
Perfectly