Chapter 16 Flashcards

(13 cards)

1
Q
  1. JIT can be used in:
A

d. All of these settings are appropriate for JIT.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. Which of the following is NOT an element of just-in-time manufacturing?
A

b. to increase queue lengths

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. Inflexible or unreliable processes that cause organizations to produce goods before they are required are called:
A

c. overproduction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Scrap or rework are examples of the JIT waste recognized as:
A

a. defects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. In the water and rocks analogy for JIT:
A

b. water represents inventory.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. A kanban can be:
A

d. All of these can be kanbans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. In a two-card kanban system:
A

c. a downstream station pulls finished material out of a production area.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. In a single-card kanban system:
A

a. the single card is the production card.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Liversuch Industries uses a kanban system to manage production of the J-15 sub-assembly. They have an hourly demand for 250 units and use containers that can hold 50 units each. It takes 90 minutes to fill and move a container of parts to the right place on the J-15 line that is currently rated at a 20% safety factor. How many production cards are needed?
A

c. 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. Livermore Industries uses a kanban system to manage production of the KR-9 sub-assembly. In a ten hour day they use 1500 units and use containers that can hold 50 units each. It takes 45 minutes to fill and move a container of parts to the right place on the KR-9 line that is currently rated at a 15% safety factor. How many production cards are needed?
A

a. 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. Livernonions Industries uses a kanban system to manage production of the BR-549 sub-assembly. In an eight hour day they use 900 units and use containers that can hold 30 units each. It takes 120 minutes to fill and move a container of parts to the right place on the BR-549 line that is currently rated at a 15% safety factor. How many production hours of inventory are needed?
A

d. 2.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. Which of the following statements regarding supply chain synchronization using kanbans is best?
A

b. For the system to work properly demand rates must be relatively stable and interruptions must be minimized

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. When using MRP and kanban together:
A

d. the number of kanbans is recalculated from the MRP system’s order changes throughout the horizon.