Chapter 2 Project Management Flashcards

1
Q

Project management

A

A systemized, phased approach to defining, organizing, planning, monitoring, and controlling projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Program

A

An interdependent set of projects that have a common strategic purpose

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Activity

A

The smallest unit of work effort consuming both time and resources that the project manager can schedule and control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

WBS work breakdown structure

A

A statement of all work that has to be completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Network diagram

A

A network planning method designed to depict the relationships between activities that consists of nodes and arcs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Critical path method

A

A network planning method to optimize the critical path to reduce total project time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Precedence relationship

A

A relationship that determines a sequence for undertaking activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Project

A

Interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of resources