Chapter 3 Flashcards

(55 cards)

1
Q

finish day/date

A

The time that task is scheduled to be

finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

concurrent task

A

If tasks can be completed at the same
time they are said to be concurrent, or
parallel.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

critical path

A
A series of events and activities with no
slack time. If any activity along the
critical path falls behind schedule, the
entire project schedule is similarly
delayed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Project planning

A

Project planning includes identifying
project tasks and estimating completion
time and costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Qualitative risk analysis

A

Evaluating risk by estimating the
probability that it will occur and the
degree of impact.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Microsoft Project

A

A powerful, full-featured program that
holds the dominant share of the project
management software market.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Brooks’ Law

A
This interesting concept was stated by
Frederick Brooks, Jr. an IBM engineer,
who observed that adding manpower to
a late software project only makes it
later
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

event

A

An event, or milestone, is a reference
point that marks a major occurrence.
Events are used to monitor progress
and manage a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

worst-case estimate

A

The most pessimistic outcome is called

the worst-case estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

task

A

A task, or activity, is any work that has a
beginning and an end, and requires the
use of company resources including
people, time, and/or money. Examples
include conducting a series of
interviews, designing a report, selecting
software

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Critical Path Method (CPM)

A
The Critical Path Method (CPM) was
developed by private industry, and
shows a project as a network diagram.
The activities are shown as vectors, and
the events are displayed graphically as
nodes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

activity

A

An activity, or task, is any work that has
a beginning and an end, and requires
the use of company resources including
people, time, and/or money.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

task name

A

A brief descriptive name for a task,
which does not have to be unique in the
project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

structured walk-through

A
A review of a project team member’s
work by other members of the team.
Generally, systems analysts review the
work of other systems analysts, and
programmers review the work of other
programmers, as a form of peer rev
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

duration

A

The amount of time it will take to

complete a task.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Project scheduling

A
Project scheduling involves the creation
of a specific timetable to facilitate
completion of a project. Scheduling also
involves selecting and staffing the
project team and assigning specific
tasks to team members.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

network diagram

A

A PERT chart also is referred to as a

network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

weight

A

Weight is an important value that
managers add to estimates so they can
be analyzed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

dependent tasks

A

A task is said to be dependent when it
has to be completed in a serial
sequence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Program Evaluation Review Technique

PERT

A
The Program Evaluation Review
Technique (PERT) was developed by the
U.S. Navy to manage very complex
projects, such as the construction of
nuclear submarines.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Project monitoring

A

Project monitoring requires guiding,
supervising, and coordinating the
project team’s workload.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Risk identification

A

Listing each risk and assessing the

likelihood that it could affect a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

PERT/CPM

A
The Program Evaluation Review
Technique (PERT) was developed by the
U.S. Navy to manage very complex
projects, such as the construction of
nuclear submarines. At approximately
the same time, the Critical Path Method
(CPM) was developed by private
24
Q

task pattern

A
A logical sequence of tasks in a work
breakdown structure. Task patterns can
involve sequential tasks, multiple
successor tasks, and multiple
predecessor tasks.
25
task box
``` In project management, a task box is a component of a PERT/CPM chart that contains important scheduling and duration information about a task. Each task in a project is represented by its own task box in the PERT/CPM chart. ```
26
project triangle
The three major components of a project: cost, scope, and time. A project manager tries to find the optimal balance among these factors.
27
milestone
A milestone, or event, is a reference point that marks a major occurrence. Milestones are used to monitor progress and manage a project.
28
task group
In task groups, each task represents | several activities.
29
Risk management
The process of identifying, evaluating, tracking, and controlling risks to minimize their impact.
30
design reviews
``` A design review, or structured walkthrough, is a review of a project team member’s work by other members of the team. Generally, systems analysts review the work of other systems analysts, and programmers review the work of other programmers ```
31
open source
Software that is supported by a large | group of users and developers
32
Testing reviews
``` A testing review, or structured walkthrough, is a review of a project team member’s work by other members of the team. Generally, systems analysts review the work of other systems analysts, and programmers review the work of other programmers ```
33
Project reporting
Project reporting tasks include regular progress reports to management, users, and the project team itself.
34
risk response plan
``` A proactive effort to anticipate a risk and describe an action plan to deal with it. An effective risk response plan can reduce the overall impact by triggering a timely and appropriate action ```
35
predecessor tasks
Often, two or more concurrent tasks depend on a single prior task, which is called a predecessor task.
36
work breakdown structure (WBS)
Breaking a project down into a series of | smaller tasks.
37
Gantt chart
``` A horizontal bar chart that illustrates a schedule. Gantt charts were developed many years ago by Henry L. Gantt as a production control technique and still are in common use ```
38
project coordinator
``` The project coordinator handles administrative responsibilities for the development team and negotiates with users who might have conflicting requirements or want changes that would require additional time or expense. ```
39
risk management plan
``` Includes a review of the project’s scope, stakeholders, budget, schedule, and any other internal or external factors that might affect the project. The plan should define project roles and responsibilities, risk management methods and procedure ```
40
code reviews
``` A code review, or structured walkthrough, is a review of a project team member’s work by other members of the team to spot logic errors. Generally, systems analysts review the work of other systems analyst ```
41
best-case estimate
The most optimistic outcome is called | the best-case estimate.
42
successor task
Each of the concurrent tasks of a predecessor task is called a successor task.
43
Slack time
``` The slack time for an event is the amount of time by which an event can be late without delaying the project. The slack time for an event is the difference between its latest completion time (LCT) and earliest completion time (ECT). ```
44
risk
An event that could affect the project | negatively
45
task ID
A number or code that uniquely | identifies a task
46
person-day
The amount of work that one person | can complete in one day.
47
quantitative risk analysis
Evaluating risk in terms of the actual impact in terms of dollars, time, project scope, or quality.
48
probable-case estimate
The most likely outcome is called a | probable case estimate.
49
start day/date
The time that a task is scheduled to | begin.
50
bottom-up technique
A bottom-up technique analyzes a large, complex project as a series of individual tasks, called project tasks
51
dependent task
A task is said to be dependent when it has to be completed in a serial sequence
52
gateway
``` (1) In business processing modeling notation, a fork in the process, allowing the flow to go one way or another. (2) A router or other network device used to connect to a larger, dissimilar type of network, such as the Internet. ```
53
predecessor task
Often, two or more concurrent tasks depend on a single prior task, which is called a predecessor task
54
project creep
The process by which projects with very general scope definitions expand gradually, without specific authorization.
55
project management
The process of planning, scheduling, monitoring, controlling, and reporting upon the development of an information system.