Chapter 4 Flashcards

1
Q

What are the 5 components included in the project plan?

A
  • Requirement phase,
  • draft requirements,
  • final requirements,
  • WBS, and
    -other activities.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How are activities developed in a project plan?

From L-C S and D

A

Activities are developed from life cycle stages and deliverables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of listing activities in a sequential order?

A

To show work tasks and how they must be accomplished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define ‘Contingency activities’ in project management.

A to M O for on-time C

A

Activities to mitigate obstacles for on-time completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Explain ‘Finish to start’ dependency in project management.

A

One task must finish before the next one can start.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How can the duration of a contingency event be calculated?

A

Duration of Contingency Activity x Probability of Occurrence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the role of a Change Review Board (CRB) in projects?

A

Acts as a clearinghouse for project changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why is it important to record everything in writing during project management?

A

For documentation, clarity, and accountability purposes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What roles should be represented in a Project Team?

A

At least one from each functional area.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why is it necessary to issue frequent status updates for stakeholders and management?

A

To keep them informed and engaged in the project progress.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a Commissioning Plan?

A

Details how the system is installed, upgraded, and commissioned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When does commissioning occur in projects?

A

During new projects and upgrade projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the purpose of Standards Compliance Testing (SCT) in commissioning?

A

To ensure organizational and government standards are met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the four main ways to test a system?

A

Pre-Delivery Test,
Site Acceptance Test,
Operational Reliability Test,
Post-Implementation Test.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the ideal system availability percentage?

A

System availability of 99.99%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How is operational availability (OA) calculated?

A

Tm/(Tm + Td) x 100 = OA, where Tm = Total Test Duration Time, Td = Total System Downtime.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the duration of a typical warranty period?

A

12 to 24 months, typically 12 months from final implementation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What should a warranty include for hardware or software failures?

A

Repair, correction, or replacement of failed components.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What should vendor’s warranty include related to replacement parts?

A

Vendor should keep 5% of system cost as replacement parts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is expected in terms of service response times during the warranty period?

A

Service response times of four hours or less.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What key documents are produced in the planning stage of a project?

A

Critical business case documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the basis for approving a business case?

A

Return on Investment (ROI).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What does the Return on Investment (ROI) calculation determine?

A

Amount of revenue generated or potential loss reductions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What types of assets are identified during the assessment stage?

CA and
SA

A

Critical assets and supportive assets.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What tool can aid in assessing vulnerabilities in an organization?
Vulnerability Self-Assessment Tool (VSAT).
26
What are three aspects of risk that need to be considered during planning? RT P of O AND L P
Risk type, probability of occurrence, and loss potential.
27
What are two objectives of the requirements document during the planning phase?
Identify reasons for security measures, and identify critical success factors, and more.
28
What are the three Phase One Planning deliverables for a project? R A report PM BE
• R A→ Risk assessment report • P M → Procurement method • B E → Budgetary estimates
29
What does the Design and Estimating phase involve in a project?
Documenting processes to support procurement of equipment and services.
30
Why is considering the design of an integrated system important?
To effectively defend against threats, vulnerabilities, and potential losses.
31
What 7 steps should an organization follow to promote order and efficiency at a bidder's conference? PA IG MP with O DPP CST Q and A and PM
Present agenda, identify guidelines, match project with objectives, discuss procurement process, conduct site tour, Q&A session, and present minutes.
32
What four criteria should be evaluated when analyzing potential bidders?
Compare against main features, review technological assets, assess life cycle cost, and evaluate strengths based on competency criteria.
33
What 11 questions should be asked when analyzing a bidder's proposal? PO F and Q C, D and M MA, CR and SOP I, CF, P-I support.
project objectives, feasibility and qualifications, capabilities, deliverables, and milestones, manpower allocation, cost reduction, and SOP inclusion, cultural fit, post-implementation support.
34
What 8 quality assurance factors should be considered when selecting a vendor? EQ co and pa av Na ac and Cer Te, Cu and Ca and ES and P of T
Equipment condition and parts availability national accreditation and certifications technology currency and capabilities Emergency service and proximity of technicians
35
What 6 things should an organization consider to determine the issuance of a contract when selecting vendors?
Consider life cycle cost, integrator's financial stability, past references, vendor shortlist reduction, finalist interviews, and minor deficiency mitigation.
36
What are the 4 objectives of the procurement phase in a project cycle? BC T and C Ev R, I and DD results Co Iss
• BC → Bidders conference (Holding a bidders conference) • T and C Ev → Technical and cost evaluations (Conducting technical and cost evaluations) • R, I and DD results → Reviewing, interviewing, and due diligence results • Co Iss → Contract issuance (Issuing a contract)
37
What are the 3 core elements of a Physical Protection System (PPS)? AE OE SSE
Architectural elements, operational elements, security system elements (technology).
38
What are the three types of measures in PPS?
Preventative measures, corrective measures, and detective measures.
39
What are the five steps in ensuring a properly installed PPS? A and P C a CD C C D B and N In and Te
Assess and plan, create a conceptual design, complete construction documentation, build and negotiate, install and test.
40
What are the six phases in the PPS life cycle? Pl D and E P In/op//tr Co/wa and Ma/ev/rep
1. Planning, 2. design and estimation, 3. procurement, 4. installation/operation/training, 5. commissioning/warranty, 6. maintenance/evaluation/replacement.
41
Why is flexibility important in a PPS?
Adversarial tactics and threats often change, requiring adaptations in the system design.
42
What should be considered for disk space requirements in a video surveillance system?
Should be based on system parameters with 50% additional storage over original design.
43
Why is it important to update documentation when operational procedures are revised?
To reflect the revision date and ensure information accuracy.
44
What topics (4) should be covered in a training program for physical protection systems? S A A A I R IT F and……more
System administration, alarm assessment, incident response, IT functions, and more.
45
What could happen if personnel dealing with new technology in systems are poorly trained?
Increased costs, Loss of benefits from technology, and potential danger.
46
Why should training instructors for physical protection systems have certifications and credentials?
To ensure proper knowledge and expertise in training personnel.
47
What are some (5) examples of issues that may arise with a training program? Lo Co Qu of St Sc and Pe In
• Lo for Location • C o for Cost • Qu of St - for Quality of Staff • Sch - Scheduling • Pe In - Personnel Involved
48
What 4 documents should be obtained from a training phase for physical protection systems? TM L P Ev Sch, and more.
Training materials, lesson plans, evaluations, schedules, and more.
49
What is the process of ensuring system compliance with operational requirements? C of the system through De In Te and Op
Commissioning of the system through design, installation, testing, and operation.
50
What are some obstacles (3) that can hinder project activities? E T P B and L of M
Employee turnover, procurement bottlenecks, Lack of materials, etc.
51
What are the 3 key pieces of information included in a formal change control process?
Date requested, Change Request number, and Who requested the change, etc.
52
In what 2 ways can project managers prevent management from losing interest in a project?
- Revalidating sponsorship and - improving communication of successes.
53
What steps can be taken to improve enthusiasm among team members?
Reinforce project objectives, assess leadership style, and observe team dynamics, etc.
54
What are the advantages - 4 - of using the project management process?
Efficient and provides improved: communication, planning, estimates, and control.
55
Why is it important to avoid the '99 percent completion syndrome' in project management?
A project should not be closed until 100 percent completion.
56
What is the final step in the project management process after project closure?
Disbanding the project team.
57
What are the four main types of bonds in a construction project?
1) Bid bonds, 2) Payment bonds, 3) Performance bonds, 4) Ancillary bonds.
58
What do bid bonds guarantee in a construction project?
A bid bond is a legal agreement that guarantees a contractor will fulfill their obligations on a project.
59
What do payment bonds provide during a project?
Payment guarantee to suppliers of goods or services.
60
What do performance bonds guarantee in a construction project?
Contractor's completion of project requirements within terms and timelines.
61
What do ancillary bonds support in a construction project?
Tasks/items within performance requirements not covered by performance bonding.
62
What should an initial budget be within if the estimator is experienced?
10 percent of final bid prices.
63
What is the purpose of budgetary estimates in PPS implementation?
To include a 10 percent to 20 percent contingency.
64
What is the estimated percentage of total project cost for installation in PPS projects?
40 percent to 50 percent.
65
What are the major types of procurement methods in the PPS cycle?
Request for Proposal (RFP), Invitation for Bids (IFB), Sole Sourcing (SS).
66
Who provides specific requirements in the Request for Proposal (RFP) process?
The customer, not the vendor.
67
What elements should be included in bid package procedures?
Operating and response procedures.
68
What are the design criteria for physical protection systems? Ass and Bu Co, Ca, Cu, Fe, im, L-c C Ma, Mo Op Pe, Qu, Qu Re Pr and Sp Fe
Assessment and Budget, Codes, capacity, culture, features, image, life-cycle costs, maintenance, monitoring, operations, performance, quality, quantity, response procedures, special features.
69
What 4 documents are included in the bid package during the design phase?
Bidders Instructions, Design Specifications, Drawings and Schedules, and Hardware Schedules.
70
What 3 aspects should a successful design of a physical protection system incorporate? AA SS and OA
Architectural aspects, security systems, and operational aspects.
71
What are some examples of documents that professionals should submit as part of their bid package for security design? PD E D D D R D and H S
Plan drawings, elevation drawings, detail drawings, riser diagrams, and hardware schedules.
72
What should be considered when designing operating procedures? Ass R P P C and R
Assessment, response procedures, prevention, control, and recovery.
73
What are the three elements in a model specification for security system design? G P E
General, Product, Execution.
74
What is a Surety Bond in the context of security system design?
A three-party instrument providing coverage for failure to live up to contractual agreements.
75
What are the 6 deliverables from the maintenance, evaluation, and replacement phase? TG MP R, U, OC and R S
Troubleshooting Guides, Maintenance Procedures, Records, Upgrades, Operating Costs, and Replacement Studies
76
What are the two main types of system maintenance mentioned?
Preventative Maintenance and Remedial Maintenance
77
What should the organization never have to pay for in terms of maintenance contracts?
The first year of equipment service or when any component is still under warranty
78
What should the single-maintainer philosophy aim to prevent?
Avoiding multiple vendors blaming each other over encountered issues
79
What are 7 considerations for deciding to replace a system mentioned in the notes? Br and H M C, St and Se Un, R R and N T, and L-C C A
Breakdowns and high maintenance costs, standardization and service unavailability, regulatory requirements and new technologies, and life cycle cost analysis
80
What does a project entail based on the notes provided? A TP with a UP, EGs, Re and a QRA
A temporary process with a unique purpose, explicit goal, resources, and a qualified risk analysis
81
What 4 activities are involved in Phase Four of the installation process? SP S and Su I, S A and S C
Site preparation, system and subsystem installation, system acceptance, and system commissioning.
82
What is the purpose of training during the installation phase?
To train everyone involved in operating or maintaining the system.
83
What responsibilities does the installer have regarding false alarms?
To ensure false alarms and their causes are minimized.
84
What 4 criteria must the installer consider for security system installation?
Conduit installation, wiring terminations, battery backup, and line supervision, etc.
85
What should be the minimum battery backup duration for security systems?
Four hours.
86
What is the maximum time delay for accessing intrusion detection system keypads?
15 seconds to disarm, 240 seconds maximum for entry.
87
What are the three elements essential for successful project management? Pirates chart courses
Think of a pirate navigating the seas—they must Plan their route, Coordinate with their crew, and Control the ship to reach their treasure (or avoid danger).
88
What are the constraints a project manager must balance?
Scope, Cost, Schedule.
89
What 3 key skills should a project manager possess? GM, L and TB
General management, Leadership, and Team building.
90
Why are weekly status meetings for the project team essential?
To discuss progress, status, and future goals.
91
What 5 things does the Project Scope Document include? ES O S C and R
Executive summary, Objectives, Scope, Costs, and Risks.
92
What are the four basic stages of a project?
Feasibility, Development, Execution, and Closeout.
93
What tools does a project manager use according to the notes? T, S, D
Training, Software, Determination.
94
What is the importance of documenting during meetings?
To ensure discussed points are captured.
95
What is the significance of a 'Lessons Learned Report'?
To document issues and improvements for future projects.
96
What is the correlation between project stages and lifecycle phases shown in a figure?
Feasibility matches Planning, Development matches Design and Estimating.
97
What is the primary difference between sole source procurement and IFB procurement?
Sole source uses only one vendor, while IFB seeks the lowest price from multiple vendors.
98
What 5 criteria are considered when selecting qualified vendors for bidding on a project?
Licensing requirements, financial stability, necessary personnel, service history, and relationships with manufacturers.
99
What is the purpose of a Request for Information (RFI) in the procurement process?
To gather information on the capabilities of prospective bidders and prequalify them.
100
How can an organization facilitate (3 ways) a fair evaluation of vendor proposals?
By using predetermined criteria, assigning weights, and establishing a balanced evaluation method.
101
What role does a bidder's conference play in the procurement process?
To present potential bidders with installation problems and organization's objectives.