CHAPTER 7: MANAGING PROJECT COSTS Flashcards

1
Q

ACTUAL COST (AC)

A

Actual amount of money spent to date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Analogous Estimating

A

Based on historical information cost of project is predicted. Least reliable, top down estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

BUTTOM UP ESTIMATING

A
  • Starts from Zero
  • accounts for each component of the WBS and sums them up
  • most time consuming and reliable
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BUDGET ESTIMATE

A
  • broad, often top down
  • -10 to +25 percent range
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

COMMERCIAL DATABASE

A
  • uses a data base to estimate cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CONTINGENCY RESERVE

A
  • allowance to account for overruns in costs
  • used at pms discretion and with management’s approval to counteract overruns
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

COST AGGREGATION

A
  • Cost parallel to WBS WP
  • Each WBS WP is aggregated to their control acc
  • each controll acc is aggregated to the sum of project costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Baseline

A
  • time lapse of when money is to be spend in relation to cumulative value of the work completed in the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

COST BUDGETING

A
  • applies cost estimates over time
  • cost aggregation assigning dollar amounts for each scheduled activity or each WP in the WBS
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

COST CHANGE CONTROL SYSTEM

A
  • system examines any changes associated with scope change, cost of materials or other resources
  • impact on overall project costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

COST MANAGEMENT PLAN

A
  • plan that dictates how cost variances will be managed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

COST OF POOR QUALITY

A
  • Cost of non conformance to quality
  • e.g. rework, defect repair, loss of life
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

COST OF QUALITY

A
  • money spend to attain expected level of quality
  • e.g. training, testing, safety precautions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

COST PERFORMANCE INDEX (CPI)

A
  • Measures financial performance
  • CPI = EV/AC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

COST VARIANCE (CV)

A

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

DEFINITIVE ESTIMATE

A
  • accurate, late in planning phase
  • buttom up
  • based on WBS
  • Variance -5 +10 percent
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Direct costs

A
  • costs attributed directly to project work
  • not shared with other projects
  • e.g. hotels, phone calls etc
18
Q

EARNED VALUE

A
  • physical work done and authorized budget for it
  • percent if BAC that represents actual work completed
19
Q

ESTIMATE AT COMPLETION (EAC)

A
  • forecasting formulas to predict the costs of the project at the time of completion
20
Q

ESTIMATE TO COMPLETE

A
  • predicts how much funding the project will require to be completed
  • 3 variations of formula based on project conditions
21
Q

FIXED COSTS

A
  • remain constant throughout the life of the project
  • e.g rental fee, consultant fee etc
22
Q

FUNDING LIMIT RECONCILIATION

A
  • approach of managing cash flow against project deliverables based on schedule, milestone accomplishment or data constrains
23
Q

INDIRECT COSTS

A
  • costs representative for more than one project
  • PM software license, utilities for company etc
24
Q

KNOWN UNKOWNS

A
  • Event that will likely happen
  • but when and to what degree is unknown
25
LEARNING CURVE
- assumption that the cost per unit decreases the more units are produced
26
OLIGOPOLY
- tight market - action of one vendor affects action of others
27
OPPORTUNITY COST
- cost of opportunity that is refused to realize an opposing opportunity
28
PARAMETRIC ESTIMATING
- using parametric model to extrapolate costs needed for a project - e.g. cost per hour, cost per unit
29
PLANNED VALUE (PV)
- work scheduled and budget authorized to accomplish that work - percentage of BAC reflecting where project should be at a given point of time
30
PROJECT VARIANCE
- discovered at project completion - VAR = BAC - AC
31
REGRESSION ANALYSIS
- statistical approach predicting future values - based on historical values
32
RESERVE ANALYSIS
- included in budget but not as cost baseline - revmserve for unknown unkowns
33
ROUGH ORDER MAGNITUDE
- rough estimate used during initiating processes and top down estimates - -25 to +75 percent of range
34
SCHEDULE PERFORMANCE INDEX (SPI)
- SPI = EV/PV
35
SCHEDULE VARIANCE
Difference between earned and planned value - SV = EV - PV
36
SINGLE SOURCE
- many vendors existing - prefer to work with selected vendor
37
Sole source
- only one vendor existing for what I need - e.g. ASML
38
Sunk costs
- money already invested into project
39
TO COMPLETE PERFORMANCE INDEX (TCPI)
- formula to forecast likely hood of project achieving its goals based on what is happening - meet BAC? TCPI = (BAC - EV)/(BAC-AC) - Meet newly created estimate? TCPI = (BAC-EV)/(EAC-AC)
40
VARIABLE COSTS
- costs that change based on conditions applied in the project
41
VARIANCE
- difference between what was expected and what was experienced
42
VARIANCE AT COMPLETION (VAC)
- predict variance project will likely have based on current condition - VAC = BAC - EAC