Chapter 7 - Project Schedule Management Flashcards

(44 cards)

1
Q

Schedule Management

A

Includes the processes required to manage the timely completion of the project
Creating the schedule baseline, project schedule, and ensuring the project stays on schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Plan Schedule Management

A

Inputs: project management plan, project charter, enterprise environmental factors, organizations process assets
Tools & techniques: expert judgement, data analysis, meetings
Output: Schedule Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Schedule Management Plan

A

Document how the project defines the activities, sequences the activities, estimates the resources, developed the schedule, and controls the schedule to ensure the project stays on schedule
Measure the schedule and how to fix it if there are any variances from the schedule baseline
Part of the Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define Activities

A

Taking the work packages on the WBS and breaking them down into activities
The specific work that will need to get done by the project team to create the deliverables
More detailed than work packages
Stored in the activities list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define Activities Process

A

Inputs: project management plan (schedule management plan - list the steps to define the activities, how to decompose each work package into activities, scope baseline), enterprise environmental factors, organizational assets
Tools & techniques: decomposition (breaking down the work into activities), rolling wave planning (progressive elaboration), expert judgement (using SMEs to help decompose the work packages)
Outputs: activity list (list of all scheduled activities on the project), activity attributes (detailed information about each activity), milestones list (all project or phase milestones - major accomplishment or event), change request, Project Management Plan updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Sequence Activities

A

Take the list of activities and put them in the order that you will perform them
Shows the relationship between each activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Sequence Activities Process

A

Inputs: project management plan (schedule management plan), project documents (activity list, activity attributes, milestone list, assumption log), enterprise environmental factors, organizational process assets
Tools & techniques: precedence diagraming method (PDM), dependency determination, leads and lags, project management information system
Outputs: project schedule network diagrams, project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Precedence Diagraming Method (PDM)

A

Technique that is used to build a sequence using the activities
Activity-on-node (AON): boxes are activities, the numbers above them represent durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Relationships

A

Finish-to-start (FS): most frequent, finish A then you can start B, Activity A is the predecessor and activity B is the successor
Finish-to-finish (FF): activities need to finish at the same time, activities A and B must be done simultaneously
Start-to-start (SS): activity A must start before Activity B can start
Start-to-finish (SF): activity B cannot finish until activity A has started - rarely used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Dependency Determination

A

Mandatory: hard logic or hard dependency, you have to finish one activity to start the next activity
Discretionary: soft logic, activities do not need to get done in a specific order
External: activities are dependent on activities outside the control of the project team (permits)
Internal: activities are dependent on activities within the control of the project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Leads & Lags

A

Show an overlap or delay in schedule
Lead: an overlap between activities
Lags: delays between activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Estimate Activity Duration Process

A

Inputs: project management plan (schedule management plan and scope baseline), project documents (activity list, activity attributes, assumption log, milestone list, resource calendars (availability of resources), risk register, resource break down structure (hierarchical break down of resources by their categories and types), lessons learned register, project team assignment, resource requirements), enterprise environmental factors, organizations process assets
Tools & techniques: expert judgement, analogous estimating, parametric estimating, three-point estimating, bottom-up estimating, data analysis, decision making, meetings
Outputs: duration estimates, basis of estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Analogous Estimating

A

Top-down
Relies on historical information to assign the current t duration to the activities
Quick to do, but less accurate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Parametric Estimating

A

Uses mathematical algorithm to calculate cost or duration
Based on historical data and variables
Can be very accurate if assumptions are correct

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

There-Point Estimating

A

Known as PERT (program evaluation and review techniques)
Optimistic: best case for the activity or least amount of time needed to complete the activity
Most likely (realistic): most likely or realistic case for the activity to be completed
Pessimistic: worst case for the activity or the longest time it would take to complete the activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Beta Distribution

A

PERT
(Optimistic + 4 * realistic + pessimistic) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Standard Deviation

A

Give a range for an estimate
(Pessimistic - optimistic) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Triangular Distribution

A

Average of the 3 numbers
(Optimistic + realistic + pessimistic) / 3

19
Q

Bottom-up Estimating

A

Most accurate method to estimate cost or time
Break down all the work required to the lowest
Evens and then aggregating the work back up to find the total duration

20
Q

Reserve Analysis

A

Adding extra time to an activity because of risk
Reserves are extra time added in case a risk arises

21
Q

Duration Estimates

A

The main output will be the duration estimates for each individual activity.
Numerical estimate, good idea to include ranges
Plus/minus 3 days

22
Q

Basis of Estimates

A

How the estimates were developed and their ranges
It can also include all assumptions and constraints made to create the estimate

23
Q

Develop Schedule

A

Process of creating the schedule baseline and project schedule
Iterative process that will be done throughout the planning phase
Plan schedule management > define activities > sequence activities > estimate activity resources > estimate activity durations > develop schedule

24
Q

Develop Schedule Process

A

Inputs: project management plan (schedule management plan), project documents (activity list, activity attributes, assumption log, milestone list, duration estimates, basis of estimates, resource calendars, risk register, response breakdown structure, lessons learned register, project team assignment, resource requirements, project schedule network diagrams), agreements, enterprise environmental factors, organizational process assets
Tools & techniques: schedule network analysis, critical path method, resource optimization techniques (resource leveling and resource smoothing), data analysis, leads and lags, schedule compression (coaching and fast-tracking), project management information system, agile release planning
Outputs: schedule baseline, project schedule (bar chart - gantt charts, milestone charts, project schedule network diagrams), schedule data, project calendars, change requests, project management plan updates, project documents updates

25
Critical Path Method
Longest path through a network diagram Know which activities, if delayed, will affect the project schedule Any delays in the critical path will delay the project Activities on the critical path are considered high risk activities, have no float
26
Resource Leveling
Resources are limited or over allocated. You will need to adjust the schedule and move the activities to be sequential rather than parallel. Will lengthen the critical path.
27
Resource Smoothing
Used to ensure the critical path does not change. It will allow activities to change if there is a float. Doesn’t affect the critical path like resource leveling does.
28
Data Analysis
What-if scenarios and simulations known as Monte Carlo Simulation What would happen if you run two parallel activities or add more resources to these activities
29
Schedule Compression
Crashing: add more resources to complete activities faster (more painters or a paint gun instead of brushes); increases cost and may lead to risk Fast-tracking: do activities in parallel rather than sequentially; get done quicker but increase risk
30
Agile Release Planning
A set of iterations that will help to create a product that would be given to customers for feedback.
31
Schedule Baseline
Part of the project management plan, can only change with an approved change request Measures the progress of the project Contains baseline start and end dates
32
Project Schedule
Includes start and end dates for all activities on the project Very detailed Bar chart (gantt chart) Milestone charts - present to senior management Project schedule network diagrams - durations and sequence of every activity
33
Control Schedule
Controlling the project work to ensure it will finish on the schedule baseline Daily process of keeping your project on track Look at the project management plan (planned work) and the work performance data (actual work) to determine if there are any variances
34
Control Schedule Process
Inputs: project management plan (schedule management plan and schedule baseline, scope and cost baselines, respective management plans), project documents (project schedule, schedule data, resource calendars, lessons learned register, project calendar), work performance data, organizational process assets Tools & techniques: data analysis (earned value analysis, iteration burn down chart, performance reviews, what-if scenarios), critical path method, project management information system, resource optimization techniques, leads and lags, schedule compression Outputs: work performance information, schedule forecasts, change requests, project management plan updates, product documents updates
35
Earned Value Analysis
A series of formulas that are used to numerically analyze the performance of a project’s related cost and time.
36
Iteration Burndown Chart
Generally used on agile projects Y-axis shows work still to be completed and the x-axis shows the duration Ideally a straight line downward from y-axis to x-axis
37
Performance Reviews
Compare the planned work and actual work performed
38
What-if Scenarios
Used to help fix the schedule or recognize it Help the project manager to optimize the best schedule and determine what risks may affect it
39
Agile and Hybrid Project Scheduling
Estimate how long it will take to complete all the user stories T-shirt sizing: high-level estimate where you assign a t-shirt size to each user story (ES - XL) Based on a relative scale where each size corresponds back to the amount of work required for each user story Planning poker: playing cards with a set of numbers on them (Fibonacci sequence) that are relative based on size. The numbers are: 1,2,3,5,8,13,21. Formula: start with 1 + 2 = 3; 2 + 3 = 5; 3 + 5 = 8; 5 + 8 = 13; etc. Read a user story and team assigns a playing card to it
40
Agile Tools
Cumulative flow diagram: track how much work is done out of the total Team velocity: how much work can get done in each iteration Burn up chart: shows the amount of work that has been done on the project Burn down chart: shows the amount of work remaining to be down
41
Lead Time
How long something takes to go through the entire process Ready to start-design-coding-testing-done Used with Kanban — go across the entire Kanban board
42
Cycle Time
How long it takes to go through part of a process Coding-testing-done Cycle time = (work in progress) / throughput 60 points of work to do 20 points per week Cycle time = 60/20 = 3 weeks
43
Critical Path Method
The longest time to complete all activities on the network diagram Activities on the critical path have no slack (aka float) Early start (ES): the earliest you can start an activity without delaying the project end date Late start (LS): the latest you can start an activity without delaying the project end date Early finish (EF): the earliest you can finish an activity without delaying the project end date Late finish (LF): the latest you can finish an activity without delaying the project due date Slack = LS - ES or LF - EF
44
Calculate Slack
Forward pass: ES + duration - 1 = EF Backward pass: LF - duration - 1 = LS Forward pass must be done before the backwards pass Slack = LS- ES or LF - LS