Commercial management Flashcards
(37 cards)
What is your understanding of the components that make the cost of the project to a contractor?
Project cost to a contractor includes direct costs (labor, materials, plant), indirect costs (site overheads, preliminaries), and profit margin.
What do you understand by the term working estimate?
A working estimate is a detailed cost forecast used during design development to control and guide project expenditure.
What are the key components of a CVR report in respect to cost/value to date?
Cost/value to date includes all actual costs incurred plus valuations of work completed but not yet paid.
What are the key components of a CVR report in respect to cost/value to complete?
Cost/value to complete estimates the remaining costs needed to finish the project based on current projections.
Explain the CVR process.
The CVR process is a profit and loss statement that measures a projects costs and value during a specified accounting period, which is typically a month. This determines the profitability of a project at a given point in time during the project life cycle. From this, you can assess whether the project is over or under performing against budget.
What do you understand by the term liability?
A liability is a sum of money owed to another company.
How does a liability differ from cost?
Liabilities are in relation to monies owed, whereas cost relates to money spent.
What would you consider before constructing a project cash flow forecast?
Step 1: Calculate income by using the agreed payment schedule set out in the contract
Step 2: Plot when income will be received and map onto a graph
Step 3: For outgoings I would utilise the project’s cost ledger and ensure that any long lead time items are accounted for
Why is the construction of a cash flow forecast so important?
Highlights the movement of income and expenditure into and out of a business over time.
Allows client to identify the funding requirements of a project and the projected flow of cash.
How is wastage calculated?
Wastage is typically calculated as a percentage of material quantities based on historical data and site conditions.
What insurances are required under a contract? How are they included in a tender?
Common insurances include employer’s liability, public liability, and contractor’s all-risk, specified in contract documents and costed in tenders.
What do you understand by the term project budget?
The project budget is the approved financial plan setting the total expenditure limits for the project.
How does the project budget differ from the tender budget?
The tender budget is the estimated cost submitted to win the contract, often refined into the project budget post-award.
What current challenges is Covid and/or Brexit bringing to Commercial Management?
Covid and Brexit disrupt supply chains, delay projects, and create uncertainty in pricing, procurement, and contract terms.
Level 2
ED1SON Alliance Reporting on client certification
How did you ensure your site visits were effectively aligned with programme progress for accurate forecasting?
I would attendance site in the final week of every month to ascertain the activities completed on site.
When attending site I printed a copy of the latest programme and activity schedule to assess the relevant activities.
Level 2
ED1SON Alliance Reporting on client certification
In what format did you present your reports to senior management?
I completed an excel spreadsheet including figures such as period application value, cumulative applied value and expected certification values.
I included narrative against any deltas between applied and expected certification values.
Level 2
ED1SON Alliance Reporting on client certification
How did you tailor them for clarity and decision-making?
When reporting on the level of certification I included concise summary of events based on factual information.
Level 2
ED1SON Alliance Reporting on client certification
What specific indicators did you use to assess the risk of incomplete work affecting client certification?
Due to the fact that the majority of my projects were option A, I used work completion percentages to ascertain whether the activity would be 100% completion by the assessment date, and therefore included within the Client’s assessment.
Level 2
ED1SON Alliance Reporting on client certification
How did you coordinate with the site or project team to validate information included in your payment applications?
I chaired regular meetings with my construction manager and assistant QS to cross-check claimed activities against progress on site.
For any discrepancies I consulted my construction manager to understand the reasons why.
Level 2
ED1SON Alliance Reporting on client certification
What was your approach to managing aged debt to prevent negative impact on commercial forecasting
I kept an up to date register of any aged debt and liaised with the Client’s accounts department on a regular basis to understand when the BACS transfer would be made to my employer.
I obtained narratives from which I was able to advise senior management on the status of the aged debt and when it would be received.
Level 2
ED1SON Alliance
Welfare cabin purchase
- What sources did you use to gather cost data for comparing hire vs purchase of welfare cabins?
I used hire rates from the existing supplier contract and obtained purchase quotations from approved suppliers. I also referenced historical project data to validate costs.
Level 2
ED1SON Alliance
Welfare cabin purchase
- How did you ensure your analysis of overheads (e.g. cleaning and maintenance) was comprehensive and accurate?
I identified all ancillary costs like cleaning and maintenance by consulting site teams and reviewing past expenditure, applying contingencies where needed to capture all overheads.
Level 2
ED1SON Alliance
Welfare cabin purchase
- How did you structure the report to senior management to justify your advice clearly?
The report included an executive summary, detailed cost comparison with overheads, risk/benefit analysis, and a clear recommendation supported by data.
Level 2
ED1SON Alliance
Welfare cabin purchase
- What factors did you consider when assessing the long-term value of purchasing welfare cabins?
I considered total ownership costs, maintenance, residual value and operational costs/.