Completion Flashcards

1
Q

In a normal, non-construction contract, what is meant by completion?

A

All obligations would be met, consistant to the requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a practicle completin certificate?

A

A certificate issued to evidence practicle completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Can a practicle completion certificate be retracted?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is practicle completion?

A

where the practical completion certificate (PCC) is issued. All obligations under the contract are seen to be done at this point.

Seen - an imortant distinction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what is the defects liability period?

A

A period of time (usually 6-12 months) after PC and is the end of the time whereby the contractor must come back and fix and latent defects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is meant by latent defects?

A

Defects that arise or become apparent after PCC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What key things happen when the PCC is issued?

A
  • Possession of site will transfer back to client
  • Responsibility to insure/protect site goes on to the client
  • Casement of liability for delay damages or LD’s
  • Passes risk of damage to site on to the client
  • Commencement of defects liability period
  • Trigger milestone payments
  • Release of (some) retention monies
  • Can effect third party agreements such as performance securities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When is the client required to take possession or admit PC under JCT?

A

When the work is “Finished” and no more patent defects can be identified

This is hard, most clients resort to finished-enough

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the test for completion?

A

The pre-described completion criteria test

Often unbiased opinion of contract administrator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What happens if a contractor disputes a client not marking a project as complete when they beleive it is?

A

Dispute resolution protocol followed - adjudication may be only way out

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Can PCC be issued if there are still patent defects?

A

That is left to the descretion of test (CA) or client, they may prioritise possession over defects being fixed and may deffer until defects liability period

Client and contractor should agree this if large defects remain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can the client use the site before PCC

A

In the absence of specific provisions in the contract the client cannot take possession of any part of the works without the express consent of the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If a conditions precident limits a CA’s ability to issue PC, what might an example of a condition be?

A

completion won’t be certified until all H&S information has been handed over

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Other than the completion of the building works, what else may the CA be looking for to issue PCC

A
  • Certificates
  • Equipment warranties
  • Opperation and maintenece manuals
  • H&S information
  • Collateral warranties

etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Is building control sign off required for PCC

A

No, though its a good indication it shouldnt, likewise neither is sign PCC should be signed off, building controll wont look at asthetical issues which could be defects - etc wrong colour paint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the *‘De Minimis Non Curat Lex’ *law principle

A

The law does not care for, or take notice of, very small or trifling matters

Relevant when measuring completion