Extension of time and Liquidated Damages Flashcards

(22 cards)

1
Q

What is an extension of time?

A

A mechanism in the contract that allows an employer to extend the time in the contract by which the contractor is required to complete works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is EOT short for?

A

Extension of time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What type of construction contracts have EOTs

A

The JCT suite

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

There are conditions that can triger EOTs. What is this term called?

A

Relevant Events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a relevant event?

A

A defined event set out in a JCT contract that will trigger an EOT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When is an extension of time triggered?

A

when a relevant event happens

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Under JCT when is a contractor bound to advise the client of a relevant events impact and effect?

A

Whenever reasonable and apparent - though its uncelar what recourse is available if they dont.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What would happen if a relevant event happened (a delay not that isnt the contracts fault or owned risk) and there was no extension of time facility within the contract?

A

The completion date would change to time at large

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is time at large?

A

Completion within reasonable time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the impacts of a contract completion date becomeing time at large

A

The client is no longer entitield to liquidated damages and delay damages become more ambiguous with no specific date of completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who confirms an EOT after the contractor sends notification?

A

The CA or EA - as soon as possible and absoloutly within 12 weeks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can the CA/EA retrospectivly bring a previously extened completion date back so that it was sooner?

A

Yes, they would do this to allow the client to claim more liquidated damages when there is a leitimate reason to bring it forward..

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What happens if a contractor disagrees with a CA/EAs decision surrounding an EOT

A

Dispute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are liquidated damages?

A

liquidated damages are pre-determined damages, calculated before damage has been incurred, that may not represent the true damage but does provide certainty of what the damages will be.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Where does the language behind liquidated damages come from?

A

Liquidare – to make clear or certain

A latin word

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Whats the difference between liquidated and unliquidated damages?

A

Liquidated - pre-determined, clear from the start
Unliquidated - retrospective, left for the courts to decide (uncertain)

17
Q

What are the two rules for LDs to be valid?

A
  1. They must represent a true and documented calculation
  2. They must be a genuine pre-estimate of loss and not be a penalty

This is set out in common law regarded LD’s

An obvious sign of a penalty would be a gross misestimation of ascertained damages

18
Q

If there are no valid LDs in the contract - can the client recover other delay damages?

A

Yes - these would be unliquidated damages and would be acheived through dispute

19
Q

What is the main benefit of LDs?

A

Clear vision of what damages will be - clarity for both parties

20
Q

What is the main disadvantage of LDs?

A

Damages may not represent true damages, client could be under or over reinbursed.

21
Q

Can you name the Relevant events?

There are 14 - lol good luck

A
    1. Changes from the employer
    1. Employer instructions
    1. The client not giving the site
    1. Archaeologist on site
    1. Suspension due to employer not paying
    1. Impediment causing delay by employer
    1. The fault of the state, unexpectedly needing to do or not do something
    1. Really bad weather
    1. If there is damage from specified peril, e.g., fire or flood, the insurance will cover the cost but there will still be time needed to remedy – this does that.
    1. Terrorism
    1. Industrial action
    1. New laws
    1. Delays from e.g., planners where contractor did everything possible to avoid.
    1. Force majeure – an event beyond the control of the parties. E.g., covid.
22
Q

What are the benefits of EOTs?

A
  • It relieves the contractor’s liability for liquidated damages for a delay that they did not cause
  • It enables another completion date to be set, which maintains the employer’s ability to take liquidated damages if another delay occurs