Contract Admin Flashcards
(36 cards)
What is a Contract Administrator (CA)?
A third-party role, usually the surveyor or architect, appointed to administer the building contract between employer and contractor — ensuring both parties meet their obligations.
What are the core duties of a CA?
Issuing instructions
Certifying valuations, extensions of time, and completion
Monitoring progress and quality
Chairing meetings and minuting
Managing contract documentation
When is the CA appointed?
Typically before construction begins, often during tender or pre-contract stages, depending on procurement route.
What are Instructions under a JCT contract?
Architect’s/CA Instructions (AIs): formal directions to the contractor to vary the works, correct defects, or clarify details.
Must be in writing.
What is a Variation?
A change to the works, quantity, or method from the original contract.
Must be issued as a formal instruction and usually leads to a change in price and/or time.
What is a Valuation and Interim Certificate?
Valuation = contractor’s progress claim
CA assesses and certifies it via an interim certificate
Usually monthly, until Practical Completion
JCT Standard Timeline for payment
- Interim Payment Application
- The Contractor submits an application (usually monthly).
- The application must be served in accordance with the contract (often 7 days before the due date).
- Due Date
- Often 7 days after the application is received (may vary).
- Payment Notice
- Must be given within 5 days after the due date.
- Issued by the Employer (or Architect/Contract Administrator).
- Final Date for Payment
- Usually 14 days after the due date (check contract specifics).
- Pay Less Notice
- Must be issued at least 5 days before the final date for payment.
- States the reduced amount the payer intends to pay and how it was calculated.
What is Practical Completion?
The stage when the works are substantially complete and can be used for their intended purpose.
CA issues the Practical Completion Certificate, triggering retention release and start of defects period.
What is the Defects Liability Period?
A period (often 6–12 months) post-Practical Completion where the contractor must remedy any defects at their own cost.
Ends with Final Certificate issued by CA.
What are Common CA Documents?
Contract drawings/specifications
Instructions
Interim certificates
Variation orders
Minutes of meetings
Final account & Final Certificate
What are Bonds in Construction Contracts?
A bond is a guarantee from a third party (often a bank or insurance company) that ensures the contractor will perform the work as agreed.
- Performance Bond: Guarantees completion of work.
- Payment Bond: Ensures subcontractors and suppliers are paid.
What are Guarantees in Construction?
A guarantee is a promise from the contractor or manufacturer that the work or materials will meet certain standards for a defined period after completion (e.g., 2-year guarantee for defects).
Can cover things like materials or workmanship.
What are Warranties in Construction?
A warranty is a legal promise that certain aspects of the project (e.g., design, materials) will be free from defects for a specified period, usually longer than guarantees.
Often included in construction contracts to protect the client against issues post-completion.
What are Third-Party Rights?
Third-party rights allow a party not directly involved in the contract to enforce terms of the contract (e.g., warranties or guarantees).
- Often used in collateral warranties where the building owner, tenants, or funders might have the right to claim under the contract.
What is Collateral Warranties?
A collateral warranty is a side agreement where a third party (often a funder, tenant, or building owner) is given the right to enforce certain provisions of the main contract.
- Common in projects where a third-party investor is involved or the building is leased.
Building Defects Case Law – Key Case
London Borough of Merton v Stanley [2001]
Issue: Contractor’s failure to follow plans resulted in defects.
Outcome: The court emphasized the contractor’s responsibility for defective works and the extent of the contractor’s duty to make good those defects.
Key learning: Contractors must adhere to the terms of the contract and workmanship standards.
Commencement of Works – When do works officially commence?
Works are deemed to commence when the contractor starts work on-site as per the contract’s start date.
Usually marked with a formal Notice of Commencement issued by the contractor or client.
What is Completion in a Construction Contract?
Completion occurs when the works are substantially finished, and the client can occupy the property for its intended purpose.
Practical Completion: Works are largely completed, but minor defects may remain.
Completion Certificate: Issued once the works are finished and comply with the contract terms.
Construction Insurance – What types exist?
Contractor’s All Risk Insurance (CAR): Covers damage to the works and third-party claims during construction.
Professional Indemnity Insurance: Covers consultants against errors in professional services.
Public Liability Insurance: Protects the contractor against third-party claims for injury or damage.
Contract Administration Case Law – Key Case
St. Martins Property Corporation Ltd v Sir Robert McAlpine Ltd [1994]
Issue: Dispute regarding the validity of an interim certificate and the role of the Contract Administrator in certifying payment.
Outcome: Court reinforced that the CA’s role in certifying payments must be performed properly and independently according to contract terms.
Key learning: The Contract Administrator’s role is independent, and any act or omission affecting certification must follow the terms of the contract strictly.
What is the Commencement Date in Contracts?
The commencement date marks the official start of the contract, triggering the contractor’s obligations to begin work on site.
It’s important for determining timeframes for completion and penalties for delays.
What is a Completion Certificate?
Issued by the Contract Administrator or Employer’s Agent when the works are completed to satisfaction, confirming that the contract has been fulfilled and no further works are required, aside from any minor defects (if any).
Case Law on Contract Administration: **
Costain Ltd v Charles Lawrence International Ltd [2006]
Issue: Dispute regarding delays and the Contract Administrator’s role in certifying extensions of time.
Outcome: The court clarified the Contract Administrator’s role in granting extensions of time is discretionary, but must be based on clear evidence and the contract’s provisions.
Key learning: Contract Administrators must exercise their discretion responsibly, based on clear, documented facts.
What are Defects in Construction?
Defects refer to any part of the work that does not comply with the contract specifications, drawings, or relevant building standards.
Identified during the Defects Liability Period (DLP).
The contractor is usually required to remedy defects at their own cost