Contract Admin Flashcards
(165 cards)
How is the Uniform Commercial Code (UCC) important to Interior Design?
“governs the sale of goods in the United States and is applicable to the purchase and delivery of furniture and other moveable items”
In regard to interior design, what is substantial completion?
“the stage when the work or a designated portion of it is sufficiently complete according to the contract documents that the owner can occupy or use the site even though a few minor items may yet need to be finished or corrected”
What is involved in generating a fee projection?
“the total fee the designer will receive after amounts for profit overhead and other expenses are deducted is allocated to the schedule and to the various staff members who will be completing the project”
What is a performance bond?
“a statement by a surety company that obligates the surety company to complete construction of the owners project if the contractor defaults”
If all bids on a project exceed the owners budget, what four options are available to the owner?
“-rebid (or renegotiate) the contract
- authorize an increase in construction costs
- work with the designer to reduce the scope of the project -abandon the project”
What are seven of the items the contractor must submit to the owner during project closeout?
“-the bonds
- all warranties
- any extra stock of materials
- a set of record drawings
- the certificate of occupancy
- documentation required by the final application for payment
- maintenance contracts and equipment operating instructions”
What are four types of written modifications that can be made after the execution of a contract?
“-a change order
- an amendment to the contract
- a written order for minor changes in the work
- a written interpretation by the interior designer”
How is a negotiated contract different from a bid (or tendered) contract?
“a negotiated contract the owner selects a contractor to do the work and the two discuss the cost and terms of the contract in a bid contract several contractors view the contract documents and submit cost proposals”
What are six things the interior designer is NOT responsible for during contract administration?
“-the means methods or techniques of construction
- safety on the job sites
- fabrication shipment or installation of construction elements or furnishings
- acts or omissions of contractors subcontractors or suppliers
- stopping the work if there are problems
- receipt inspection and acceptance of furniture or fixtures”
What is the contract time?
“the period from the starting date established in the agreement to the time of substantial completion”
At an owners request, a contractor may include alternates in the bid documents. What is an alternate?
“a construction item that could at the owners discretion be substituted for a similar item in the base bid to reduce project costs”
What is the basic process for getting approval on submittals from subcontractors to suppliers?
“-first the submittals is sent to the general contractor who reviews it and then sends it to the interior designer for approval
- if the submittal also requires a review by one of the designer’s consultants it is sent to the consultant for review
- the submittal is then sent back to the contractor who returns it to the party who originally made the submittal”
What is a unit price?
“a set cost for providing a portion of the construction work that is based on an individual quantity such as per unit or per square foot”
What are two common types of construction claims?
“-claims for additional timer
-claims for concealed or unknown conditions”
What seven types of information are typically included in the instruction to bidders?
“-procedures for submitting bids -where to obtain bidding documents
-procedures for opening bidsr
-submittals required with the bidsr
-bidders representation statement
-required bonds
-procedures for issuing addenda and other modifications”
How is mediation different from arbitration?
“in mediation a neutral third party facilitates an agreement between the disputing parties but the agreement is not binding.in arbitration the third party hears arguments and renders a decision according to specified rules and the decision is binding”
What are the six basic components of an owner-vendor agreement (or owner-contractor agreement)?
“-the agreement itself “ -the conditions of the contract (general “” supplementary and other)
- the drawings
- the specifications
- all addenda
- all modifications issued after the execution of the agreement”
What is an addendum?
“a written or graphic document issued by the interior designer before the execution of the contract that modifies or interprets the bidding documents by additions deletions clarifications or corrections”
What are six common reasons why a designer might withhold payment to a contractor?
“-the work is defective
- the contractor failed to pay the subcontractors
- the contractor has damaged the property of the owner or another contractor
- third party claims have been filed
- evidence exists that the work will not be completed on time
- the contractor failed to conform to the contract documents”
Who is responsible for making the acceptance inspection of furniture or fixtures?
“the owner is responsible for acceptance inspection of furniture and fixtures (FF&E delivery)”
What part of a contract agreement may be used to include unique contract documents that modify General Conditions of the Contract for Construction?
“Supplementary Conditions”
What form does a vendor or contractor use to request a payment from the owner?
“Application for Payment form”
What two types of contracts are typically used on large commercial interior design projects?
“-construction contract
-contract for furniture fixtures and equipment”
What are the interior designers obligations during construction observation?
become generally familiar with the progress and quality of the work
- keep the owner informed about the progress of the work -endeavour to guard the owner against defects in the work
- determine in general if the work is progressing in such a way that it is in accordance with the contract documents”