Contract Administration Flashcards
For the ECFRS decorations project, what was the type of contract and procurement?
Minor Works, should have been intermediate for sectional completion.
Traditional, client retains control over design, client can specify exact works required, single stage and design finalised so cost certainty achieved, straightforward to analyse tender returns, flexibility with variations post tender, contractor does not price design risk.
What were the relevant events for the ECFRS decorations project?
No relevant events, the contractor was not entitled to an extension of time
How do you assess the delays for the ECFRS decorations project?
Reviewed on site progress and revised dates against original programme and investigated reasons why.
How did you calculate the LAD amount for the ECFRS decorations project?
Loss of rent / income, fees, storage costs, financing costs, etc
for ext decs client had calculated amount due to the storage costs and project team fees
Referring to the ECFRS decorations project, what entitles the contractor to an EoT?
Inclement weather
Force majeure
Additional instructions
Impediment due to client
Suspending works due to client not paying
Contractor wasn’t entitled to any of these
How long after issuing a 7 day notice can you terminate contract?
If the contractor does not comply within those 7 days within 10 days
For Burnham Road what are the consequences of issuing a MGD certificate?
- Contractor’s obligations are complete.
- Release of final retention
- Start of latent defect period
What are latent and patent defects? Was the defect at Burnham Road latent or patent?
A patent defect is one that has been identified during the works or during the defect liability period, whereas a latent defect could be concealed and may not be apparent until many years later, for example a building cracking due to inadequate foundation design.
Worktop issue was a patent defect.
For Burnham Road, when was the worktop defect recorded?
During the rectification period.
What made you think the Burnham Road defect was the contractor’s responsibility?
Pipe leaking within a couple weeks of completion not fit for purpose.
Contractor agreed rectification is required.
Also responsible to rectify associated making good.
Contractor agreed to rectify worktop during EOD inspection.
For Kelsey Street, how do you chair a meeting? Explain the process?
- Arrange a suitable date between the parties
- Circulate invitation on site or teams
- Send agenda or previous meeting minutes before
- Run through items with the parties
- Make notes and issue minutes within a week thereafter
- Carry out site inspection or valuation accordingly
Who is responsible for the risk of additional asbestos for the Kelsey Street project? Was an R&D survey undertaken?
The client because they did not have up to date asbestos records and undertake an R&D survey prior to commencement.
An R&D survey was undertaken once the contractor was on site and then there was a significant delay due to client indecisiveness, therefore contractor entitled to additional time and money.
For Kelsey Street what information was submitted with the EoT claim?
- Explanation and contract conditions
- Delay impact on programme
- Photographs
- Likely costs in accordance with relevant matter claim
For Appleford Court, how do you determine the due date?
Interim valuation date where not stated is one month after date of possession. Due date 7 day after normally.
For Appleford Court, what was the consequence of late payment?
There was no consequence on this occasion, the client apologised and confirmed payment would be one or two days late. The contractor confirmed that this was okay provided it did not happen again and took no further action.
What would happen if you fail to issue a payment certificate within 5 days of the due date?
Contractor is to issue their payment notice and final date for payment extended by delayed days that a notice wasnt issued
What happens if the contractor does not make application by the due date?
Even if interim valuation not submitted works should be valued
For Appleford Court how did you undertake a valuation? Explain the process?
- Receive application for payment on interim valuation date
- Attend site on due date with application
- Review items with contractor and query any as necessary
- Reach agreement on valuation, return to office and issue payment certificates.
For Burnham Road, what information was required to achieve PC?
Final BC certificates, NHBC warranties, NICEIC certificates, snag lists, tv aerial certiciate, kitchen and bathroom guarantees, contractor reports, O&M manual, H&S file.
Regulation 38 certification not required because it wasnot multi storey and multi occupancy.
How did you undertake handover for Burnham Road?
- Visit properties with client and contractor
- Check the remaining snags
- Complete key and meter schedule
- Issue certificates
For Burnham Road, what triggered the EOD inspections?
The end of the rectification period as stated on the PC certificate.
For Burnham Road, how did you arrange the EOD inspections?
Contacted client, they arranged access. Then contacted the contractor to let them know the proposed date and we all attend the properties.
Talk me through the process of carrying out an EOD inspection?
- Arrange date with client and contractor
- Send letters to notify residents
- Inspect the property and identify any defects. Check the snag lists.
- Note down any defects of EOD schedule
- Request client obtains resident sign off forms
- Issue CMGD and release retention once rectification is complete of all defects.
What are the implications of issuing a PC certificate?
Releasing Retention Money.
Ending Contractor Liability for Liquidated Damages.
Starting the Defects Liability Period.
Triggering the Final Account Stage.