Contract Administration Flashcards
(63 cards)
What are some standard forms of contract and sub-contract used in the industry?
The suite of contracts I am most familiar with is the (Joint Contracts tribunal ltd) JCT suite of contracts, contracts include:
- Standard building contract
- Intermediate building contract
- Minor works building contract
- Design and build contract
- Management building contract
- Construction management contract
- Major Project construction contract
Alternatives suites include
- NEC contracts
- FIDIC contracts
What are the forms of subcontract?
What are the forms of NEC Contract?
NEC4 Engineering & Construction
NEC4 Design Build & Operate Contract
NEC4 Engineering & Construction Subcontract
NEC4 Framework Contract
NEC4 Professional Servies Contract
NEC4 Supply Contract
What are the options of NEC contracts?
Option A: Priced contract with activity schedule
Option B: Priced contract with bill of quantities
Option C: Target contract with activity schedule
Option D: Target contract with bill of quantities
Option E: Cost reimbursable contract
Option F: Management contract
What are NEC contracts?
NEC (New Engineering Contract) contracts are a suite of construction and engineering contracts developed by the Institution of Civil Engineers (ICE) to promote good project management and collaboration. They are designed to be flexible, clear, and easy to administer, with a focus on preventing disputes through proactive risk management and clear communication.
How do NEC contracts compare to other suites?
Project Management Focus:
NEC contracts integrate project management principles into the contractual framework, encouraging proactive risk management, early warnings, and collaborative problem-solving.
Emphasis on Collaboration:
NEC contracts emphasize a spirit of mutual trust and cooperation between the parties, encouraging them to work together to achieve project objectives.
What are the main differences between NEC3 and NEC4?
The differences from NEC3 to NEC4 can be summarised in four points:
More contract types available
Greater clarity in guidance and language
Commercial simplification to avoid disputes
Application of common amendments to NEC3 to make NEC4 fit-for-purpose
What are FIDIC contracts?
FIDIC contract is a standard form construction contract published by the International Federation of Consulting Engineers (FIDIC). These contracts are widely used in international construction projects and are known for their balanced approach to risk allocation between the employer and contractor. FIDIC contracts aim to define the contractual relationship and fairly distribute risks, often with significant negotiation.
What types of FIDIC contracts are there?
Green Book - Short form, less value that 500,000
Red Book - Conditions of contract for building and engineering
Yellow book - Conditions of contract for plant design and build
Silver book - Conditions for EPC / Turnkey projects
What is a JCT Minor Works Contract and what is it for?
A standard form of JCT contract, designed for smaller, basic construction where the works are simple in nature. For traditionally procured projects. These contracts offer less detailed conditions and control procedures compared to larger JCT contracts like the Intermediate or Standard Building Contracts.
What is a JCT intermediate works contract?
A standard forms of JCT construction contracts designed for medium-sized, less complex building projects. They offer more detailed conditions and control procedures than the simpler Minor Works contracts but are less comprehensive than the Standard Building Contracts. For simple projects involving normal well established trades and do not involve complex service installations or other specialist work.
What is a JCT construction management contract?
Is designed for construction projects where the employer appoints separate trades to carry out the works, and a construction manager to oversee the works for a fee.
What is a JCT management building contract
is for use on construction projects where the client appoints a management contractor to complete the works. Construction is completed under a series of separate works contract.
When were JCT building contracts established?
1931
What are the roles and responsibilities of a contract administrator?
Keeping records
Conducting site inspections
Chairing, attending and recording meetings
Reporting to the client / employer
Issuing instructions
Interim valuations of the works
Issuing certificates
Manage the insolvency of a contractor
Adjusting the contract sum
Deciding validity of Loss and expense claims
What certificates can a contract administrator serve? (under JCT)
SBC, IC and ICD each provide for the issue of eight different kinds of certificate:
- Interim certificate
- Non-completion certificate (not MW/MWD)
- Section completion certificate (not MW/MWD)
- Practical completion certificate
- Certificate of making good
- Certificate releasing insurance money
- Certificate after termination
- Final certificate.
No certificates are issued under DB, because there is no independent architect as certifier.
What are the CA’s responsibilities when an instruction or variation is required?
It is solely the CA’s responsibility to issue instructions which should be given in writing and issued promptly, The CA will need to be aware of the cost implications of issuing instructions.
What are the purpose of certificates and notices?
- To record an event – as in the case of a practical
completion certificate, a certificate of making good
and a final certificate. - A financial statement – as in the case of interim
certificates, payment notices and pay less notices.
What are the main elements you would include within an interim valuation?
- Preliminaries
- Measure work
- variations
- materials on site
- materials off site (if applicable)
- loss and expense
- retention
What needs to be in place for you to include payments for materials on site within interim valuations?
- the materials should be for the works
- they should be adequately protected against weather and other casualties and stored securely
- delivered to programme (not brought to site prematurely)
- in a reasonable quantity
Under most JCT contract conditions, these materials and goods become the employer’s property once they are certified and paid for, provided the contractor has valid title to them. However, the contractor remains responsible for loss or damage to them while on site. This addresses the complex issue of “retention of title” clauses often found in supplier contracts.
Who conducts interim valuations?
The value of monthly payments is estimated by a site measure validated by the quantity surveyor, certified by the contract administrator and paid (within a stated time) by the employer.
When are interim valuations undertaken?
Typically monthly, as stated in the contract particulars. These continue after practical completion, until the final certificate is issued. The last due date is either the date of:
- expiry of the rectification period or (if later)
- issue of the certificate of making good.
What is a retention?
A percentage of the amount certified as due to the contractor on an interim certificate, that is deducted from the amount due, and retained by the client.
What is the purpose of retention?
The purpose of retention in a construction contract is primarily to safeguard the employer. It serves as a sum of money (the retention fund) held by the employer to protect against various issues related to the contractor’s performance.
Specifically, retention is intended to:
- Guard against defective or non-conforming work or materials provided by the contractor.
- Safeguard against latent defects that may develop during the rectification period and were not identified at practical completion. The rectification period is typically twelve months, during which the contractor must make good any defects, shrinkages, and other faults that appear.
- Mitigate the risk of the contractor’s possible failure to complete the contract.