Contract Administration (L2) Flashcards

(16 cards)

1
Q

What are the main standard forms of Contract?

A
  • JCT (Joint Contracts Tribunal)
  • NEC (New Engineering Contract)
  • FICID (International Federation of Consulting Engineers)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When might you recommend the use of a JCT Design and Build Contract?

A
  • Employers wants a single point of responsibility for design and construction
  • When the design is not fully complete at tender stage
  • When the contractors design input is required
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key differences between JCT and NEC

A
  • JCT is more traditional and prescriptive, based on legal president
  • NEC is more collaborative, proactive and flexible
  • JCT based on issues after they occur. NEC is more proactive (early warnings etc.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Name some common Procurement routes?

A
  • Traditional (Design-Bid-Build)
  • Design and Build
  • Management Contracting - MC procures trade contracts for client and manages / coordinates for the client
  • Construction Management - Client appoints CM and all trade contractors. CM manages the work but does not carry risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the key payment mechanisms in contracts?

A
  • Interim payments (based on valuations)
  • Advanced Payment (in some contracts)
  • Retention (to cover defects)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Practical Completion?

A
  • The point when the works are complete enough for the client to take possession and use the building
  • Triggers: Release of half retention, start of defects period, end of Contractor liability for delay
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Key differences between Intermediate Contract and Minor Works Contract?

A
  • Sectional / Partial Completion (none for MW)
  • Loss and Expense claims (none for MW)
  • Retention Periods (3 months for MW)
  • Requirement for programme (none for MW)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Key differences between Intermediate Contract and Design and Build?

A
  • Contractor Proposals (only in D&B)
  • Named subcontractors (none in D&B)
  • Contract Administrator vs Employers Agent (EA for D&B)
  • Design liability (only in D&B)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Construction contract dispute resolution mechanisms?

A
  • Negotiation - First and most informal step. Easy fix
  • Mediation - Voluntary and non-binding. Preserves relationships
  • Conciliation
  • Adjudication (Construction Act 1996) - 28 day process. Binding unless overturned later in Arb/Lit
  • Arbitration - Private, formal process. Binding and enforceable
  • Litigation (through the courts) - Public legal process
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a collateral warranty?

A

A separate contract providing rights to 3rd parties (e.g., funders, tenants)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What documents are usually required to form a contract package?

A
  • Employers requirements or specification
  • Contractors Proposals (if D&B)
  • Drawings
  • Preliminaries
  • Appendices (insurance details, warranties etc.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is an Extension of Time

A

A contractual mechanism to adjust the completion date due to qualifying delay events, while prevents the application of liquidated damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a collateral warranty?

A

It extends the contractors liability for defects beyond the employer to third parties like funders or tenants, who wouldn’t otherwise have the right to claim

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a subcontractor warranty?

A

A subcontractor warranty is a specific type of collateral warranty. It is from a subcontractor to a third party, giving the employer a direct right against the subcontractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the difference between a collateral warranty and a subcontractor warranty?

A

A collateral warranty is a general term that extends the contractors liability beyond the employer to a third party. A subcontractor warranty is specific from a subcontractor to a third party.

Subcontractor warranties most common in D&B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is Final Account?

A

Final account is the agreed total amount of money due to a contractor under the terms of the building contract, including all variations, loss and expense, provisional sums and adjustments.

Final account marks the financial close-out of the contract