Contract Dates Flashcards

(71 cards)

1
Q

Contractor to give Owner notice of cancellation or expiration of required insurance.

A

3 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Owner to give Contractor notice of cancellation or expiration of required insurance.

A

3 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Successful Bidder to deliver required bonds to Owner, after execution of Contract.

A

3 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Architect to issue addenda, before bid date.

A

4 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Contractor/Architect’s notice to Owner before disclosing confidential information.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Architect to respond to Application for Payment.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Contractor to pay subcontractor, after receiving payment from Owner.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Contractor to provide proof of payment of subcontractors, at Owner’s request.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Owner to pay Contractor, after date established in Contract Documents, if any.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Contractor’s notice to Owner and Architect of stopping Work, after failure to receive payment.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Contractor/Architect’s notice to Owner before terminating Contract for cause.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Owner’s notice to Contractor before terminating for cause.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Bidder’s deadline to submit RFIs, before bid date.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Owner to furnish reasonable evidence of financial arrangements to Bidders, upon request.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Architect to request lien rights from Owner, at Consultant’s request.

A

7 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Contractor to send Application for Payment to Architect, prior to scheduled progress payment date

A

10 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Bidder’s deadline to return Bid Documents to issuing office for refund of deposit, after bid date.

A

10 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Bidder’s deadline to propose substitutions, before bid date.

A

10 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Owner to furnish reasonable evidence of financial arrangements to Contractor, at Contractor’s request.

A

14 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Contractor to report concealed or unknown conditions, after discovery.

A

14 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Architect to report objections, whether by Architect or Owner, to proposed superintendent or subcontractors, or request additional time to consider.

A

14 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Owner to evaluate, give notice of, or enforce mechanic’s lien rights.

A

15 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Owner to furnish information necessary for Architect to evaluate, give notice of, or enforce lien rights, upon request.

A

15 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Injured party to give notice of injury or damage to other party, after discovery.

A

21 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Of stopped Work, at no fault of the Contractor, before Contractor may terminate the Contract.
30 days
26
Days of stopped Work, due to Owner non conformance, before Contractor may terminate the Contract.
60 days
27
Days after Substantial Completion, Construction Phase services to be compensated as Additional Services.
60 days
28
Cumulative days of suspended Work before Architect can terminate.
90 days
29
Architect issue addendum to all bidders for acceptable substitution
4 days
30
Architect issues Certificate for Payment within _____ days after Contractor applies
7 days The Architect will, within seven days after receipt of the Contractor’s Application for Payment, either (1) issue to the Owner a Certificate for Payment in the full amount of the Application for Payment, with a copy to the Contractor; or (2) issue to the Owner a Certificate for Payment for such amount as the Architect determines is properly due, and notify the Contractor and Owner of the Architect’s reasons for withholding certification in part as provided in Section 9.5.1; or (3) withhold certification of the entire Application for Payment, and notify the Contractor and Owner of the Architect’s reason for withholding certification in whole as provided in Section 9.5.1.
31
Owner pays Contractor within ___ days after the date established in the Contract Documents.
7 days
32
Contractor pays subs and suppliers
7 days
33
Contractor can stop the Work if Architect does not issue a Certificate for Payment within ___ days after receipt of the Contractor’s Application for Payment.
19.7 Failure of Payment If the Architect does not issue a Certificate for Payment, through no fault of the Contractor, within seven days after receipt of the Contractor’s Application for Payment, or if the Owner does not pay the Contractor within seven days after the date established in the Contract Documents, the amount certified by the Architect or awarded by binding dispute resolution, then the Contractor may, upon seven additional days’ notice to the Owner and Architect, stop the Work until payment of the amount owing has been received.
34
The Contractor shall pay each Subcontractor, no later than ___ days after receipt of payment from the Owner.
9.6.2 The Contractor shall pay each Subcontractor, no later than seven days after receipt of payment from the Owner, the amount to which the Subcontractor is entitled, reflecting percentages actually retained from payments to the Contractor on account of the Subcontractor’s portion of the Work.
35
If requested, the Contractor has ___ days to furnish written evidence that he has properly paid Subcontractors and suppliers amounts paid by the Owner to the Contractor for subcontracted Work.
9.6.4 The Owner has the right to request written evidence from the Contractor that the Contractor has properly paid Subcontractors and suppliers amounts paid by the Owner to the Contractor for subcontracted Work. If the Contractor fails to furnish such evidence within seven days, the Owner shall have the right to contact Subcontractors and suppliers to ascertain whether they have been properly paid. Neither the Owner nor Architect shall have an obligation to pay, or to see to the payment of money to, a Subcontractor or supplier, except as may otherwise be required by law.
36
Contractor can ask Owner proof of Financial ability before & days of Final Bid Receipt
7 days
37
Written Notice needed to terminate Contract bet Owner-Architect, Owner-Contractor, Architect- Consultant
7 days
38
Owner can terminate contract with Architect or Contractor w/o cause within __ days of written notice
7 days
39
Architect can terminate contract with CONSULT. w/o cause within __ days of written notice
7 days
40
Owner has __ days to return Dwgs to Architect after termination of contract
7 days
41
Architect has __ days to return Dwgs to Consultant after termination of Contract
7 days
42
Substitution for a materials, system or product to architect before the bid deadline
10 days
43
Contractor has __ days to correct work after Owner notifies
10 days
44
Architect has time to review Claim
10 days
45
To respond to initial decision makers’ request for additional supporting data
10 days
46
Request Cert of Pay before Schedule of Value date of actual Payment
10 days
47
Super name objection by Architect or Owner
14 days
48
Owner to Request for architects certificates
14 days
49
Owner has __ days to furnish all info to Contractor or Architect for filing Lien claim
15 days
50
Notifying of concealed subsurface condition
14 days
51
Damage discovered; notify Owner or Architect within __ days
21 days
52
Damage to each other file claim within __ days of occurrence of problem
21 days
53
Architect has __ days to take decision on a claim- if no decision Architect/ Contractor can go for Mediation
30 days
54
Either party can demand in writing within __ days of initial decision to the other party to file for mediation within 60 days of initial decision
30 days
55
Owner and Architect go for Arbitration with __ days of Mediation decision
30 days
56
Notice given to Owner by Contractor or Architect by CONSULT. before actual insurance expires
30 days
57
Contractor can terminate contract if No Fault/ Govt rule/ no Pay
30 days
58
Architect / CONSULT. receives compensation after work is resumed for interruption, delay if work stopped more than __ days
30 days
59
Final payment to the Contractor is due no later than __ days after the issuance of the Architects final certificate for payment
30 days
60
File lien within \_\_-\_\_ days after the last work is performed or materials are installed
30-90 days
61
\_\_ days consecutive / ___ days/ 100% schedule time in One Year work is stopped – Contractor can terminate Contract
60 days consecutive / 120 days/ 100% schedule time in One Year work is stopped – Contractor can terminate Contract
62
\_\_ days Mediation stays pending after date of filing
60 days Mediation stays pending after date of filing
63
Change of service for Architect and CONSULT. if Construction Admin Service goes beyond __ days
60 days
64
Architect / CONSULT. can terminate Contract of work stopped __ consecutive days
90 consecutive days
65
If Bidding is not progressed after CD documents is issued Project Budget subject to modification
90 days
66
Architect to Return Submittals/ shops
Reasonable Promptness
67
Respond to RFI
Reasonable Promptness
68
CONSULT to seek arbitration within _reasonable time_ after claim
Reasonable Promptness
69
Time to claim warranty after Substantial Completion
1 Year
70
Suit to enforce the bond must be brought within __ years from the date on which final payment under the contract is due
2 years
71
Time limit on Claim after Substantial Completion
10 years