Contract Practice Flashcards
What is a contract?
- Legally binding promise (written or oral) by one party to fulfil an obligation to another party in return for consideration’
What should a basic binding contract consist of?
Offer, acceptance, Consideration and Intention to create legal relations
Define express terms
terms of the agreement which are expressly agreed between parties
Define implied terms
A contractual term that has not been expressly agreed between the parties but has been implied into the contract either by common law or by statute
What is tort?
A tort is a civil wrong
Part of the civil law
A claim in tort is concerned with loss or harm
How do statutory provisions and contract provisions differ?
Statutory provisions are set out by law and must be complied with regardless
Contract provisions relate to the contract in question and therefore only apply to specific project
What is your opinion of oral contracts?
Whilst they are legally binding, the difficulty lies in having proving specific terms and conditions of the agreement. Having a written contract is always the preferred opinion
What is a breach of contract?
Breach of contract occurs when one party in a binding agreement fails to deliver according to the terms of the agreement
A breach of contract can happen in both a written and an oral contract
What is the LDEDCA 2009?
Local Democracy, Economic Development and Construction Act 2009
When did the Local Democracy, Economic Development and Construction Act 2009 come into force?
October 2011 in England and Wales
What did the LDEDCA amend?
The Housing Grants Construction and Regeneration Act 1996
Changed the way construction contracts are entered into and in particular introduced amended regime for payment and adjudication
What are the key payment provisions under the LDEDCA 2009?
Payment
1) Under HGCRA a construction contract must have an adequate mechansim for determining what payments are due and when they become payable
2) Pay when certified clauses can no longer be used to prevent paying a subcontractor on the basis that a certificate in the main contract is yet to be issued
What is a letter of intent?
Used to describe a letter from an employer to a contractor (or from a main contractor to a subcontractor) indicating the employers intention to enter into a formal written contract for works
Letter of intent typically asks contractor to begin those works before formal contract is executed
What info is typically included in letter of intent?
Detailed description of works
Contract sum
Date for possession
Date for completion
Insurance provisions required
What are the key contract provisions under the LDEDCA 2009?
Contracts
1) Repeals the requirement for construction contracts to be in writing therefore, contracts that are partly in writing or wholly oral are now covered. Allows parties to go to adjudication, even if their involvement is not formally recognised in writing
What are the key contractual payment notice provisions under the LDEDCA 2009?
Contractual Requirements
1) construction contract must specify that either the payer or the payee will issue the pay notice
2) Must be issued not later than 5 days after pay due date and paid before final date for payment identified by construction contract (usually 14 days)
3) Pay notice must specify sum the payer / payee considers to be due at the payment due date and basis for which sum was calculated
4) Pay notice must be issued even if pay notice is nil
What happens if payment notice is not issued?
Payer is required by contract to issue pay notice - failure to do so in set timeframe the payee if entitled to issue a default payment notice
What is a default payment notice?
Obliges the payer to pay the amount due and allows the payee their statutory right to suspend performance for non payment
What is a pay less notice?
A pay less notice allows the payer to amend the sum due if it is later discovered that the work or amount notified in pay notice is unsound.
When would a pay less notice be issued?
Paying parties are required to pay notified sum in either the pay notice or default pay notice by final date or serve a pay less notice
A pay less notice must specify sum paying party considers due on date the notice is served, basis of sum and be served no later than prescribed period prior to final date for payment
What can the payee do if the pay notice dates are not followed and the payer does not pay by final date for payment?
The LDEDCA 09 clarifies contractors right to suspend works in the event of non-payment
To suspend performance of obligations by reason of non payment , a default pay notice must have been issued and there must have been failure to pay.
What is the payer liable to pay the payee if works are suspended due to non payment?
The party who has not paid is liable to pay the payee (contractor) a reasonable amount by way of costs and expenses incurred by exercising the suspension of all or part of the works
What are the advantages of a Letter of Intent?
Allows work to commence before the main contract is agreed / signed
What are the disadvantages of a Letter of Intent?
May lead to complacency and disincentise both parties from signing the main contract
Contractually less robust than the main contract
Employer loses incentive in negotiations of the main contract