Contract Practice Flashcards
What is a contract?
A legally binding promise (written or oral) by one party to fulfil an obligation to another in return for consideration.
For a contract to be legally binding, it must have:
- offer
- acceptance
- consideration
- legality of contract (cannot contain illegal terms)
- capacity to contract (must understand contract consequences e.g. not minors or mentally disabled people)
- intent to create legal relations
Define “express terms”
The terms of the agreement expressly agreed between the parties.
Ideally they’re written in the contract but if the contract is agreed verbally, these will be the terms discussed and agreed between the parties.
Define “implied terms”
The contractual terms not expressly agreed between parties but are implied into the contract by case law or statute.
What is tort?
Tort is a civil wrong causing a claimant to suffer loss or harm, resulting in legal liability for the person who committed the tortious act.
How do statutory provisions and contract provisions differ?
Statutory provisions are set out by law and must always be complied with,
whereas contract provisions relate to the contract and therefore only apply to a specific project.
They’re also set out by the parties and their solicitors, they control what these are.
What is your opinion of oral contracts?
Although they’re legally binding, I think they’re not the most ideal because it’s more difficult to prove the expressed terms of the agreement as they aren’t written down. Therefore I prefer written contracts.
What is a breach of contract?
This occurs when a party in a binding agreement fails to fulfil their obligations under the contract.
This can happen in both written and oral contracts.
What is the LDEDC (Local Democracy, Economic Development and Construction) Act 2009?
This Act amended the Construction Act (Housing Grants Construction and Regeneration Act 1996) in 2011.
It impacted adjudication, payment, suspension provisions in all “construction contracts” entered into on or after 1st October 2011.
What are the key provisions under the LDEDC Act?
Contracts!
- The Act covers construction contracts that are partly or completely oral, parties can now go to adjudication over these type of contracts.
Payment!
-
Suspension of performance for non-payment!
- Clarifies the contractor’s right to suspend the works in the event of non-payment.
- However, a default notice must be issued and there must have been failure to pay. The party in default is liable to pay the contractor a reasonable amount for the costs and expenses incurred by suspending all or part of the work.
What is a letter of intent (LOI)?
A letter from the client to a contractor (or MC to a subcontractor) indicating the client’s intention to enter into a formal written contract for works described.
It usually asks the contractor to begin those works before the main contract is executed.
What information is typically included in a LOI?
- Name of client and contractor (or MC and subcontractor)
- Expiry date of letter
- Detailed description of the work to be completed
- Contract sum (if agreed)
- Method of payment
- Date for possession
- Date for completion
- Insurance provisions required
- Typically states employer’s right not to award the main contact for whatever reason
- ADR method
What are the advantages of a LOI?
Works on-site can commence before the main contract is agreed (earlier start on-site as LOI faster to produce than main contract)
Can see how the contractor performs before entering into a main contract with them.
What are the disadvantages of a LOI?
- Contractually less robust than the main contract
- Can disincentivise both parties from signing the main contract
- Employer loses incentive in negotiations of the main contract
Who issues the LOI?
The client
In what circumstances might a LOI be used?
- When an early start on site is important to the employer
- Where materials have long lead times and early procurement would aid the programme
- Starting construction works might trigger early founding
Who signs a LOI?
The client and contractor (or main contractor and subcontractor)
What would you say if the client asked you to draft a LOI?
LOIs are legally binding agreements like a contract, therefore I would not draft those.
What are the different types of LOI?
Comfort Letter:
- Expresses a party’s intention to act in a particular way at some point in the future, or at the time of issuing the letter.
Instruction to proceed with consent to spend:
- Allows works to proceed up to a certain value while the main contract is being finalised.
Recognition of contract (letter of acceptance):
- generally issued only once the contract has been substantially agreed and usually marks the completion of negotiations between the parties
- some forms of contract e.g. FIDIC use this to formally execute the main contract.
Are you aware of any case law relating to LOIs?
Ampleforth Abbey Trust vs Turner & Townsend:
The defendants were the PMs for building school accommodation for the claimant Trust. The defendants were responsible for procuring the building contractor and building contract. The building contract was never signed and the entire works (which were completed late) were procured under LOIs. Therefore, the Trust couldn’t claim liquidated damages under the building contract for the late completion of the works.
The judge held that the defendant had been negligent by failing to take the steps reasonably required of a competent PM to finalise the building contract between the Trust and contractor.
What is a parent company guarantee (PCG)?
A form of security that protects the client should the contractor default. The parent company (or holding company) guarantees to the client that if the contractor defaults on their obligations (typically through insolvency), they will remedy the breach, meeting all the contractor’s obligations under the contract (and/or covering loss and expense incurred by the client).
In what circumstances may a PCG be required?
- When a small contractor is part of a large, financially stable group of companies.
- The client may simply want this extra form of security.
Are there any Acts which govern third party rights?
Contracts (Rights of Third Parties) Act 1999
What is the overarching purpose of the Contracts Act 1999?
The Act allows third parties to enforce terms of a contract which they are not party to, on the condition that:
1) third party must be expressly identified in the contract, by name, class or description
2) the provision must confer a benefit on the third party.
E.g. tenant or building purchaser suffers loss due to subcontractor’s poor workmanship can now create a contractual relationship between them.
It also gives parties access to various remedies if those contract terms are breached.
https://www.lexisnexis.com/uk/lexispsl/construction/document/391372/56NS-GV21-F186-33HC-00000-00/Contracts__Rights_of_Third_Parties__Act_1999_in_construction_overview
What are the advantages of third-party rights?
Certainty:
- Once the third party rights are agreed, there is little room to revisit the wording when protection is required as is often the case with collateral warranties. This can help reduce costs.
Time & Cost:
- Since no separate document (i.e. collateral warranty) is being entered into, using the Act cuts down on the time and cost associated with warranties being drawn up, signed and circulated.
Subcontractors:
- Third party rights can be extended into subcontracts so that (provided the relevant building contract and subcontract are drafted accordingly) a client can grant third party rights in relation to work done by subcontractors unilaterally, without needing to chase many individual warranties.
unilaterally = undertaken by one person or party