Contract practice Flashcards
What contract suites are you aware of in the UK construction industry, other than JCT?
NEC
FIDIC
What are the main differences between the NEC and JCT contracts?
- NEC uses compensation events to assess time and cost together, JCT assesses these separate under Loss & expense and extension of time.
- Programme and Early warning register are key contract documents under the NEC forms.
- NEC uses Core/ Main and Secondary option clauses
- NEC uses simple, present tense language
- NEC encourages collaboration
- NEC is forecast rather than retrospective (i.e. variation costs can be agreed at FA on JCT, however we agree them prior to instructing)
- NEC does not provide for the use of Provisional Sums
You mention that you are aware of collateral warranties, What is a Collateral Warranty and why is it used?
Provides security for investors. A collateral warranty is used to create direct contractual relationships between parties that would otherwise not exist. It extends the rights under a principal contract, i.e. duty of care/ Professional Indemnity etc. It extends the duty of care for the whole of the principal contract. IT IS A CONTRACT BETWEEN THE THIRD PART AND SUB-CONTRACTOR/ CONTRACTOR ETC.
What are third party rights?
Allow third parties to have rights in relation to contracts without the need for additional documentation. I.e. third party can enforce the benefit of the contract
Why would you use third party rights instead of collateral warranties?
Warranties often involve a lot of admin and cost.
How do you go about deducting LAD’s?
a. Notify intent to charge LAD’s
b. Deduct costs from valuation and payment certificate
What are heads of claim?
Prolongation / disruption / acceleration
What are the differences between NEC and JCT?
QS / PM / CE’s / collaborative / legal jargon
What is required for a Contract to be valid?
Offer – acceptance – consideration – intent to form contract – legality – capacity
Do you know when FIDIC may be used and what it stands for?
a. Fédération Internationale des Ingénieurs – Conseils
b. Used internationally, the engineer acts as CA
Are you aware of the updates to JCT?
a. 2024 updates recently published.
b. More gender-neutral language
c. Captures updates to the – Building Regulations & Building Safety Act
d. Target cost contract (TCC)
What Acts are there relating to construction?
a. Building Safety Act 2022
b. Corporate Insolvency and Governance Act 2020
c. Housing Grants, Construction and Regeneration Act 1996
d. The Procurement Act 2024
e. Construction (Design and Management) Regulations 2015
f. Health and Safety at Work etc Act 1974
What is the construction act (housing grants construction and regen)?
Ensure payments are made promptly throughout the supply chain, and easier dispute resolution.
Do clients have to use the new suite of JCT contracts?
No, it will take time to implement and for client legal teams to assess.
How would you deal with ordering materials upfront?
a. Off-site materials bond
b. Vesting
What other bond are there?
Retention bond, advance payment bond
When might you or might not use a performance bond?
Technically shouldn’t be needed, as the tender has proved the contractor to be capable, and it adds additional cost. However it is good when the contractor is new to the client, or where there is a potential risk.
What contracts are you aware of and when would you use them?
a. I am aware of JCT D&B which would be used where the client wanted the contractor to be responsible for design maybe where the design had not yet been completed, and there was more urgency to get to site.
b. I am aware of JCT SBC and IC which are used where the client wants to retain control of the design and handle that risk and where the design is needed to be completed to RIBA 4 prior to entering the contract.
c. I am aware of JCT MW, which is a simpler contract used on smaller scale projects, or those of relatively simple work
What are the types of contract sums you can get/ basis of cost?
a. Lump sum – only adjusted by variations
b. Reimbursable (Prime Sum) – don’t know what the final account will be, paid actual.
c. Re-measurable – approximate quants are remeasured fully on site
What are some typical contract amendments?
a. The contract can be amended in many ways, one is amending the payment terms in the JCT D&B contract for example from the standard 14 days payment to 21 days for example. This is often to give the client more time to organise payment, as 14 days may not be enough time to deal with internal paperwork.
b. Another example is amending the defects rectification period from the standard 6 months in the JCT D&B to 12 months, this gives more time for any defective workmanship to show, across all seasons and weather, as the 6 months doesn’t do this.
c. Retention, from 3% to 5%
What is the limitation period for a contract signed as a deed?
12 years
What is the limitation period for a contract signed under hand?
6 years
What does it mean if the LAD’s section in the contract is written as ‘nil’
there are no LAD’s to apply
What if the LAD’s section is left blank with no rate?
This technically means they are unlimited and the client can apply any amount, this would likely lead to disputes