Contract Practice Flashcards
What is a contract?
An agreement between 2 or more parties which is intended to be legally enforceable.
What types of Contract are there?
Lump sum / target / reimbursement / remeasurement
Why are they required / relevant for the construction industry?
- Requirement for effective risk management / allocation.
- Long term nature of projects.
- Complexity of projects.
- Define roles, responsibilities and how parties interact.
What is a Letter of Intent?
A document from an employer to a contractor (or from a main contractor to a subcontractor) indicating the employer’s intention to enter into a formal written contract for works described in the letter, and asking the contractor to begin those works before the formal contract is executed.
What elements must be in place in order for a legally binding contract to be created.
certainty as to key terms;
consideration (the ‘price’ paid under the contract in return for performance by the other party of its obligations; and
a mutual intention to enter into a binding legal contract.
What is Quantum Meruit?
Quantum meruit is a judicial policy that allows a party to recover losses in the absence of an agreement or binding contract.
- By allowing the recovery of the value of labour and materials, quantum meruit prevents the Unjust Enrichment of the other party.
- In the absence of an agreement or formal contract, a party that has provided a good / service may be unable to recover losses in court if the transaction goes wrong.
What are the different ways in which a contract can be made?
- Oral – Construction Act applies to oral as well as written.
- Under hand – Contracts that are simply signed, although not always, by each party to the contract.
- Under deed – A more formal document than a contract under hand. In most cases it is optional to execute document as a deed.
How is a contract converted from under hand to under deed?
The contract should state somewhere (e.g. in the first line) that it is a deed;
The appropriate signature blocks for deeds should be used.
What is the main legal difference between under hand and under deed?
There is no need for ‘consideration’ in a contract made as a deed (signed by both parties).
The limitation period (the time limit for commencing legal proceedings) is 6 years from the breach of contract in the case of contracts under hand, and 12 years from the breach of contract in the case of deeds.
What are the key elements of a contract executed under hand?
- Only an expression of approval/agreement is required.
- Assent does not have to be in written form. If written a signature is not necessary. If written and signed (no witness required), delivery is not required.
- For the validity of an informal contract, written is necessary only when at least one of the parties has expressed an intention not to be bound without one. In such a case, the agreement must be put in writing, and that writing must be presented to this party for an expression of assent.
- Limitation period is 6 years from when the cause of action occurred (breach of contract).
- Effective on execution.
What are the key elements of a contract executed under deed?
- Can be executed in three ways:
1. by the signature of a single director in the presence of a witness;
2. affixing its common seal in the presence of two directors or a director and secretary;
3. by the signature of two directors, or a director and secretary. - Limitation period is 12 years from when the cause of action occurred (breach of contract).
- Must be clear on contract that is to be a deed.
- Effective once signed copy of agreement is physically delivered to representative of other party.
What are the key requirements for a contract to be made binding?
- Offer by one party
- Acceptance by the other party
- Consideration of the offer
- Intent to form a contract
- Legality of contract
- Capacity to make an agreement
What are common contract documents?
a) Conditions of contract and any amendments to standard forms
b) Preliminaries
c) Contract sum analysis
d) Drawings
e) Specifications
f) Existing building information
g) Any contractor’s proposals for CDP work
Who needs to understand the contract?
- All parties mentioned in the contract including the Employer, design team, consultants, Contractor and those involved who are not mentioned.
What project elements to consider when deciding on the most appropriate a form of contract?
- Time / Cost / Quality objectives.
- Experience of client.
- Level of client design input.
- Level of risk the client is willing to take.
- Level of administration.
What forms of contract are there?
1) JCT (Joint Contracts Tribunal)
2) NEC3 (New Engineering Contract)
3) ICE 7 (Institute of Civil Engineers)
4) GC Works (PACE – Property Advisors to the Civil Estate)
5) FIDIC (International Engineers Federation)
Name the main types of JCT contract
a) Minor works
b) Intermediate
c) Standard building contract
d) Major Projects
e) Design and Build
f) Prime cost contract
g) Measured Term contract
h) Construction Management Agreement
i) Management Contract
j) Framework Agreement
What standard forms of JCT contracts are you aware of?
- JCT SBC 11 With Quantities
- JCT SBC 11 Without Quantities
- JCT SBC 11 With Approximate Quantities i.e. Remeasurement
- JCT Prime Cost Building Contract i.e. Cost Plus
When would you use JCT Minor Works?
- Projects that are short in duration, small and simple
- Guidance is for a value up to £150,000
- It is a short, easy to follow contract
- It is a lump sum form; design should be completed prior to execution
- Not as comprehensive as others – limited claims provisions, no fluctuations
When would you use JCT Intermediate Contract?
- Recommended for project that do not exceed one year’s duration or up to £750,000
- For projects that are simple in content, require only basic skills and trades and where services are not complex and where the works are already designed
When would you use JCT Standard with quantities?
- Work has been designed prior to contract;
- Employer provides drawings and bills of quantities to specify quantity and quality of work;
- It is a lump sum form of contract;
- The contractor’s risk is limited to price only;
- The employer takes the risk of errors in the bill.
When would you use JCT Standard without quantities?
- Work has been designed prior to contract;
- Quality of work and degree of complexity is not such to require bills of quantities;
- Contract documents to include drawings (description of work) and with specification or activity schedule;
- It is a lump sum form of contract;
- The contractor’s risk includes both price and quantity.
When would you use JCT Standard with approximate quantities?
- Work has not been fully designed prior to contract;
- Employer provides drawings and approximate bills of quantities;
- This is a re-measurement form of contract – Contract price is based on a tender figure which is converted to a final sum on re-measurement and valuation of all work;
- There is no contract sum;
- Construction is wished to commence prior to the design being completed
When would you use JCT Major Works?
- Projects that are significant in both size and quantity
- Generally for clients that have their own in house contractual procedures