Contract Practice COPY Flashcards
(157 cards)
What constitutes a contact?
Offer Acceptance Consideration Intention Capacity Legality
What are the NEC main options?
There are 6 main options;
A) Priced contract with an activity schedule
B) Priced contract with a bill of quantities
C) Target cost contract with an activity schedule
D) Target cost contract with a bill of quantities
E) Cost reimbursable contract
F) Management contract
What are the clause headings in a JCT Contract?
Recitals Articles Contract Particulars Attestation Conditions of Contract Schedules
What is included in a set of Contract Documents?
Preliminaries Contract Sum Analysis / Pricing Document Scope of Works Specifications Drawings Schedule of Amendments Pre-Construction Information
What are the JCT Payment Provisions?
7 days prior to due date, contractor to submit application for payment
5 days from due date contract administrator shall issue their interim certificate
14 days from due date is the final date for payment
5 days prior to final date for payment employer may issue a pay less notice
Tell me the differences between JCT and NEC contracts?
The NEC uses 6 main options whereas the JCT is a suite of different contract
The NEC is written in layman terms whereas the JCT used legal wording
The NEC does not mention a QS, only a project manager
The NEC uses Compensation Events whereas the JCT used Variations
The programme is a contract document in NEC. 25% of monies can be withheld if a compliant programme is not submitted
Bill rates are binding for Variations under JCT. In NEC they are not, the cost of Compensation Events is built up from first principles
What other types of Contract are you aware of?
ICE - for civil engineering works
GC Works - Government forms of contract
FIDIC - International Federation of Consulting Engineers
What happens at Practical Completion?
Once the Contract Administrator issues the certificate of Practical Completion;
Liquidated Damages cease to be levied
The Defects Rectification Period begins (usually 12 months)
Possession of the site passes to the employer
Insurance of the works passes to the employer (if not already in their name)
Half retention is released (the remaining half is release once the Certificate of Making Good is issued)
What is a Relevant Event?
An event which would entitle the contractor to apply for an Extension of Time (Liquidated damages are not levied for this period).
Variations
Exceptionally adverse weather
Force Majeure
Deferment of possession of the site by the employer
Specified Perils?
What is Loss and Expense?
Construction contracts generally provide for the contractor to claim direct loss and expense.
The works must be materially affected by the relevant matter(s) for which the client is responsible.
Claims are for direct loss and therefore consequential loss is generally excluded.
What is a Relevant Matter?
An event which entitles the contractor to make an application for Loss and Expense.
Deferment of possession of the site by the employer
Suspension of the works
Instructions (around opening up / inspection works / provisional sums)
Delays in receiving instructions
Discrepancies in contract documents
Disruption caused by works carried out by the client
What is the purpose of a Loss and Expense claim?
A claim for Loss and Expense should put a contract back into the position they would have been in, should the Relevant Matter not have occurred.
What are the Heads of Claim for Loss and Expense?
Prolongation
Insufficient use of plant, labour, materials
Increased cost of plant, labour, materials
Loss of Profit
Head office overheads
Finance charges / interest
How is a Loss and Expense claim paid for?
Contractor must give written notice of a claim as soon as it becomes reasonably apparent.
Once the total loss and expense has been ascertained, is should be added to the contract sum and paid on the next interim certificate.
Loss and expense claims are NOT subject to retention.
How does payment option Alternative A in the JCT Design & Build Contract work?
Alternative A is to use stage payments.
Stages are clearly identified in the Contract Particulars. E>G Substructure
Payment for that stage is released upon completion
JCT D&B makes no mention of a QS, so this is a simplified payment option that an Architect could manage
It can incentivise the contractor to complete stages promptly
What is a Specified Peril?
Specified perils tend to be significant events that would cause very significant damage, such as fire, explosions, earthquakes, flooding and so on. All-risks insurance will tend to cover a broader range of risks, albeit it may not cover every possible risk0
How do you agree a Variation?
Variation is a modification to the design, quantity or quality of the work.
1) Use a contract rate - if there is a bill item of a similar nature
2) Use a star rate - this is based on experience of what is fair and reasonable
3) Use dayworks - Prime cost + labour + materials + plant + % additions (% addition for contractor profit is NOT included)
4) Benchmark / market testing
Name the JCT Suite of Contracts.
JCT Standard Building Contract with / without / with approximate quantities
JCT Intermediate Contract
JCT Minor Works Contract
JCT Measured Form Contract
JCT Prime Cost Contract (Cost Reimbursable)
JCT Target Cost Contract
JCT Design and Build Contract
JCT Management Contract
JCT Construction Management Contract
JCT Framework
JCT Construction Excellence for Partnering
What are the drawbacks of a Bespoke Contract?
Costly
Time consuming to produce
Untested in court
What are the benefits of a Bespoke Contract?
Contracts can be made simpler
Contracts can be made easier to administer
Contractor may have input
Risk should have been allocated equitably between parties
Contract can include incentives for contractor to reduce costs
Employer benefits from clear, tailored allocation of risk and responsibilities
Would you recommend a Bespoke Contract?
No. They are untested in court. The principle on Contra Referendum means that an ambiguous clause with be interpreted against the party who wrote it.
What do you know about the Housing Grants Construction and Regeneration Act 1996?
Intended to make sure payments are made promptly and to improve cashflow throughout the supply chain. Also intends to make sure disputes are resolved quickly.
Provisions of the act include;
The right to be paid interim, periodic or stage payments
The right to be informed of the amount due or any amounts withheld
The right to suspend performance for non-payment
The right to adjudication
Disallowing pay when paid clauses
Are you aware of the Local Democracy, Economic Development and Construction Act 2009?
The act now applies to contracts that are not in writing
It is no longer allowable to define within a contract who will bear the cost of adjudication + adjudicator can correct clerical error
Closed loophole in pay when paid clauses
What should you do before terminating a contract?
Discuss the situation with the employer and other party
Take note of all relevant clauses for termination
Seek expert assistance
Write and serve notice in accordance with the contract, detailing the breach
Assuming the breach continues and after the requisite time period, dispatch further notice if the contract requires one
Prepare documents, final account, secure site, alternative contractor