Contracts & Legal Flashcards
G704-DB
Certificate of Substantial Completion for OWNER to fill out because owner takes on that responsibility in DB
G732
Application and Certificate for Payment - CM Adviser Edition anticipates that the architect and the constructionmanager-adviser may certify a different amount than that applied for, with each initializing the figures that have been changed and providing explanations accordingly.
G612
Owner’s Instructions to the Architect Regarding the Construction Contract, Insurance and Bonds, and Bidding Procedures is a questionnaire used to obtain information from the owner necessary to arrive at a construction contract through the bidding process.
D200
Project Checklist identifies tasks and data necessary to fulfill assigned project responsibilities. It can also serve as a permanent record of owner, contractor, and architect decisions.
G716
RFI
Project Authority Matrix
Can be found in A201. Designates if O, A or C must approve contract elements.
G711
Architect’s Field Report
G702
Application and Certificate for Payment. GC shall submit itemized application for payment to architect at least 10 days prior to date established for progress payments in accordance with schedule of values. Needs to be notarized, contain supporting data and reflect retainage. Can include payment for work authorized by CCD. Architect has 7 days to review/approve. The owner could have as little as 3 days to make payment. Certificate for payment does not constitute acceptance of Work not in accordance with CDs. Look for progress and quality.
G703
Continuation Sheet / Schedule of Values: Required for stipulated sum or GMP contracts
G701
Change Order: prepared by the architect, signed by the opener and contractor stating their agreement on: 1. Change in the work2. Change in contract sum, if any3. Change in contract time, if any
G714
Construction Change Directive: prepared by the architect, signed by the owner and architect directing agreement on on contract time, sum or both. Once a contractor signs it, it will become a change order.
G710
Architect’s Supplemental Instruction: used for minor change in the work. Only needs architect’s approval. Architect submits in writing and if contractor thinks there is a change in contract sum or time, he should inform the team and not proceed until approved. If they proceed with the work anyway, they waive the right to the change in time/money.
G704
Certificate of Substantial Completion
Post-construction additional services
Lists found in B101 and D200: Post Occ Eval, construction as-builts, commissioning, LEED, FFE, Interior Design, warranty review, move-in assistance, energy analysis
Contracts for post-construction additional services
2 ways: G802, Amendment to the Professional Services Agreement adds services to original agreement (statute of limitations has already begun). B101 creates another contract and statutes timeframe begins again.
Performance Bond
Statement by surety company that obligates them to complete construction on a project if the contractor defaults on their obligations.
Payment Bond
An amount of money guaranteeing that the contractor will pay subcontractors, vendors, and suppliers for their work free of liens.
Spearin Doctrine
1918 Court Ruling: If the contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications. However B101 and the professional standard of care does not require defect-free documents (nor does it allow negligence). The difference between defect-free documents and the professional standard of care is often called the Spearin Gap. The costs associated with document defects that fall within the professional standard of care are borne by the owner.
The Work
Construction and services performed by the contractor per the contract.
The Project
Total construction including the Work and any other work provided by the owner or his consultants.
Owner’s right to stop the work
A201 2.3If the connector fails to correct work that is not in accordance with CDs, or repeatedly fails to carry out the work per the CDs, the owner may issue written order to the contractor to stop the work or any portion thereof until cause is eliminated.
Owner’s right to carry out the work
If the contractor defaults or neglects to carry out the work in accordance with the CDs and fails to commence correcting it within 10 days of receiving written notice from the owner, the owner may correct it themselves. Contractor must pay for owner’s expenses and any add services from architect. Architect must approve these actions.
A201 3.2.3 requires the contractor to do what if he discovers a nonconformity in the CDs?
Promptly report it to architect. Failure to do so may result in liability for remediation costs.
When do warranties start?
A201 3.5/9.8.4At substantial completion