Cost Estimation: Flashcards

(36 cards)

1
Q

Cost estimation is a blend of ___ and ____.

A

Art, Science

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

True or False: a high degree of accuracy is attainable without much effort

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Factors that affect cost estimation?

A

Optimism
Marketing
Blaming/Killing the messenger
Scoping of requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Ways to get better cost estimates:

A
  1. Study lessons learned
  2. insist on estimation integrity
  3. Analyse cost early on
  4. Define project better
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Estimation Methods:

A
  1. Bottom up analysis
  2. Analogous Estimating
  3. Parametric Esimating
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Estimation Method: Bottom up Analysis

A

estimate based on material/labor costs

not appropriate for conceptual design phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Estimation Method: Analogous

A

Experience based approach (heuristic)
based on similar products
can be applied at any level
Not flexible during trade studies due to limited past cases

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Estimation Method: Parametric

A

Based on CERs (Cost Estimation Formulas)
Can apply complexity factor for changing tech
Accounts for hardware dev

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost Estimation methods with appropriate lifecycle phase:

A

Pre A & A - Parametric
B - Any method
C - Bottom up (detailed)
D - Bottom up (detailed)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

True or False: Use of the detailed cost estimation method increase over project maturity.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

True of False: Use of the parametric cost estimation method increases over project maturity.

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Pros & Cons: Parametric Estimation

A

Pros:
- less time consuming
- more effective for what ifs
- More consistent estimates
- Traceable to past space systmes
Cons:
- applicable to set range of historical data
- Must adjust CERs for new technology an shit
- Usually not accurate for later phases in project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

CER

A

Cost Estimate Formula:

We fit curves to data points between some measured parameter (weight/volume) and associated cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

We should ____ historical data to account for gradual inflation over time when using the parametric estimation method.

A

Normalize/Adjust/Account for

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The ‘complexity factor’ for a CER ______ with the increase in component design changes.

A

Complexity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

CER Complexity Factor:

A

Used to adjust CER for unique features unaccounted for in historical data.

17
Q

What is the learning curve for cost estimation?

A

The idea that we learn how to use less resources and do things faster with each iteration of a design.

18
Q

Formulae: Learning Curve

A
Y = k*x^n
Y - production effort unit (hours,$)
k - first unit effort
x - number of units
n - learning factor (percentage)
19
Q

The learning curve factor for aerospace projects is approximately ____ %.

20
Q

Cost estimates include ____ aspects of mission effort

21
Q

Multi-System Wraps:

A

costs incurred when integrating subsystems

22
Q

Cost distributions skewed to the right are ____ costly.

23
Q

Cost distributions skewed to the left are ____ costly.

24
Q

The _____ _____ _____ is a method used to sum cost distributions.

A

Monte Carlo Simulation

25
What does an "S-Curve" show?
The cost risk relationship
26
The ______ is a result of the statistical summation of cost distributions.
S-Curve
27
An S-Curve shows _____ that a project will cost an estimated amount or less.
Confidence
28
We want the S-Curve to track to the ____ as the project matures.
Left: results in higher probability of lower cost.
29
What is cost phasing?
Spreading the estimated cost over the design phases, years, or other time metric.
30
Complex, single copy, projects have a ___, ___ skewed BETA curve. (left, right, even short, tall)
Tall, Left
31
Complex, multiple copy, projects have ____, ____ skewed BETA curve. (left, right, even short, tall)
Tall, Even
32
Simple, single copy, projects have ____, ____ skewed BETA curve. (left, right, even short, tall)
Short, Even
33
Simple, multiple copy, projects have ____, ____ skewed BETA curve. (left, right, even short, tall)
Tall, Right
34
A beta curve shows the relationship between ____ and ______
Cost and time
35
True or False: wraps cost 33% of project
True
36
True or False: 75% of recurring cost is incurred by the CDR.
False. | 75% of non-recurring by CDR