critical path analysis Flashcards

(6 cards)

1
Q

what does a precedence/ dependency table show?

A

a table which shows which activities must be completed before the others are stared

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what does a dummy activity show?

A

dependencies between activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

does a dummy activity have weight?

A

no

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

at most how many activities can there be between any two events?

A

one

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what does a late event time do?

A

latest time can be left without extending project time

How well did you know this?