Critical path analysis Flashcards

(22 cards)

1
Q

What is a precedence table?

A

A table which shows the activities that each activity is dependent on

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is an event?

A

The completion of an activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is an activity on arc network?

A

A way of representing each activity’s dependencies in network form

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Describe an activity on arc network

A

The activities are represented by edges, and the events are represented by vertices. Each edge has an arrow defining its direction. It is convention to use straight lines for edges

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a source vertex?

A

A vertex with an indegree of 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a sink vertex?

A

A vertex with an outdegree of 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a dummy activity?

A

An activity which has no weight, but is used when it is otherwise impossible to show an activity being dependent on several events, or to avoid two activities sharing an edge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the early event time of an event?

A

The earliest possible time that it can occur

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How can the early event time of an event be calculated?

A

Starting from the source vertex and working forwards, it is the longest possible path into the event

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the late event time of an event?

A

The latest time that it can occur without delaying the overall time of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How can the late event time of an event be calculated?

A

Starting from the sink vertex and working backwards, it the longest possible path into the event subtracted from the sink vertex’s early event time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the float of an activity?

A

The amount of time that its start may be delayed without affecting the duration of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How can the float of an activity be calculated?

A

Latest finish time - duration - earliest start time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a critical activity?

A

An activity with a float of 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a critical path?

A

A path from the source vertex to the sink vertex which entirely follows critical activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What can be said about the vertices on a critical path?

A

The early event times and the late event times are equal

17
Q

Describe a Gantt chart

A

The number scale represents elapsed time. The critical activities are all shown on the same line at the top. All other activities are shown on their own line, with a solid box representing the earliest start time and the duration, while a dotted box extends to the latest finish time, showing its float

18
Q

How can one work out which activities must be happening on a certain day from a Gantt chart?

A

It is all activities whose solid box must lie on the imaginary vertical line drawn on the appropriate time

19
Q

How can one work out which activities may be happening on a certain day from a Gantt chart?

A

It is all activities whose solid box may lie on the imaginary vertical line drawn down the appropriate time after being moved around within its dotted box

20
Q

What assumptions must be made when scheduling?

A
  • Each activity is completed by a single worker in the time given as the duration of the activity
  • Once an activity has started, it must be completed by the worker
  • Once a worker has completed an activity, they become immediately available to start another activity
21
Q

Which worker should always be used when scheduling?

A

The first available one

22
Q

What should be done if there is a choice of tasks for a worker?

A

Assign the one with the lowest latest finish time