Critical Path Analysis Flashcards

(15 cards)

1
Q

What is a precedence/dependence table?

A

A table that shows which activities must be completed before others are started

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is an activity network? (3)

A

A network where activities are represented by arcs and the completion (events) are represented by nodes
The source node is the first node (represented by 0 or 1)
The sink node is the final node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a dummy activity?

A

An activity with no time or cost, used to show dependencies between activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why is it important that there is only one activity between any two events?

A

Every activity must be uniquely represented in terms of its events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is duration?

A

The length of time an activity takes to complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is early event time?

A

The earliest time of arrival at the event, allowing for the completion of all preceding activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is late event time?

A

The latest time an event can be left without extending the overall duration of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the forward pass? (3)

A

Calculates early event times
Starts from source node
Choose highest numbers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the backward pass? (3)

A

Calculates late event times
Starts from sink node
Choose lowest numbers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a critical activity?

A

An activity where any increase in its duration results in a corresponding increase in the overall duration of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a critical path? (2)

A

A path from the source node to the sink node, using only critical activities
The longest path in a network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does every network have?

A

At least one critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the total float of an activity? (2)

A

The amount of time that its start may be delayed without affecting the duration of the project
Total float = latest finish time - duration - earliest start time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the float of a critical activity?

A

Zero

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a Gantt chart?

A

A graphical way to represent the range of possible start and finish times for all activities in a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly