Formal and informal plans, policies, procedures, guidelines, completed schedules, and risk data in any organization are best known as
OPAs
Capitalizing on cultural team differences, focusing on sustaining a culturally diverse project team and encouraging team members to work together are examples of
develop project team
If a contractor is concerned with fluctuation in prices due to project length, you can ease them by doing what?
adjusting a fixed price contract with economic price adjustment.
What is used during the control scope process as a comparison to actual results to determine variance?
scope baseline
Team performance WILL/ WON”T help PM work with team to determine project roles, responsibilities, and reporting relationships?
NOT
The staffing management plan describes how human resource requirements are met on a project. It includes the ___
staff release plan
Name the 3 inputs to develop project team
- project staff assignments
- HRM plan
- resource calendars
Analogous estimating is also called
top-down estimating
Inspections have 4 synonyms. Name them
- review
- product review
- audit
- walkthrough
The BAC IS/ NOT dependent on the EAC.
NOT
Resource leveling CAN/ NOT cause the critical path to change
NOT