Deck 6 Flashcards

1
Q

Crashing the project requires

A

additional resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Fast tracking is a schedule compression technique in which

A

activities planned to be done sequentially are done in parallel resulting in a shorter project duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Resource leveling increases

A

project duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Portfolio management is managing projects, programs and other work as a group to

A

meet strategic business objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Procurement negotiations CAN/ CANNOT be started during plan procurement management process

A

NOT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which tool/ technique is most important to the PM during the development of project charter?

A

Expert judgment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which process will PM perform to create the schedule baseline?

A

Develop schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the best place to look for a good reference for a new metric?

A

Enterprise Environmental Factors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How does PM verify that the project deliverable quality is low?

A

With a walk through/ inspection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

If SV is positive, SPI must be

A

Above 1.0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A process is considered out of control if

A

any data point exceeds a control limit or if seven consecutive points are above or below the mean

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a formal method of sending a summary of the approved changes to all stakeholders?

A

Status report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Flowcharts are defined as

A

diagrams of the section of actions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Fishbone diagrams (ishikawa) are defined as

A

cause and effect diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Decision trees defined as

A

Depicting decisions and aspects of a decision such as utility, probability, cost or outcomes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Influence diagrams are defined as

A

visually depicts risks, decisions, and impacts and how they influence each other

17
Q

What activity ensures the composition of a project’s configuration item is correct and that the corresponding changes are registered, assessed, approved, tracked and correctly implemented?

A

Configuration control

18
Q

Which measurement is the calculated projection of cost performance that must be achieved on the remaining project work to meet a specified management goal?

A

To complete performance index (TCPI)

19
Q

Where would you find project approval requirements?

A

Project charter

20
Q

Cost of conformance includes

A

inspection costs, prevention costs, training, document processes, equipment, appraisal costs

21
Q

Which plan is NOT an input in the identify risks process?

A

Scope management plan

22
Q

Which document does NOT require an approved change request when it is changed?

A

Project charter

23
Q

Crashing is a schedule compression technique that is performed by doing what?

A

allocating more resources or approving overtime. This method is useful when additional resources will shorten the duration of the project.

24
Q

In what process do you perform both resource leveling and modeling techniques?

A

Control schedule

25
According to Maslow's hierarchy of needs, paying a financial bonus or increasing the salary satisfies the ___ need.
safety
26
EEFs are inputs to all processes EXCEPT
collect requirements
27
Which of the following statements is NOT true about risks on a project?
Risks can only have negative impacts on the project objective
28
What does the "Rule of Seven" refer to for control charts?
Seven data points in a row falling on one side of the mean
29
Which forecasting method can be used in the monitor and control process?
Scenario building
30
What are three tools and techniques in the develop project team process?
interpersonal skills team-building activities Recognition and rewards