Design and Specification 3 Flashcards
Allendale Road: What were the clients/project requirements?
The primary requirements were:
- Provide a new roof covering as water ingress evident.
- Minimise capital expenditure
- Provide break out areas to the roofs.
Allendale Road: What statutory matters did you consider?
Party Wall - No
Planning - Yes to terrace areas.
CDM - Yes (carried out in house by NCC)
Building Regulations:
A - Was the structure fit for break out areas and balconies?
B - Means of escape, fire detection etc.
C - Moisture (roof)
K - Hand rails for protection from falling (1100mm minimum)
L2B - Upgrade thermal insulation due to replacement of the water proofing layer. (0.18 uValue required)
Allendale Road: What drawings did you provide?
- Roof plan drawing
- Sections and details which were drafted from Construction Technology book by Greeno and Chudley.
This allowed various suppliers such as Sika, Bauder and Moy to price for the works on a ‘Or Similar’ basis.
They all use similar BBA systems.
Allendale Road: Why was the roof thermally insulated?
Its a requirement of Approved Document L2B as more than 50% of the individual roof coverings or 25% of the entire element was being renovated which is classed as a Major Renovation.
(i. e. element being renovated was the water proofing layer)
(0. 18 uValue required)
Allendale Road: What other roof covering options did you consider?
- Liquid applied as its good for detailing and guarantees can be topped up. (too expensive!)
- Considered single-ply to the roof terraces however, too weak as ‘single membrane’ which wouldn’t be suitable for the works as the building has a lot of plant on the roof.
- Bitumen system selected as a little more expensive than single ply though a lot more robust which was needed for the plant.
Allendale Road: Why did you specify a warm roof system to these areas?
Rejected: cold roof - as wanted to minimise disruption internally.
Rejected: inverted roof - as more costly to repair.
Selected: warm roof - as most economical option.
Allendale Road: How had the existing bitumen roof covering fail?
- UV degraded and brittle with age (bitumen subject to extensive thermal changes which can then cause cracks/rips to appear)
- Joints delaminated by water (standard with laps/joints as they’re exposed to wind and rain)
Allendale Road: Why did you specify a new modified bitumen roof covering?
A strong surface was required due to the extensive plant on the roof.
The bitumen system is more robust due to having more layers appose to a single layer ‘single ply’ system.
Although cost was a key issue and a single ply was slightly cheaper, the cost difference between that and bitumen system was minimal.
Allendale Road: How long does a bitumen roof covering or single ply usually last?
Both are the same being around 30-40 years.
Allendale Road: Why did you use tapered insulation?
- Increase the falls of the flat roof as they were poor.
- Phenolic insulation suitable due to this as wool couldn’t attain these falls.
- Polystyrene discounted with the client as flammable.
Allendale Road: What thermal requirements were there?
0.18 – Refurbishment requirements for flat roof.
Was classed as a Major Renovation of the thermal element as more than 25% of the surface was being re-covered.
Allendale Road: How did you design the build up?
Chudley and Greeno – Construction Tech book, this allowed me to go to different manufactures on a hybrid performance basis.
Allendale Road: Explain the difference between cold, warm and inverted?
Cold – Insulated below the roof deck
Warm – Insulated above the roof deck.
Inverted – Insulated above the roof deck but the water proof layer in below the insulation.
Note: VCL’s are all fitted below the insulation on all systems. Though, Bauder states no VCL required for inverted systems.
Allendale Road: Tell me about the parapet requirements?
Approved Document K – 1100mm
Allendale Road: What other regulations did you consider?
CDM 2015
CAR 2012 – Client had reports on file.
Allendale Road: Was your spec prescriptive or performance? And what are these?
Hybrid approach (though, more prescriptive)
Prescriptive provides in depth detail specifying exact items.
Performance on a descriptive and open basis allows contractors to propose solutions -riskier!!
Allendale Road: What other roof coverings did you consider and why weren’t these suitable?
Single-ply system was considered; though, the surface is generally weak and wasn’t suitable as there were extensive plant/machinery to the roof.
Liquid - too expensive.
Allendale Road: How does blistering occur and what would you advise if its minimal?
Moisture trapped under the covering trying to escape as evaporation occurs.
If small and not causing any issues leave!
If large pop the blister and patch repair, further investigate any breaches which has caused the water to enter.
Investigate where water has entered and resolve.
Harley Terrace: What was included in your technical drawings?
Floor plans
SofW
Specified: Structural details Materials Fittings/fixtures Electrical installations
Harley Terrace: When did Building Control approve the drawings?
Partially approved during pre-construction and fully approved following SE’s input.
Harley Terrace: What had caused the bulge to the rear wall?
Failed wall ties which were subject to corrosion from water/moisture entering cavity.
Wrought iron twist/fish tail wall ties were used.
Harley Terrace: Why didn’t you carry out the party wall notices etc?
I was conflicted as I was lead consultant and a ‘party’ to the works.
Harley Terrace: How did you calculate the provisional sum?
Labour rate on how long I thought it would take.
Harley Terrace: What is a provisional sum and what is a PC sum?
PC sum’s are used to cover items/materials.
Provisional sums are used to cover undefined/unknown works.