Design Economics and Cost Planning Flashcards

(41 cards)

1
Q

What is a cost plan?

A

A detailed understanding of the anticipated cost of a project during the design stages which will inform the budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a cost estimate?

A

A prediction of the cost of a project based on limited information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is NRM?

A

It is a suite of measurement rules for building projects which provides a consistent way to approach the estimation and cost planning process to allow all readers to interpret the information clearly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is in the suite of NRM?

A
  • NRM1 - Order of cost estimating and cost planning
  • NRM2 - Detailed Measurement of Building Works
  • NRM3 - Order of cost estimating and cost planning for maintenance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the purpose of NRM2?

A

It allows Quantity Surveyors to measure and quantify designs in a structured manner for the preparation of BoQ’s.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is risks dealt with under NRM?

A

It does not recommend to assess risks as percentages, but the risks are accurately quantified and priced.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the risk categories under NRM?

A
  • Employer change risk
  • Employer other risk
  • Design Development risk
  • Construction risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the structure of NRM?

A
  • Group Element
  • Element
  • Sub Element
  • Component
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is included in Preliminaries?

A
  • Site establishment
  • Site accommodation
  • Management and Staff
  • Temporary Services
  • Temporary Works
  • Insurance, Bonds and Warranties
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Order of Cost Estimating?

A

A high level estimation given on an elemental/ functional unit basis, i.e. cost per m2, cost per hotel key, etc.

The purpose is to give the likely cost of the project and indicate to the client to make budgetary considerations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the stage/s when Order of Cost Estimates (NRM1) are performed?

A

During RIBA 0-3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the stage/s is when Detailed Measurement (NRM2) is performed?

A

During RIBA 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How are Professional Fees at the Order of Cost estimating stage determined?

A

Through percentages using historical benchmarks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Name some Professional Fees which should be considered under Order of Cost Estimates?

A
  • Design Team Fees
  • Consultant Fees
  • Surveying Fees
  • Legal Fees
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a Provisional Sum?

A

An allowance inserted into a contract price for an element of work that is undefined that a firm cost cannot be determined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are types of Provisional Sums?

A

Defined PSum: An item of work that has been described in sufficient detail, but the design is incomplete.

Undefined PSum: An element of work that is not described well enough and the design is not present.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Under the forms of contract you have used, how are PSums administered?

A

Under FIDIC and ICE forms of contract a PSum is expended through the Engineer’s instruction via an add and omit variation.

Under NEC, there is no facility for PSums.

18
Q

What are the risks associated to PSums?

A

The actual cost and time in converting the PSum may exceed it’s allowance.

However, additional claim for prelims for Defined PSums are not accepted.

19
Q

What are Prime Costs?

A

Cost elements that cannot be determined or agreed upon as a fixed price at the time of tender are instead covered by a Prime Cost rate, which applies solely to the supply of materials and excludes labour, plant, and overheads and profit

20
Q

Under the forms of contract you have used, how are Prime Costs administered?

A

FIDIC and NEC do not allow for Prime Costs, whereas ICE contracts do.

This is administered through the variation process under the ICE contract.

21
Q

What is the RIBA Plan of Work?

A

RIBA 0 - Strategic Definition
RIBA 1 - Preparation and Brief
RIBA 2 - Concept Design
RIBA 3 - Spatial Coordination
RIBA 4 - Technical Design
RIBA 5 - Engineering/ Construction
RIBA 6- Handover
RIBA 7 - Use

22
Q

What is the purpose of a Cost Plan?

A

To inform the client of the estimated cost of a project throughout the design stages to enable them to make budgetary decisions.

23
Q

What does a Base Cost Estimate include?

A

All costs in delivering a project, excluding risk and inflation.

i.e. professional fees, construction works, legal fees, etc.

24
Q

What does a works cost estimate include?

A
  • Prelims
  • Construction costs
  • OH&P
25
What are the key cost planning stages?
- Formal Cost Plan 1: Order of Cost estimating/ planning, based on elemental or functional unit rates, RIBA 0-2, mainly based off historical cost data. - Formal Cost Plan 2: Detailed measurement and prediction of cost from RIBA 3 design. - Formal Cost Plan 3: Detailed measurement and costing based on RIBA 4 design and BoQ is prepared. - Pre-Tender Estimate: Detailed measurement and quantification of cost of the tender information.
26
What are the contents of a cost plan?
- Exec Summary - Version control + changes between cost plans - Market Conditions - Total estimated construction cost - Summary of cost plan (group element breakdown) - Risk Register
27
What does the cost plan help to inform and what can be done to ensure the estimated cost meets their needs?
A cost plan helps to determine whether a construction project is affordable. If not, then value engineering considerations can be made to lower the estimated cost to ensure a value for money outcome is achieved
28
How are professional fees determined under a cost plan?
If the cost of the relevant fees are know, then that should be utilised. If it is unavailable an estimated percentage approach can be used based on historical benchmark data. NRM provides guidance in respect to this.
29
What are some of the adjustments performed on a cost plan to ensure a more accurate estimation?
- Location factor adjustment - Tender Price Index adjustment
30
What information accompanies a cost plan?
- Cover Letter - Exec Summary - Basis of cost plan: drawings/ design information, assumptions and exclusions. - Cashflow forecast - Value Engineering - Risk Register
31
What is a Pre-Tender Estimate?
An estimate of the works/ services which have included under an ITT. The tender returns are then used to perform a comparative analysis against the PTE.
32
What is the purpose of risk allowances?
It serves the purpose of including sums of money to account for unknown events that may occur during the course of the project.
33
When considering a fees estimate what items should you consider?
Consultant Fees: - Project and Design Team Fees - Cost Consultant Fees - Survey Fees - Legal Fees - Specialist Consultants Main Contractor Pre-Construction Services: - Management and Staff Fees - ECI fees - Main Contractor Design Team Fees
34
What factors related to Design and Construction impact a project's costs?
- Design Complexity - Definition of Design - Risk Allocation - Variations - Contract Type - Value Engineering - Law, regulations etc.
35
Name some of the reasons for cost overruns of projects?
- Unclear and changed objective during the project - Unrealistic cost estimates - Uncoordinated design - Poor Project Management and Control - Improper risk management
36
What is BWIC?
BWIC stands for Builder's Work in Connection to. These are mainly civil works to enable a service or element to be incorporated into the permanent works, i.e. coring, drilling, chasing, and cutting.
37
What is Benchmarking?
The process of undertaking a comparison of cost or rates against historical data or other similar data.
38
What is BCIS?
Building Cost Information Services provides cost information online which supports estimating activities.
39
What is CESMM4?
It stands for Civil Engineering Standard Method of Measurement 4th version. It is a measurement guide for the preparation of cost plans and BoQ's which is used predominantly in the infrastructure sector and civil engineering projects.
40
What is the structure of CESMM4?
- First Division - Second Division - Third Division - Measurement Rules - Coverage Rules - Additional Description Rules
41
What are method related charges?
Pricing the means and methods of construction that are not directly measurable through standard BoQ items, i.e. fixed and time related charges.