Design Economics and Cost Planning Flashcards
(55 cards)
What is the difference between an order of cost estimate and a cost plan?
- a cost estimate is prepared earlier on in the design process typically between RIBA Work Stage 0 - 2.
- this is when the level of design information is more limited and allows a cost estimate to be prepared on a cost per m2 or cost per functional unit basis
- a cost plan is produced typically at each RIBA Work Stage from Stage 2 onwards
As the design progresses more information can be included to eventually breakdown the estimated cost of the development elementally
What is the difference between cost and price?
- cost is the total cost of labour, plant, materials and management deployed for a specific activity
- price is the amount a purchaser or client will pay for an item or product and is made up of the cost plus the main contractor’s profit margin
How do you proceed if the cost plan exceeds the project budget?
- I would analyse the costs to assess the source of the increase and identify whether any element of work is abnormally high against the order of cost estimate
- when the reason for the overspend is identified I would then look to propose value engineering options to my client and design team to bring the forecast back in line with the budget.
What is buildability?
it is harnessing the contractor’s expertise and knowledge during the design stage to generate ideas for effective and efficient methods of construction
What are the advantages of build ability?
- can result in better programming, sequencing and construction methods
- a quicker more efficient programme can be achieved
- reduce capital and life cycle costs of the building can be obtained
- the quality in the finished building’s performance and maintenance characteristics can be improved
What is wall to floor ratio?
- this shows the relationship between the wall area and floor area
- it is used to show the cost efficiency of the building
- the lower the ratio, the cheaper the building is to construct as there is less external envelope to construct in comparison to the floor area
What is the most efficient shape?
- a building with a circular floor plate would offer the most efficient design as there is less floor to wall area
- however a circular floor plate has a poor lettable floor area and is difficult to fit out therefore a square floor plate is considered the most efficient
How would you prepare an estimate for M&E works?
- I would ask an M&E specialist surveyor to undertake the estimate
- for feasibility estimates the M&E amount would be included in the m2 or functional unit rate
What is a section 106 agreement?
S106s are agreements between local authorities and developers that are negotiated in the context of granting planning consent
What is construction to ‘shell and core’?
- shell and core is the basic structure, services and envelope f the building
- normally includes the fit out of landlord and common areas e.g. reception, toilets, lifts and stair cores
- basic services are typically terminated at entry points to each of the lettable floor plates however life safety services infrastructure is normally provided
What is a CAT A fit out?
- also known as a developers fit out
- provide generic fit-out items to suit most developers e.g. life safety, suspended ceiling tiles, raised floors, carpets, lighting and power distribution to floor plate
What is a CAT B fit out?
- CAT B overlays the CAT A provisions with bespoke elements that are specific to the needs of the building’s user to enable the tenant to occupy the space
- e.g. partitions, power distribution to the floor boxes, data cabling, artwork, branding, finishes etc
Where could you find the definitions for shell and core, CAT A and CAT B?
The British Council of Offices (BCO) fit-out guide
What is BWIC?
- Builders work in connection and is usually set as a % of the services costs
- It accounts for the main contractor to perform any drilling, fixing, cutting and penetrations to enable the services installation
What is an order of cost estimate?
- the determination of the possible cost of a building early in design stage in relation to the employer’s fundamental requirements
- takes place prior to preparation of a full set of working drawings or bills of quantities and forms the initial build-up to the cost planning process
What is the purpose of an order of cost estimate?
- to establish if the proposed building project is affordable and if affordable to establish a realistic cost limit
- the cost limit is the maximum expenditure that the client is prepared to spend on the proposed building project
What is the format of a feasibility estimate or order of cost estimate?
- this can be presented on a cost per m2, functional unit or elemental basis
- can also be presented as a range
- elemental rates for main elements e.g. substructure, external walls etc
- any site abnormal costs or enabling works
- other inclusions like preliminaries, contingency, inflation and location factor adjustments
What is a functional unit?
- a unit of measurement that considers the prime use of a building e.g. hotel or hospital may be cost per bed
Where would you get your rates from for a preliminary estimate?
- similar projects and historical cost data such as previous tender submissions or a contract sum analysis
- other sources may include estimating price books, BCIS or specialist contractors
What information do you need to be able to carry out an order of cost estimate?
- building location
- type of building
- floor area or number of functional units
- storey height
- whether raised access floors or suspended ceilings are required
- initial floor plans, roof plans, elevations or sections
- requirements for refurbishments to existing building and enabling works
- indication of specification and quality
- programme, procurement and contract strategy
- budget and cashflow restraints
- site conditions and ground conditions
- indicative M&E design intent
- details of professional fees, development costs, VAT and treatment of inflation
What is a cost plan?
- presents the estimated cost of the development into an elemental or functional format
- shows how the design team proposes to distribute the funds available on the different elements f the proposed building
What is the purpose of a cost plan?
- used by the cost consultant to control the development of the design
- identifies the clients agreed cost limit and how the money is to be allocated to the different elements of the building
When would you carry out a cost plan?
- a formal cost plan is typically between RIBA Stage 2 - 4
- stage 2 is concept design
- stage 3 is spatial coordination
- stage 4 is technical design
- a cost plan at stage 4 will typically form the basis of a pre-tender estimate to compare tender submissions against
What are the principle components of a cost plan?
- construction costs
- preliminaries
- contractors oh&p
- contingency
- inflation
- assumptions
- exclusions
- area schedule
- list of drawings and specifications used