DR Extension of Time for WS Flashcards

1
Q

When is court permission needed to extend time to serve a witness statement?

A
  1. If extension of time has an impact on future hearing dates
  2. If 28 day extension between parties cannot be agreed
  3. If witness statement is served late (relief from sanctions)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How to support application for extension of time to serve WS?

A
  • Reasons for delay
  • Any previous breaches of deadline
  • Impact on future hearing dates

Court has discretion and will consider the factors above