Earned value management Flashcards

(17 cards)

1
Q

Actual Cost

A

What the project has spent so far

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Budget at Completion

A

What the project budget is.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Planned Value

A

What the project should be worth.

PV = % planned completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Earned Value

A

What the project is worth

EV = % planned completion x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Variance

A

The difference between earned value and actual cost

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Variance

A

The difference between earned value and planned value

SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost Performance Index

A

Shows overall cost efficiency on the project

CPI = EV /AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Schedule Performance Index

A

Shows overall schedule adherence

SPI = EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate at Completion (Standard formula)

A

Forecast final project costs based on current performance.
Standard formula.

EAC = BAC / CPI

Other note:
as per research and reading, EAC is to forecast scheudle or cost is not very much overruns.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate at Completion (Future work at planned cost formula)

A

Forecast final project costs based on current performance.
Future work at planned cost formula

EAC = AC + BAC - EV

Other note:
as per research and reading, EAC is to forecast scheudle or cost are overruns.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate at Completion (CPI and SPI affect remaider of project)

A

Forecast final project costs based on current performance.

EAC = AC + [ (BAC - EV) / (CPI x SPI) ]

Other note:
as per research and reading, EAC is to forecast scheudle or cost are fucked up overruns and worst case scenario.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Estimate at Completion (Initial cost estimates flaws)

A

Forecast final project costs baed on current performance.

EAC = AC - Estimate for remaider of project

OR

EAC = AC - ETC

Other note:
as per research and reading, EAC is to forecast scheudle or cost are overruns a little bit (not so fucked up).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Estimate to Completion

A

Product how much more the remaider of the project will cost.

ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

To Complete Performance Index (BAC)

A

Predict likelihood of reaching BAC
Great than 1, harder to complete and meet based on BAC.
Less than 1, easier to complete and meet based on BAC.

TCPI (BAC) = (BAC - EV) / (BAC - AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

To Complete Performance Index (EAC)

A

Predict likelihood of reaching EAC
Great than 1, harder to complete and meet based on the EAC.
Less than 1, easier to complete and meet based on the EAC.

TCPI (EAC) = (BAC - EV) / (EAC - AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Variance at Completion (VAC)

A

Projection of being over or under budget based on the current performance.

VAC = BAC - EAC

17
Q

Code: Please Eat Carl’s Sugar Candy SEE The Tuffy Violin.

A
Please = PV
Eat = EV
Carl's = CV
Sugar = SV
Candy = CPI
S = SPI
E = EAC
E = ETC
The = TCPI (BAC)
Tuffy = TCPI (EAC)
Violin = VAC