Earned Value Management Flashcards

(14 cards)

1
Q

PV (Planned Value)

A

Budgeted value of work planned to be done at a given time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EV (Earned Value)

A

Budgeted value of work completed at a given time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AC (Actual Cost (total))

A

Actual cost of work completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BAC (Budget at Completion)

A

The original cost baseline plus or minus all approved cost changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

EAC (Estimate at Completion)

A

Expected total project cost (forecasted based on performance to date)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

ETC (Estimate to Completion)

A

Expected remaining cost (now until project completion)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

VAC (Variance at Completion)

A

Expected variance over/under budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CV (Cost Variance)

A

EV - AC

Negative is bad, Positive is good, Zero is on budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

SV (Schedule Variance)

A

EV - PV

Negative is bad, Positive is good, Zero is on schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

CPI (Cost Performance Index)

A

EV/AC

Under 1 is bad, Over 1 is good, Exactly 1 is on budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

SPI (Schedule Performance Index)

A

EV/PV

Under 1 is bad, Over 1 is good, Exactly 1 is on schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

EAC (Estimate at Completion)

A

.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

EAC (Estimate at Completion)

A

.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

EAC (Estimate at Completion)

A

.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly