Earned Value Management Formulas Flashcards

(12 cards)

1
Q

EV [Earned Value]
also
BCWP [Budgeted Cost of Work Performed]

A

EV = % Complete * BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

CV [Cost Variance]

A

CV = EV - AC

Positive Value ⇒ Good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

SV [Schedule Variance]

A

SV = EV - PV

Positive Value ⇒ Good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

CPI [Cost Performance Index]

A

CPI = EV / AC

Value > 1 ⇒ Good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

SPI [Schedule Performance Index]

A

SPI = EV / PV

Value > 1 ⇒ Good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

EAC (1) [Estimate at Completion]

A

EAC (1) = BAC / CPI

Bigger Value ⇒ Good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

EAC (2) [Estimate at Completion]

A

EAC (2) = BAC + AC - EV

Bigger Value ⇒ Good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EAC (3) [Estimate at Completion]

A

EAC (3) = new_estimate + AC

Bigger Value ⇒ Good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EAC (4) [Estimate at Completion]

A

EAC (4) = AC + (BAC - EV) / (CPI * SPI)

Bigger Value ⇒ Good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ETC [Estimate to Completion]

A

ETC = EAC - AC

Smaller Value ⇒ Good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

VAC [Variance at Completion]

A

VAC = BAC - EAC

Positive Value ⇒ Good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI [To-Complete Performance Index]

A

TCPI = (BAC - EV) / (BAC - AC)

Value < 1 ⇒ Good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly