Earned value mgmt formulas Flashcards

(15 cards)

1
Q

Cost variance

A

Ev - ac
Positive :-) Under budget
Negative :-( Over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned value

A

Percent complete * bac

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Planned value

A

What proj s/b worth

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Budget at completion

A

What the proj budget is

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Schedule variance

A

EV-PV
Positive means :-) ahead of schedule
Negative means :-( behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Variance at Completion

A

Projection of being over or under budget based on current performance
BAC-EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost Performance Index

A

EV/AC
Shows overall cost efficiency of proj
>1 means under budget
<1 means over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Schedule Performance Index

A

EV/PV
Shows overall schedule adherence
>1 means ahead of schedule
<1 means behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate at completion (EAC) - standard formula

A

Forecasts final proj costs based on current performance

BAC/Cpi

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate at Completion - Future work at planned costs formula

A

AC+BAC-EV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate at Completion (EAC) - CPI and SPI affect remainder of project

A

AC + [BAC-EV/(CPIxSPI)]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Estimate at Completion - Initial estimates flawed

A

AC + estimate for remainder of proj

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Estimate TO complete

A

Predicts how much more the remainder of the project will cost
EAC-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

To complete performance index (TCPI) - Utilizing BAC

A

Predicts likelihood of achieving BAC
(BAC-EV)/(BAC-AC)

Greater than 1 - harder to complete and meet BAC
Less than 1 - easier to complete and meet BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

To complete performance index (TCPI) - Utilizing EAC

A

Predicts likelihood of achieving EAC
(BAC-EV)/(EAC-AC)

Greater than 1 - harder to complete and meet EAC
Less than 1 - easier to complete and meet EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly