Estimating Flashcards

(84 cards)

1
Q

When preparing a bid, a contractor must consider

A

profit, overhead, labor and mateiral, and evaluate the effect of unexpected delays on costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

space holder

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

if you place an advertisement which offers a home improvement service for $95 and have no intention of signing a contract for that low of a price this is

A

a misdemeanor and cause for disciplinary action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

a cotractor signs a home improvement contract and accepts a down payment, but never shows up to do the work. what is the fine

A

contracotr is subjected to a penalty of $100-$5000 and or one year in jail

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

you are bidding on a state college job and the work involves new construction. you decide to use subcontractors to do some of the work. you do not however submit the names of any subcontractors

A

you will be responsible for completing the whole contract yourself

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

a contractor finds a 12” discrepancy on a set of drawings for an office building. the contractor should

A

contact the architect or designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

when preparing a bid, which of the following is normally the most difficult to estimate

A

labor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

if a contractors bilingual salesperson makes a presentation to a customer in spanish, the home solicitation contract must also be

A

written in spanish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

the homeowner has drawn plans for the job that you are bidding on and the dimensions on the plans are not accurate. you should

A

notify the homeowner that you cannot bid until proper corrections are made

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

every contractor and estimator considers cost estimating a challenge

A

due to weather, location, number of employees, and each job is different

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

you have prepared a bid which enables you to make a profit, however fthe customer cannot afford it. what should you do

A

do not change your bid unless the scope of the job is reduced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what is job costing?

A

-it assists you in defining costs for future bidding
-assures that cost estimates will be accurate
-it assists you with the labor and material costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

if you are doing a complete package bid including all phases of the new house so that you can give the customer a price that will be complete and you forgot to charge for one phase, what should you do

A

do all of the phases including the one that you forgot to charge for regardless if it means that you will have to absorb the loss

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

the benefit of using job cost cards is

A

to keep accurate costs records for bidding in the future

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

labor costs can be established by

A

taking the hours from the detailed job cost time cards from past jobs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

how do you prepare a bid accurately

A

factor in effects of the unexpected cost of delays

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

job costing is helpful in

A

determining the profit or loss on the job

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

you would not include which of the following in a bid

A

possible legal fees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

the reason for standardizing bidding with your company is that it

A

guarantees the accurancy of cost estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

you know if you are bidding correctly when

A

the job and estimated costs correspond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

what is the best way to access the job that you are bidding on

A

you inspect the job

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

what is the most difficult item to estimate

A

labor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

a contractor should include material, labor and direct costs, permits, profit and ____ when bidding on a home improvement contract

A

overhead costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

in order to ensure no errors in the bid, you should

A

double check the bid prior to submitting it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
what does direct labor consist of
actual cost of the labor payroll
26
when bidding a job, it is alright to
double check your estimate
27
job costs cards do not provide any benefit in
keeping cost records that are accurate for bookkeeping
28
what is the usual procedure for the contractor if changes have been made to the original construction documents after the project has been issued and work has commenced
the contractor should have a signed change order for the additional costs
29
the most important element of a contract between the parties involved is
mutual agreement
30
which of the following generally summarizes the work and closeout of the project
general requirements
31
on large jobs, the person usually in charge for guaranteeing that the project drawings are in accordance with the building codes and local ordinances is
the architect/ engineer
32
when a contractor agrees to fulfill work or services for a given labor rate per hour and a 15% profit on the cost of materials, this is called a
cost plus fee contract
33
the two basic types of construction contracts are
competitive bid and negotiated
34
construction estimating is the analysis of all the elements in the cost of a project. which of the following is the best description of this
material, labor, equipment, job and company overhead and profit
35
once the documents for a construction projects are completed, bids taken, the contract issued and ____ then the contractor can commence construction
the contract is signed
36
the purpose of an addendum to the bidding and construction documents is
to make changes to the documents prior to the contractor being awarded the contract
37
which of the following is awarded the contract, when the construction documents state a lump sum bid
low bid
38
which of the following is ussually awarded a building construciton contract
the low bidder
39
when working with construction contracts which of the following best depicts front end loading
the practice of contractors overpricing items of work in the beginning of the job
40
the term "time is of the essence in this agreement" is best described by which of the following
specified completion dates must be met
41
a competative bid contract is
a lump sum and unit price contract
42
do most construction contracts allow the owner to change work durring construction
Yes, if the contractor is compensated
43
Construction estimating is best defined by which of the following
analyzing all elements involved in the cost of a building construciton project
44
which of the following person is hired as a full time employee by the contractor preparing materials lists, labor units and other costs for the project that the firm has bid on
estimator
45
when a contractor is submitting a competitive bid on a construction project a ____ is necessary
set of construction documents
46
after a material takeoff, the unit prices are generally put in and the material prices extend to reach a complete cost of material for the job. generally, the next step in the estimate is
to figure the labor units (generally in hrs)
47
who should be contacted if the working drawings are unclear durring the process of takeoff and bidding
the architect
48
a lump sum contract is best described by which of the folloowing
one in which the contractor agrees to perform specific work or services in place of a fixed amount of money
49
Space holder
50
the first step in determining an accurate cost of a construction project iss
making a complete material takeoff
51
a contractors gross profit for a project is determined by which of the following
amount of contract - direct costs - indirect costs gross profit
52
it is the ____ responsibility for the subcontractors work in a standard building construction contract
general contractors
53
the two basic types of construction contracts are
competitive bid and negotiated
54
eevery contractor and estimator consideres cost estimating a challenge
-due to weatehr location, proper numbers of emloyees and otehr problems -because each job is different therby making it difficult to make a takeoff, assignment of labor units and the pricing of construction costs uniform
55
____ shows all bids recieved with teh name of each contractor and the amount of each bid
a bid opening report
56
items which must be included in the bid are costs for permits, borrowed funds and additional insurace and other fees which are all considered ____ costs
indirect
57
which of the following should be charged to individual jobs and not be included in direct labor estimates
supervision
58
when preparing an estimate and the cost of labor and materials are known but the total estimate is not known, you should use ____ to calculate overhead and profit to arrive at the total price
the mark up equation
59
if mistakes happen and all of those bidding did not receive identical bidders documents, it is sufficient cause to have bids cancelled and the entire project
re-bid
60
when preparing an estimate, there are times when a contingency factor might be neccessary. what is a contingency factor
an estimated value figured into a bid that allows for unexpected delays and costs
61
upon competion and acceptance of the job or upon final payment, the owner may request ____ from the contractor
a waiver and release
62
which of the following is not a good practice when bidding on a job
figuring out how to beat the competition
63
If the second lowest bidder challenges the bid and the low bidder is non-responsive, the contention of an award may result in potential:
-litigation -forfeiture of the award -advertising the contract again
64
When preparing an estimate, in what category would you consider equipment and general maintenance
indirect costs
65
which of the following includes all payrool taxes, insurance and employees' benefits assessed against the labor payroll
direct labor burden
66
on a public works job, the prime contractor has ____ after receipt of bids, to submit requested subcontractor information
24 hours
67
to provide a good accurate bid, the contractor must ____ the construction process on paper
plan
68
after receiving all bids, what is the phase of elevation of bids called
bid opening phase
69
when preparing an estimate, which of the following would you factor into the cost of doing the job
cost of performance bond
70
when preparing a bid for a contract, which of the following is most difficult to calculate
labor
71
contract ____ generally exceed the profits and represnt a claim of the working capital
retentions
72
when preparing an estimate, general administration, office help and bad debts are considered an
overhead cost
73
which of the following is essential to the continuation of business and must be included in all bids
profit
74
mike has reviewed plans and specification for a remodeling job for an architect and would like to bid the job. what is his next step
walk the jobsite
75
in order to provide a good accurate bid, it is neccessary for the contractor to carefuly review the job through ____ inspection
on the site
76
durring bidding time when contracts are updated with change orders, all contract bidders will be mailed the updates by
certified mail with a return receipt requested form
77
if you have lost practically every bid that you have placed in the past 3 months, which of the following is most likely the reason
you are trying to make more profit than is realistic
78
what is considered a cost management system
a computer record of all costs of previous jobs
79
work classification calculated provides information on bids for
labor
80
____ should be charged to individual jobs and should not be included in direct labor estimates
supervision
81
overhead and profit are added to the job estimate using ____ based on the total job estimate
a mark up percent
82
____ must not be taken in material cost estimates unless the contractor is certain that sufficient funds are available
cash discounts
83
____ bid is one that meets all of the requirements specified in the notice inviting bids and instructions to bidders
responsive
84
how can a contractor make sure that they will receive progressive payments on time
have the owner open a third party escrow account