EVMS Formulas Flashcards

(16 cards)

1
Q

Cost Variance (CV)

A

CV = BCWP - ACWP

Cost Variance = Budgeted Cost of Work Performed minus Actual Cost of Work Performed

Positive is favorable, negative is unfavorable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

CV %

A

Cost Variance Percentage

CV% = (CV/BCWP) * 100

CV% = (Cost Variance divided by Budgeted cost of work performed) times 100

CV % = ((BCWP-ACWP)/BCWP) * 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Schedule Variance (SV)

A

SV = BCWP - BCWS

Schedule Variance = Budgeted Cost of Work Performed minus Budgeted Cost of Work Scheduled

SV = (what we said we’d get done minus what we actually got done in hours/cost)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

SV %

A

SV % = (SV/BCWS) * 100

Schedule Variance Percentage = (Schedule Variance divided by Budgeted Cost of Work Scheduled) times 100

SV% = ((BCWP - BCWS) / BCWS) * 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Variance at Completion (VAC)

A

VAC = BAC - EAC

Variance at Completion = Budget at Completion minus Estimate at Completion

VAC = Baseline minus Forecast/current Status

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

VAC %

A

VAC % = (VAC/BAC) * 100

Variance at Completion Percentage = (Variance At Completion divided by Budget At Completion) times 100

VAC % = ((BAC-EAC)/BAC) * 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Overall Percent Scheduled

A

% Scheduled = (BCWScum / BAC) *100

% Scheduled = (cumulative budgeted cost of work scheduled divided by Budget At completion) times 100

% Scheduled = (cumulative work scheduled now divided by baseline) times 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Overall Complete Percentage

A

% Complete = (BCWPcum / BAC) * 100

% Complete = (Cumulative budget cost of work performed divided by Budget At Completion) times 100

% Complete = (total work done now divided by baseline) * 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Overall Percent Spent

A

% Spent = (ACWPcum / BAC) * 100

% Spent = (cumulative actual cost of work performed divided by Budget At Completion) times 100

% Spent = ( Actual cost of work done now divided by baseline) * 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost Efficiency or Cost Performance Index (CPI)

A

CPI = BCWP / ACWP

Cost Performance Index = Budget Cost of Work Performed divided by Actual Cost of Work Performed

CPI = Baseline work / actual work done

Favorable is > 1.0
Unfavorable is < 1.0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Schedule Efficiency or Schedule Performance Index (SPI)

A

SPI = BCWP / BCWS

Schedule Performance Index = Budgeted Cost of Work Performed divided by Budgeted Cost of Work Scheduled

SPI = Baseline / Forecast

Favorable is > 1.0
Unfavorable is < 1.0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

BEI - Baseline Execution Index

A

BEI = Total Tasks Complete / (Total tasks with Baseline Finish On or Prior to current Status/data Date + Tasks without baseline finish dates)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Hit Task %

A

Hit Task % = 100 * (Tasks in denominator that completed On or Before baseline finish / Tasks baselined to finish within current status or data date reporting cycle)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

EAC

Estimate at Completion

A

EAC = Actuals to Date + (Remaining Work / Performance Index)

EAC CPI = ACWPcum + [(BAC - BCWPcum) / CPIcum]

EAC SPI = ACWPcum + [(BAC - BCWPcum) / SPIcum]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

EAC Composite

A

EACcomposite = ACWPcum + [(BAC - BCWPcum) / (CPIcum * SPIcum)]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

To Complete Performance Index - TCPI

A

TCPI target = Work remaining / cost remaining

TCPI target = (BAC-BCWPcum) / Target - ACWPcum)

 To Determine the TCPI for BAC, LRE, or EAC Substitute TARGET with BAC, LRE, or EAC
# To Determine the Contract Level TCPI for EAC, You May Replace BAC with TAB