EVMS Terms Flashcards

(28 cards)

1
Q

ACWP

A

Actual Cost of Work Performed

Cost actually incurred in accomplishing work performed = Actual Cost

(Hours claimed/money spent)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

AUW

A

Authorized Unpriced Work

Work contractually approved, but not yet negotiated / definitized

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

BAC

A

Budget at Completion

The sum of all budgets for the contract thru any given WBS/OBS level (Baseline)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BCWP

A

Budgeted Cost of Work Performed

Value of completed work in terms of the work’s assigned budget = Earned value

(what tasks/work was completed)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

BCWS

A

Budgeted Cost for Work Scheduled

Time-phased Budget Plan for work scheduled = Planned Value

(Baseline)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CA

A

Control Account

Lowest CWBS (contract WBS) element assigned to a single focal point to plan & control scope / schedule / budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CBB

A

Contract Budget Base

Sum of NCC (Negotiated Contract Cost) & AUW (Authorized Unpriced Work)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EAC

A

Not the ‘East Australian Current’ navigated by Crush & Squirt

Estimated At Completion

Estimate of total COST for the contract thru any given level generated by
Ktr, PMO, DCMA, etc.

(Forecast after Status updated)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

ETC

A

Estimate To Complete

Estimate of the cost of remaining work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

DCMA

A

Defense Contract Management Agency

Provides contract administration services for the Department of Defense, other federal organizations and international partners, and is an essential part of the acquisition process from pre-award to sustainment.

Provides guidelines for best practices and standards to use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

LRE

A

Latest Revised Estimate

Ktr’s EAC = Contractor’s (SDL) forecast or EAC (estimate at completion)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

MR

A

Management Reserve

Budget withheld by Ktr PM for unknowns / risk management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Ktr

A

Contractor = SDL

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

NCC

A

Negotiated Contract Cost

Contract PRICE minus profit or fee(s)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

OTB

A

Over Targeted Baseline

Sum of CBB (Contract Budget Baseline) + additional budget approved for remaining work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

PAC

A

Price At Completion

EAC (Estimate At Completion) plus adjusted profit and/or fee(s)

17
Q

PMB

A

Performance Measurement Baseline

Contract time-phased budget plan
costed schedule baseline

18
Q

PP

A

Planning Package

Far-term CA (control account) activities not yet defined into Work Packages

19
Q

SLPP

A

Summary Level Planning Package

Far-Term contract activities not yet assigned to a CA (Control Account)

20
Q

TAB

A

Total Allocated Budget

Sum of all budgets for work on contract = NCC, CBB, or OTB

21
Q

TCPI

A

To Complete Performance Index

Efficiency needed from ‘time now’ to achieve a Cost Target = BAC, LRE, or EAC

22
Q

UB

A

Undistributed Budget

Broadly defined activities not yet time-phased for distribution to CAs or SLPPs

23
Q

WP

A

Work Package

Near-term, detail planned activities within a CA (control account)

24
Q

BCWR

A

Budgeted Cost of Work Remaining (BCWR)

  • represents that portion of the budget for work not yet accomplished within a Control Account. It is the difference between the Budget at Completion (BAC) and the cumulative Budgeted Cost for Work Performed (BCWP), or BAC - BCWP cum.
25
CPI
Cost Performance Index aka Cost Efficiency
26
SPI
Schedule Performance Index aka Schedule Efficiency
27
BEI
Baseline Execution Index
28
BOE
Basis of Estimate - details of what went into costing (labor, materials, equipment etc)