Exam 2 Flashcards

(107 cards)

1
Q

what are the stages of the construction project

A
design
pre construction
procurement
construction
post construction
owner occupancy
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what are the 4 steps to the design process

A

programmnig and feasibility
schematic design
design development
contract documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what happens in hte programming and feasibility part of the design process

A

owner will inform designer what they like and often talk about hte budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what happens in the schematic design part of hte design process

A

first step of the creative process
design team starts to consider aesthetic features
design is far enough along that team can outline preliminary specifications and estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what happens in the design development of the design process

A

where much of the detail gets done

specifications become more developed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what happens in the contract documents of the design process

A

final detailed drawings
aka working documents
the docs are rarely perfect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what does the design phase end with

A

bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what happens in the pre construction phase of a job

A

estimators pass the job over to PM
it is about planning the jobs and needs to be done quick
assign project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what does the Project Manager do on hte job

A

leads the build and needs to have a lot of experience in construction. he assembles the possible team, schedule, quality control, cost control, etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what does the contract administrator do

A

assist both PM and Super

process progress payment applications, change orders, or submittals on behalf of the PM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what does the super do

A

responsible for coordinating all the construction activities and keeping the project on schedule
in charge of all direct labor and subs
daily point of contact for the owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what does the field engineer do

A

usually first step to becoming PM
does much of the paperwork
Process and track RFIs submittals and shop drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what is due diligence

A

process of identifying any problems or areas of concern that exists so that those problems can be factored into pre construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what is value engineering

A

it is an analysis of design , products, and materials to say whether they are really the best solutions relative to their cost
the process that may or may not be conducted durring the pre construction phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

what is the procurement stage

A

the part where you buy all the materials you need to build the project and the labor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what is a purchase order

A

agreement to provide certain products for a specified price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

what is a list of things the CM team will need to do before the job ends in the clsoe out phase

A
project punchout
substantail completion
final inspection
certificate of occupancy
commissioning
final documentation
final completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

what is the project punchout

A

the little things that need to be done before the owner moves in

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

waht is the punch list

A

the major adjustments or repairs before substantial completion can be achieved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

what r the two steps to project completion

A

substantial completion

final completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

what is substantial completion

A

occurs after punch list has been completed and the arch approves it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

what is final completion

A

accomplished after all remaining contract requirements have been met such as, insurance of final paperwork and documentation, also certified by architect and sets up the release of all remaining payments due to the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

what is a certificate of occupancy

A

means that the owner can move in

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

what is commisioning

A

showing hte owner how to work the equipment in the building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
what is final documentation
documents given to the owner that can compare to an owners manual, include warranties, opperation manuals, inspecting and testing reports
26
what are as built drawings
record drawings that are turned over to the owner at the end of the project that identifys any changes or adjustments made to teh conditions and dimensions of the work relative to the original plans and specs
27
what is express warranties
written into the contracts, deal with workmanship and instilations
28
what is inplied warrinties
deals withe products and equipment installed in the new facility
29
what is the minimum for most building contracts
most require at least 1 year
30
what is the project evaluation
chance for hte management teams to debrief what worked and what dident
31
what is an estimate
it is an educated guess based on the info given
32
what are the Measure quantities
are from the architects plans and are multipled by the unit costs of Labor, Material, Equipment
33
what happens to the cost as complexity of teh project increases
it goes up
34
when looking into the future how can the time of the job affect the cost
need to anticipate changes in price of materials and the availablity of labor
35
where is the quality of the work defined
in the standards set in the specifications which impact cost
36
what are the types of estimates
conceptual and preliminary and detailed
37
what are conceptual estimates
used when there are no drawings at all. often the owner does not know if teh project is feasible
38
what are preliminary estimates
used when you have a preliminary set of drawings with overall dimensions. should never be used to commit a contract price
39
what are detailed estimates
used when youhave a complete set of plans and specs. counts everything but takes time and skill
40
whate are direct costs
cost that go into building the facility | materials, labor, equipment, subs
41
what are indirect costs
expenses incurred in order to manage and deliver teh materials, labor, equipment, and subs
42
what are indirect costs ofter reffered to as
overhead or General Conditions
43
what are most General conditions a factor of
time
44
what are the 3 things to be concerned with when you estimate
quantities pricing productivity
45
how does the project team prep for estimating a project
reviewing plans and specs pre bid meeting site visit
46
what happens and who goes to pre bid meetings
the estimator usually goes and it allows contractors to get many of their questions answered
47
what does Work Breakdown Structure WBS do
establishes the basic building blocks of estimate and schedule
48
what is the Purpose of the Work Breakdown Structure WBS
to organize and identify the work by breaking down each division into a seperate work package
49
what is a work package
detailed items of work bundled together under a particular trade
50
what makes up the bulk of the construction estimate
sub and vendor bids
51
what are the 4 steps to ensure that the solicitation of the subs and vendors is complete and thorough
soliciting bids reviewing bids analyzing bids choosing bids
52
what happens in the pre construction phase
owner and architect create initial decision, pproject program, project delivery method, and contract form then contract with builder and create the contract form
53
who is invited to the pre construction conference
``` owner arch primary engineer PM and staff public officials ```
54
what is the purpose of the pre construction meeting
to establish the rules that are to be followed and to clarify the lines of authority and communication
55
what is discussed at the pre construction meeting
``` site logistics coordination issues like RFIs and shop drawings schedule issues payment process change order process dispute resolution completion resolution ```
56
what is contract administration
managing the general or supplemental conditionsof the contract need a clear and accurate paper trail
57
what are the typical owner-architect-contractor relationships
antagonistic adversarial suspicious win/lose mentality
58
what are submittals
can range anywhere from specification information to a physical mock up or inplace tests
59
what are shop drawings
drawings of materials to be fabricated for instillation
60
what does CNC files mean
Computer Numerical Control
61
what are mock ups
test the assembly, constructability, appearance, and owner approval
62
what are as built drawigns
provide the owner with a set of drawigns of what was actually installed adn placed
63
what is the information flow
``` sub GC arch (approval or disapproval) GC Sub Installation ```
64
what is the payment process
request from GC to owner, needs bills from subs and vends architect approves or dissaproves GC must pay subs and vends regardless of arch approval
65
what is scheduled values
established at the start of the project, it is the template for measuring work progress
66
what is the pay request continuation sheet
calculation of completed work modified by change orders
67
how often do applications for payment happen
occurs every billing cycle
68
when does the final payment and ending the job happen
occurs after punch list is complet | final submittalss must also be delivered to teh architect
69
after the final payments and ending job what docs need to be recieved
``` as built drawings opperation and maintenence manuals product and equip warranties test reports surplus materials permits Lien-waivers ```
70
what is the carrot approach
each day earlier of the approved schedule leads to mandatory payment from owner to GC
71
what is the stick approach
each day project is late GC pays owner
72
what is another name for stick approach
liquidated damages
73
what is the change order process
instigated by contractor or arch arch presents to owner once approved moves back to contractor
74
what are some of the causes of time extensions
``` severe weather slow response to RFIs delay in owner supplied materials labor strikes etc ```
75
what are the different dispute resolution approaches and which are most costly
mediation least expensive minitrial medium expense arbitration most expensive
76
what happens in a mediation
impartial 3rd party facilitates the talks between teh parties it could still end up in a litigation
77
what happens in a minitrial
combines both mediation and litigation( gets execs from both parties involved) can still end up in litigation
78
what happens in an arbitration
arbitrator sits in essentially as a judge attorneys are present resolution is binding and final
79
what is a Lien-waiver
stating they have recieved payment and waiving any lien rights
80
what is a full litigation
could be decided by a judge and jury
81
what is the Supers job
organize the jobsite setup temporary field office find best way to manage control and coordinate everythign
82
what are construction operations
actual work that it takes to build the project
83
what are axioms
a statement or proposition which is regarded as being established, accepted, or self-evidently true
84
what are the 3 fundamental axioms for scheduling subs
resist bringing subs on to early make sure subs have everything needed pay all subs promply when work is done
85
what are the important steps once material order is placed
will call and delivery confirmation by super reciept and direction of material by onsite mangment inspection of materials
86
what are Will-Calls
a verbal confirmation of an order that has been placed prior to the date it is actually due for delivery. occurs before the scheduled delivery date
87
what affects productivity
cost and schedule
88
what is not a factor of productivity
saftey | the the factors are fairly obvious
89
what managment concerns created by construction itself
noise control dust and mud control environmental protections clean up and trash removal
90
what are some possible environmental issues that could arise on a job
storm water pollution prevention plan SWPPP endangered species on or near the site natural vegitation onsite requiring protection wetlands protection burried historical or cultural artifacts
91
what does a clean site mean
a safe site
92
what 3 things must the super do before construction work can begin
setup field office organize job site establish work hours
93
what are laydown areas
place for large orders to be sorted
94
what are Logs used for
to track regular jobsite activities | phone calls, deliveries, RFIs
95
what is the superintendent diary
notes daily work activities, conversations, observations
96
what are daily field reports
are filled out by super more formal than the diary
97
how can visual records be helpfull
progress photos help document construction methods and capture any problem areas
98
what is included in correspondance and when does it need to be done
``` must be filed and recorded throughout the duration of the project included: submittals change orders RFIs emails payment requests ```
99
who is the front line rep for the company
the super
100
what are the 4 on site managment team members
PM Contract adiminstrator general superintendent field engineer
101
who is in charge of doing the commissioning
GC Subs Arch Engineers
102
What Does ROM stand for and what does it do
Stands for a Rough Order of Magnitude and is a measure of the projects level of effort and cost to complete
103
What is a Work Breakdown Structure(WBS)
a tool used by estimators to organize the work of a contract in a hierarchical fashion
104
what items constitute the burden of payroll taxes
Employers portion of social security workers compensation unemployement tax Employee benefits
105
what is a scope sheet
describes the items of work to be performed under a particular trade heading
106
what are the characreristics in a quality estimate
``` organization correct quantities accurate labor hours correct pricing accurate calculations completeness proper overhead proper profit ```
107
what are quanitity surveyors
people responsible for counting up all of the quantities of materials, labor and equipment necisary for the job