Exam 2 Flashcards
(107 cards)
what are the stages of the construction project
design pre construction procurement construction post construction owner occupancy
what are the 4 steps to the design process
programmnig and feasibility
schematic design
design development
contract documents
what happens in hte programming and feasibility part of the design process
owner will inform designer what they like and often talk about hte budget
what happens in the schematic design part of hte design process
first step of the creative process
design team starts to consider aesthetic features
design is far enough along that team can outline preliminary specifications and estimates
what happens in the design development of the design process
where much of the detail gets done
specifications become more developed
what happens in the contract documents of the design process
final detailed drawings
aka working documents
the docs are rarely perfect
what does the design phase end with
bidding
what happens in the pre construction phase of a job
estimators pass the job over to PM
it is about planning the jobs and needs to be done quick
assign project team
what does the Project Manager do on hte job
leads the build and needs to have a lot of experience in construction. he assembles the possible team, schedule, quality control, cost control, etc
what does the contract administrator do
assist both PM and Super
process progress payment applications, change orders, or submittals on behalf of the PM
what does the super do
responsible for coordinating all the construction activities and keeping the project on schedule
in charge of all direct labor and subs
daily point of contact for the owner
what does the field engineer do
usually first step to becoming PM
does much of the paperwork
Process and track RFIs submittals and shop drawings
what is due diligence
process of identifying any problems or areas of concern that exists so that those problems can be factored into pre construction
what is value engineering
it is an analysis of design , products, and materials to say whether they are really the best solutions relative to their cost
the process that may or may not be conducted durring the pre construction phase.
what is the procurement stage
the part where you buy all the materials you need to build the project and the labor
what is a purchase order
agreement to provide certain products for a specified price
what is a list of things the CM team will need to do before the job ends in the clsoe out phase
project punchout substantail completion final inspection certificate of occupancy commissioning final documentation final completion
what is the project punchout
the little things that need to be done before the owner moves in
waht is the punch list
the major adjustments or repairs before substantial completion can be achieved
what r the two steps to project completion
substantial completion
final completion
what is substantial completion
occurs after punch list has been completed and the arch approves it
what is final completion
accomplished after all remaining contract requirements have been met such as, insurance of final paperwork and documentation, also certified by architect and sets up the release of all remaining payments due to the contractor
what is a certificate of occupancy
means that the owner can move in
what is commisioning
showing hte owner how to work the equipment in the building