Exam questions Flashcards
(166 cards)
Project charter
The team charter can be altered by team member at any time, Project Charter contains Pre-approved financial resources, can be approved by the sponsor or an authorized representative who can take financial decisions as well as provide financial resources for the project. Since Project Sponsor falls under the Upward bracket when stakeholders are classified based on direction of influence
The Develop Project Charter is the process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. This process has four T&T: Expert Judgement, Data Gathering, Interpersonal and Team skills (Conflict management, facilitation, etc.), Meetings.
The project charter includes the Project exit criteria which states the conditions to be met to close or cancel the project or phase. states the conditions to be met to close or cancel the project or phase.
Appraisal
It gets carried out in the Executing processes group, In a Project Performance Appraisal team members get feedback from project work supervisors.
Burndown and burnup charts
A burndown chart shows how much work is remaining to be done, whereas a burnup chart shows how much work has been completed, and the total amount of work. The burnup charts can also show the changes in project scope, making the impact of those changes visible.
They are examples of Data Analysis technique.
The total estimated Project Cost is
EAC (Estimate At Completion).
Risk avoidance
If the project team is trying to get rid of a possible threat by changing the Project Management Plan, is an example of Risk avoidance
Residual and secondary risks
Residual risks are those risks which are expected to remain after the planned response of risk has been taken, as well as those that have been deliberately accepted. Secondary risks are those risks which arise as a direct outcome of implementing a risk response.
Prevention and inspection
Prevention is keeping errors out of the process. Prevention over Inspection is the biggest slogan of Modern Quality Management.
Affinity Diagrams
Tool to organize and group the results of Root Cause Analysis, are decomposed and organize ideas creatively
Change request
The ultimate authority to approve the change request is always the sponsor.
All Change Requests are recorded in the Change log as a part of project document update. Change Log is also an example for a project document that maintains the status of all change request.
Approved Change Requests generated by Perform Integrated Change Control process becomes input to Direct and Manage Project Work, Control Quality and Control Procurements processes.
A change request must be submitted to update any baseline or Project Management Plans. The standards outlined in the Configuration Management plan determines whether any of the Project documents are subject to the change control procedures.
The Project Manager and Team should analyze the impact of change on other constraints (Schedule, Cost, Quality, Risk, etc.) first, in order assess the reasonableness of the requested change before sharing the same to the CCB.
Though there can be many reasons for a high amount of change requests, If project stakeholders are not identified in the early stage of the project, their project requirements will not be included in the project scope leading to an increased number of Change requests.
Variability risk
Is performed as a part of Perform Quantitative Risk Analysis process.
Active Risk acceptance
When a no response plan has been initiated, and a contingency reserve has been kept to handle the risk if it occurs.
CCB
Change control board, does not approve change request, they are approved be the sponsor.
Does not exist in agile
Kick off meeting
Is part of the Manage Stakeholder Engagement process
If the project is small, the kickoff meeting occurs shortly after the initiation process (in the planning process group). The meeting includes all team members, as the same team is involved with the planning and execution
Risk mitigation
Mitigation is to reduce the impact of the threat.
Control charts
Are established as a part of the Manage Quality processes
The Control chart is an example of Data Representation technique used to Control Quality process to determine its stability.
Confirmation of formal acceptance
The Confirmation of formal acceptance of sellers’ work happens during closing (close Project/phase process).
But formal acceptance of project deliverables is done as part of the validate scope activities.
Perform Quantitative Risk Analysis
Ensures risks are quantified and provides a numerical estimate of the overall effect of risk on the objectives of the project.
Availability of budget and time is a key factor that determines the need for the Perform Quantitative Risk Analysis process. A small project with a limited budget may decide to do away with this process if the project management team decides that quantitative statements about risk and impacts are not needed.
It helps determine the areas of maximum uncertainty on over all project objectives.
Fast tracking and Crashing
Fast tracking involves the performance of activities in parallel, whereas crashing involves the addition of resources to a project. In fast tracking, there is increased risk, whereas in crashing there is increased cost.
Scope baseline
Is the output of the Create WBS process.
Whereas Scope baseline is not an input for Planning Cost Management, and developing initial Cost Management Plan. It is later referred for cost estimation which is a part of Estimate Cost process and cost budgeting, part of Determine Budget process.
Resource leveling
Is a resource optimization technique in which start and finish dates are adjusted based on resource constraints.
Work Performance Information
Work performance information works as an output of control quality and as an input for Monitor and Control Project Work.
includes information about project progress, such as which deliverables have been accepted and which have not been accepted, along with the reasons behind acceptance and non-acceptance.
Contingency and management reserve
Contingency reserve is a part of Cost baseline, and it gets created before baseline gets finalized. If additional funds are required for implementing risk response plan created post planning, management reserve needs to be used. For accessing management reserve, a formal change request should be in place.
Management reserve is NOT part of Cost baseline.
Product owner
Product owner is also ultimately responsible and accountable for the end product that is built, ensures the product vision and is accountable for managing the product backlog.
Product owner is responsible for maximizing the value of the product, and only he has authority to cancel the sprint, although he or she may do under the influence from key stakeholders, sponsor, project manager or any other stakeholders.
The Product Owner cannot update the Sprint Backlog; but can cancel a sprint.
The Product Owner is accountable for ordering the Product Backlog items, whereas the team manages the sprint backlog and the task execution.
Cannot Update the business case.
Retrospectives meetings
Retrospectives are conducted during Control Schedule, Control Quality, Monitor Stakeholder Engagement processes, and all are part of Monitoring and Controlling process group.
Retrospective allow the team to learn, improve, and adapt it process. One of the principles behind the Agile Manifesto: “At regular intervals; the team reflects on how to become more effective, then tunes and adjusts its behavior accordingly.” Supports this concept.