Exam Questions Flashcards
(436 cards)
A project manager is attempting to establish the proper sequencing and duration of project activities. Which of the following would be the MOST beneficial?
Network Diagram
Which of the following are characteristics of a project?
Temporary , Start and Finish.
A company has determined it does not have the in house capability to perform a project and wants to procure third- party services. Which of the following documents will the company MOST likely release FIRST?
RFI
The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation. Which of the following should the project manager bring to the meeting to support this recommendation? Choose two
The issue log to show why the vendor should be replaced.
A change management plan to have the vendor replaced.
A project manager is creating the WBS. In which of the following phases is the project?
Planning
Which of the following is a characteristics of a matrix organization?
Authority is shared between functional and project managers.
A WBS is being developed for a project. Which of the following would be BEST suited to contribute cost and time estimates for the project activities ?
Project manager
A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints.
Status report
A stakeholder is unaware of a project’s status. Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two).
Status report and Meeting Minutes.
There are four parallel paths on a network diagram. The summary duration of each path is below:
A,C,G: 10 weeks
A, B, F: 8 weeks
D, E, H:12 weeks
D, B, F:7 weeks
Which of the following tasks are on the critical path?
D, E, H
A project team is comprised of a mix of in house and virtual team members.
When a complex announcement needs to go out to the entire project team, which of the following is the MOST effective way to communicate it?
Hosting a web conference meeting is the best method. It gives the project manager the opportunity to explain the announcement and answer any questions from the team.
A project requires daily status updates.
Which of the following is the MOST effective method for providing these updates?
Standup
A project sponsor and Chief Information Officer (CIO) disagree about how to release that final deliverables to the market. The sponsor wants to do a massive product release, while the CIO wants to be extremely cautious and add more time for testing and defect resolution. The project manager works with both parties and determines the best solution is to roll the product out in a pilot release to see how it tests, and then use customer feedback to determine next steps.
Which of the following conflict resolution techniques is the project manager using?
Negotiating
A project manager is justifying a required change with the associated impact on the project.
Which of the following is the NEXT step?
Approval
The PMO is responsible for (Choose Two)
Setting standards and practices for the organization and providing governance.
Outlining consequences of non-performance and coordinating between disparate projects.
A critical stakeholder has requested additional status updated beyond the schedules.
Which of the following factors MOST likely needs to be accounted for when communicating with this stakeholder?
Frequency
Which of the following activities are associated with the closing phase of a project ? (Choose Two )
Archiving of project documents and Lessons learned
Which of the following describes a burn rate?
Rate at which the project budget is used.
The project manager for a TV tower construction project receives notification that a strong storm is expected the following week.
Evaluate the risk, develop a mitigation plan and communicate it according to the communication plan.
One deliverable failed during testing, and this has already happened several times.
Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?
Fishbone diagram
During the invitation phase, a project manager has asked for a document containing the high level objectives and goals for a project.
Which of the following documents would contain these items?
Requirements document
A team lead informs the project manager that the data center will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the data center project is out on medical leave.
Which of the following should a project manager update to document this information?
A list of realized risks.
The executive sponsor asks a project manager to summarize the following for a project:
- Final capital expenditures
- Anticipated cost of new employee resources to support the solution.
- Maintenance estimates.
Which of the following information should the project manager provide?
Cost baseline
Which of the following defines a group of projects that work together to achieve a common goal?
Program