Extensions of time / loss and expense Flashcards
(15 cards)
What is an extension of time?
Extension on the date of completion due to the occurrence of a relevant event
What is the process of an EOT?
1) Contractor notifies CA of EOT as soon as reasonably apparent + details on cause / effect
2) CA assessment
3) CA notifies PC as soon as reasonably apparent but within 12 weeks
What is a relevant events?
A delay which impacts the completion date not caused by the fault of the contractor
What are some examples of relevant events?
- Variations / instructions
- Deferment of giving possession of site
- Antiques found on site
- Exceptionally adverse weather
- Works by statutory undertakers
- Force majeure
What counts as Exceptionally adverse weather?
Exceeding the long term average for that time of year / location
What is the time frame for a contractor to raise a relevant event?
As soon as reasonably apparent
What is a Relevant Omission?
Omission of any work or obligation through an instruction for a variation
What is Concurrent Delay?
Where contract delay and employer delay occur at the same time, need to assess in detail to see which arose first
What is Loss & Expense?
Contractor can claim direct loss and / or expense as a result of the progress of the works being materially affected by a relevant matter
Process of Loss & Expense?
1) Contractor gives written notice as soon as reasonably apparent with cause + effect
2) CA assessment
3) CA has 28 days to respond and 14 days per subsequent monthly update
What is a Relevant Matter?
A relevant matter is a matter for which the client is responsible that materially affects the progress of the works.
Examples of Relevant Matters?
- Failure to give the contractor possession of the site
- Delays in receiving instructions
- Opening up and testing works
- Discrepancies in contract documents
- Issues relating to CDM
- Disruption caused by works being carried out by the client
What’s the difference between a Relevant Event and a Relevant Matter?
Time and cost
What are the common heads of claim in Loss & Expense claims?
- Prolongation
- Thickening of preliminaries
- Disruption
- Head office / administration costs
- Acceleration costs
What is force majeure?
Events that are beyond reasonable control of a party, such as war or an epidemic