Flashcards in Formulas Deck (11)
Loading flashcards...
1
Q

BAC

A

budet at completion = original budget

2
Q

AC

A

actual cost = amount spent at a point in time

3
Q

EV

A

earned value: actual % complete * BAC

4
Q

PV

A

Planned Value = planned % complete * BAC

5
Q

CV

A

cost variance = ev - ac

6
Q

cpi

A

cost performance index - ev/ac

7
Q

sv

A

schedule variance - ev - pv

8
Q

spi

A

schedule performance index - ev/pv

9
Q

EAC

A

Estimate at completion
= BAC / CPI

10
Q

ETC

A

Estimate to Completion
= EAC - AC

11
Q

TCPI

A

To complete performance index

= (bac - ev) / (bac - ac)