Q

What constitutes “delayed completion” in a property transaction?

A

The party due to complete fails to do so on the agreed completion date/time under the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Is delayed completion an actionable legal wrong?

A

Yes. It’s a breach of contract giving rise to remedies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What remedy exists at common law for delayed completion?

A

The innocent party may sue for damages for breach of contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What’s the aim of common law damages?

A

To put the innocent party in the position they would have been in had the contract completed on time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Where do you usually find contractual provisions for delay compensation in residential transactions?

A

Standard Conditions of Sale, Condition 7.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Under Standard Conditions of Sale, who can be liable for compensation for delay?

A

Both buyer and seller.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Where are delay compensation provisions found in commercial transactions?

A

Standard Commercial Property Conditions, Condition 10.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Under the Standard Commercial Property Conditions, who is liable for delay compensation?

A

Only the buyer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How is the contract rate for delay compensation determined?

A

Either expressly agreed in the contract or defaults to the Law Society Interest Rate if referenced.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What was the Law Society Interest Rate as of April 2025?

A

4% above Barclays Base Rate; with Barclays Base at 4.5%, total = 8.5%. (Always check current rate.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

If the buyer causes the delay, on what sum is compensation calculated?

A

On the balance due (i.e., the outstanding completion monies).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

If the seller causes the delay, on what sum is compensation calculated?

A

On the whole purchase price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Step 1 in calculating contractual compensation for delay?

A

Calculate daily interest: (Relevant sum × Contract Rate) ÷ 365.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Step 2 in calculating compensation for delay?

A

Count the number of days late: include the scheduled completion day; exclude actual completion day; count calendar days.