Functional Analyst - Helpful Questions 2 Flashcards
A dispatcher needs to know the available staff for any given day. Laborers must track vacation time for the dispatcher to use.
Where can this be done?
A. Define Person Availability in the People application
B. Modify Person Availability in the People application
C. Define Person Availability in the Calendars application
D. Modify Person Availability in the Calendars application
B. Modify Person Availability in the People application
A company has a requirement to report on actual labor hours, materials, services and tools used as work progresses on a work order.
What is the earliest point in the basic life cycle a user can start reporting?
A. APPR B. COMP C. WMATL D. WAPPR Reveal Solution
A. APPR
A vendor requires a payment of 20% of the purchase price when the purchase order (PO) is sent and the company wants to withhold of the payment until 90 days after receiving the item before final payment is made.
How would this be accomplished?
A. A Purchase Requisition would be created and three invoices would be generated via the invoicing application. One invoice for 20%, one for 60% and one for 20%.
B. A Price Contract would be created with a payment schedule with an invoice of 20% at the time the PO is Approved, an invoice of 60% at the time the item is received and another invoice for 20% 90 days after receipt.
C. A Blanket Contract would be created with a payment schedule with an invoice of 20% at the time the PO is Approved, an invoice of 60% at the time the item is received and another invoice for 20% 90 days after receipt.
D. A Purchase Contract would be created with a payment schedule with an invoice of 20% at the time the PO is Approved, an invoice of 60% at the time the item is received and another invoice for 20% 90 days after receipt.
D. A Purchase Contract would be created with a payment schedule with an invoice of 20% at the time the PO is Approved, an invoice of 60% at the time the item is received and another invoice for 20% 90 days after receipt.
A company wishes to group its location records into a hierarchy to assist users in searching for assets.
How can this be accomplished?
A. Location Groups can be created and LIVE locations added.
B. Locations can be linked by using the Related Records tab in the Locations application.
C. Location records will need to be added to a network and can only include locations with an ACTIVE status.
D. Location records need to be added a system and can only include locations with an OPERATING type.
D. Location records need to be added a system and can only include locations with an OPERATING type.
Hide Solution
A company has assets at multiple locations that require maintenance. There is a requirement to have a single work order with charges rolled up to a single GL account.
How can that be achieved?
A. Create a task work order for each asset.
B. Create a child work order for each asset.
C. Add a job plan that has the assets associated.
D. Add the assets in Multiple Assets, Locations and Cls
D. Add the assets in Multiple Assets, Locations and Cls.
Hide Solution
An administrator has a requirement to create 44 new assets that each share a common configuration.
Which application can do this with a single action?
A. Assets
B. Item Master
C. Classifications
D. Asset Templates
D. Asset Templates
A user belongs to two non-independent security groups, Group A and Group B. Group A has a purchasing limit of $7000 and Group B has a purchasing limit of
$8000.
What is the purchasing limit of a user who belongs to both security groups?
A. $7000
B. $8000
C. $15000
D. $56000
B. $8000
Always is going to be the highest of the X security group purchasing limits.
What costing method should be used if the receipt cost of items that are the newest in stock is required?
A. LIFO
B. FIFO
C. Average
D. Standard
A. LIFO
Which report option provides multiple access points for an end user to run reports including the toolbar shortcuts of Browser View, Direct Print, Direct Print with
Attachments and direct access from application dialogs including Work Order Status Change and Inventory Reorder?
A. ERI
B. BIRT
C. Cognos
D. SQL Server
B. BIRT
An approved work order has been assigned an incorrect job plan.
How do you correct this?
A. Change the Job Plan Revision to the correct revision.
B. Clear the Job Plan field and enter the correct job plan.
C. Create a Follow-up work order with the correct job plan.
D. Select Remove Work Plan from the More Actions menu and enter the correct job plan.
Reveal Solution
C. Create a Follow-up work order with the correct job plan.
The user wants to have a new job plan reference an existing job plan so that the data in the existing job plan will be available without re-entering it.
What is the name of this feature?
A. Nested job plans
B. Job plan revisions
C. Job plan sequences
D. Attachment job plans
A. Nested job plans
check
A custom field has been added to the Work Order Tracking application to identify the inspector for environmental impacts of each work order.
What type of role is used to assign the work order to the environmental inspector?
A. Person
B. Person Group
C. A set of data related to the record
D. A set of data related to the login user
C. A set of data related to the record
check
A supervisor is required to report actual work hours by work order number.
With which statuses can this be accomplished? (Choose two.)
A. INPRG B. WAPPR C. CANCEL D. PNDREV E. COMPLETE
INPROG, COMPLETE
A fixed-schedule PM needs to be set up.
What other setting need to be selected in addition to the frequency value?
A. Alert Lead (DAYS) must equal 0
B. Alert Lead (DAYS) must be greater than 0
C. Use Last Work Order’s Start Date to Calculate Next Due Date? checked
D. Use Last Work Order’s Start Date to Calculate Next Due Date? unchecked
Reveal Solution
C. Use Last Work Order’s Start Date to Calculate Next Due Date? checked
A company has a requirement to have items in the storerooms to be reordered automatically.
How can this be achieved?
A. Reorder Escalation
B. Reorder Cron Task
C. Reorder “” Reorder Items
D. Reorder Direct Issue Items/Services
B. Reorder Cron Task
A company has a requirement to share calendar, classification, job plan, item description and PM data.
What needs to be created?
A. Single organization, single site environment
B. Multiple organizations with a shared site environment
C. Multiple organizations with one site per organization environment
D. Multiple organizations with multiple sites per organization environment
A. Single organization, single site environment
An engineer schedules a very complex asset report developed in BIRT. The engineer needs to set a feature to be able to retrieve the report contents from within
Maximo for very large files that are restricted by the email server.
Which feature does this?
A. Direct Print
B. Email with a File URL
C. Email with a File Attachment
D. REPORTSCHEDULE cron task
B. Email with a File URL
A company has a requirement to have labor certificates defined.
In which application can this be done?
A. Crews
B. People
C. Certifications
D. Qualifications
D. Qualifications
A master PM can be used to do which of the following?
A. Create a job plan revision.
B. Generate work orders for associated PMs.
C. Create associated PMs for an item’s location.
D. Change the status of work orders generated from associated PMs.
C. Create associated PMs for an item’s location.
An administrator has a requirement to ensure that purchase requisitions have been approved before being able to create purchase orders from them.
Which settings control this behavior?
A. Clear the Allow PO Creation From Unapproved PR? checkbox in Purchasing Options.
B. Clear the Allow PO Creation From Unapproved PR? checkbox on the purchase requisition.
C. Check the Require PR Approval on PO Creation? checkbox during the creation of the purchase requisition.
D. Check the purchasing option Require Approval to Convert PR to PO or Contract? (checkbox in Purchasing.
D. Check the purchasing option Require Approval to Convert PR to PO or Contract? (checkbox in Purchasing.
Hide Solution
A maintenance planner is in the process of planning time sensitive emergency maintenance work orders for a number of assets where items need to be reserved.
What reservation type should be used?
A. Soft
B. Hard
C. Urgent
D. Critical
B. Hard
A company wishes to create a location that is used during the receiving process when inspection occurs.
Which type of location is used?
A. A HOLDING location at the SITE level.
B. A CLEARING location at the ORG level.
C. A RECEIVING location at the SITE level.
D. An INSPECTION location at the ORG level.
Hide Solution
A. A HOLDING location at the SITE level.
A user is in the Inventory application and has enabled a record for edit mode. The user performs an operation that does not release it from edit mode.
Which operation is it?
A. Save action
B. Moving to Start Center
C. Running a query from the list tab of the application
D. Paging through records by using the Next and Previous links
A. Save action
A user has created a work order against asset ABC. A technician determines that asset ABC is faulty and it needs to be replaced. The technician replaces asset
ABC at the operating location with asset XYZ from a repair location.
What happens after the swap?
A. Asset locations have been swapped.
B. Asset identifiers have been swapped.
C. Inventory locations of the assets have been swapped.
D. The faulty asset ABC status at the operating location gets updated to OBSOLETE.
A. Asset locations have been swapped.