What is the primary goal of the commissioning process in construction?

A

To verify systems meet performance requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which of the following is NOT a part of the commissioning process?
A) Design review
B) Pre-installation verification
C) Post-occupancy survey
D) System testing and verification

A

Post-occupancy survey

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why is commissioning important in reducing long-term operational costs?

A

It reduces energy usage by verifying system efficiency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the main purpose of the commissioning report?

A

To document the performance of building systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which phase of commissioning focuses on reviewing design documents and ensuring they meet project goals?

A

Design Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a key task during the construction phase of commissioning?

A

Verifying the installation of systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The final commissioning report should include all EXCEPT:
A) Testing results
B) Problem resolutions
C) Recommendations for future systems upgrades
D) Profit margin analysis

A

Profit margin analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which of the following best describes the role of the commissioning coordinator?
A) To design the building’s systems
B) To oversee and verify commissioning tasks
C) To perform all testing and troubleshooting
D) To coordinate the project’s marketing

A

To oversee and verify commissioning tasks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is one of the main responsibilities during the design phase of commissioning?

A

Reviewing construction plans for compliance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In the commissioning process, which document outlines testing procedures and results?

A

The testing reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does “acceptance verification” ensure in the commissioning process?

A

Systems meet performance specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

In the commissioning process, which document outlines testing procedures and results?

A

The testing reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does “acceptance verification” ensure in the commissioning process?

A

Systems meet performance specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does the commissioning report help the facility management team with after
construction?

A

Managing ongoing system maintenance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The design phase of commissioning ensures that the building systems are:

A

Designed to be compatible with the owner’s goals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which document helps track whether systems meet regulatory standards in
commissioning?

A

Acceptance verification documentation

17
Q

What is the primary role of the commissioning agent during the commissioning process?

A

To oversee testing and system performance evaluations

18
Q

Which phase of commissioning would most likely include system tests and functionality
checks?

A

Acceptance Phase

19
Q

The executive summary overview in the commissioning report is designed to:

A

Summarize key findings and results from the commissioning process

20
Q

Which phase of commissioning would address performance issues found after the system is installed?

A

Acceptance Phase