Identifying the Project Scope Flashcards

1
Q

Scheduling steps

A
  1. Identify scope
  2. Activities and tasks
  3. Dependencies and networks
  4. Estimating and risks
  5. Critical Path
  6. Add resources
  7. Schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Identify the scope =

A

Identifying the products or outputs that are needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Activities and tasks=

A

Determine the activities and take required to produce the products or outputs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Dependencies and networks=

A

Establish the dependencies between the activities and draw a network showing how they link together

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Establishing risks =

A

Estimate the duration and the associated risks ( duration is added to the network)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Critical path=

A

When the duration has been added to to the network we can identify the critical path and then add resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Resources =

A

Resources are added when the critical path has been identified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Schedule =

A

After all the steps are completed a schedule is established ( probably have to run up and down the steps unlikely to get it right the first time)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

PBS ?

A

Product breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

PBS: scope ?

A

The totality of the outputs , outcomes and the benefits and the work required to produce them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

PBS: Scope management

A

The process whereby outputs , outcomes and benefits are identifies , defined and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

PBS: the scope of the project is defined by listing all the _______ that will be provided and the amount of ______ involved

A

Products
Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

PBS: it is important to state what is out of scope as this sets the _________ for the _________

A

Expectations
Project stakeholder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Product break down structure =

A

The products are established by producing a product break down structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A product breakdown structure is a?

A

Hierarchal structure - products at the high level are shown as consisting of the products at the lower levels

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

WBS?

A

Work break down structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Work breakdown structure :

A

Once products have been identified we can define the activities required to produce the product

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

WBS + PBS - there is no need to ?

A

Consider the order of activities as this point

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Once the WBS is completed we can move on to consider the ?

A

Organisational break down structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

OBS?

A

Organisational break down structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Organisational breakdown structure:

A

Once we know what activities are required we can establish the skills or the personnel required to undertake the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

OBS: once we determine who will undertake the work , tasks are allocated to the team through a ?

A

Responsibility assignment matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Responsibility assignment matrix =

A

RAM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Responsibility assignment Matrix:

A

Combines the WBS with the DBS to produce a report showing who does what

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
RAM: The acronym RACI is used to ?
Define the activities
26
RAM: RACI ?
Responsible - The person doing the work Accountable - the person accountable for the work being done Consult - the person or people who will be consulted during the execution of the work Informed: the person who will be informed about the work during during its execution
27
CBS?
Cost Breakdown Structure
28
Cost Breakdown Structure:
Based on the RAM and the WBS and will be finalised once estimating step has been completed.
29
CBS: the CBS is normally some Sort of ?
Spreadsheet , where we list all The activities and against each activity we allocate the areas of cost
30
CBS: areas of cost ?
The cost of labour + Materials Plant and specialised equipment
31
CBS: Areas of cost also include ?
Allowances for contract or subcontract cost along with cost for management and overheads and allowances for any contingencies or risks.
32
CBS: the cost is allocated to ?
Different cost areas, once totalled up we can and an allowance for profit to obtain the final cost for the project
33
BENEFITS OF STRUCTURE: helps the team to think about the _________ and in turn reduces the risk of _________
Work requires Overlooking something
34
BENEFITS OF STRUCTURE: plans can be used to gain _______ from the _______
Agreement Customer/client
35
BENEFITS OF STRUCTURE: the WBS list all the activities required to produce the ________
Network diagram and schedule
36
BENEFITS OF STRUCTURE: the CBS provides a ______
Total cost for the project
37
BENEFITS OF STRUCTURE: the PBS Identifies ____________ . The numbering system provides________
Products / outputs Consistency throughout the project documentation
38
BENEFITS OF STRUCTURE: the structure ensures the team members know _____
What they most do
39
Scope management liner vs Iterative: how is the scope identified
Linear : scope is developed using a pbs and or WBS Iterative: the scope is structured using a prioritisation technique such as MoSCoW - must have - should have - could have - won’t have
40
Scope management liner vs Iterative: CBS vs MUST HAVES
Linear : the cbs is used to define the cost of all resources , labour and materials etc. necessary to complete the work Iterative: must have requirements are priorities into user stories and these are translated into a target scope of work
41
Scope management linear vs Iterative: work
LINEAR - time cost and quality Are generally defined later in the planning process ITERATIVE - the target scope of work must be achieved within a target time window w/ defined resources
42
Scope management iterative - subsequent iterations may result in the scope being ______ based on the _______ gained and any _____ the team has acquired and the emerging ______
Modified Experience Insight Priorities
43
The PBS is a hierarchical structure where the main main output of the project is placed at the ________. The next level down shows the components that makeup the _______. The process continues to the level of __________ products. Each products will have defined _______ and _____ methods.
Top level Higher level Individual products Acceptance criteria Quality control
44
The pbs shows ?
What will be delivered
45
Once the PBS is completed it can be used to do the initial _____ to obtain stakeholders _______ that the Products identified are what stakeholder expect the project ______ and get a firm agreement to that effect.
Scope verification Agreement To deliver
46
Following the categorisation of the project to Create products , the PM is able to direct those products to the must suitable _______ resource for more detailed scope _____. This results In the baseline scope of work to be defined through a _______ which will detail the activities which will be _____and ______to meet all the requirements and benefits.
Technical Definition WBS Scheduled and resourced
47
The lowest level of the WBS consist of work packages that contain the activities to be performed to allow ____, ______ and ____. All necessary to do the work and ultimately deliver the output.
Scheduling , estimating and resourcing assignments
48
Where the objective is well understood and has a tangible out it is usual to define the scope as ____________________.
Accurately as possible at the beginning of the lifecycle
49
Where the objective is less tangible or subject to significant change a more ______________
Flexible or iterative approach to scope Is needed
50
In the WBS each work package will have a _________ in order to be tracked within the business management systems of the Organisation. Any estimated cost related to the delivery of the work package can then be ______ using the ________.
Coded reference Recorded Coding structure
51
The resulting structure of the WBS is the ______. A ______ breakdown of the project into cost elements.
CBS Cost
52
The CBS provides a ______ view of the project and splits the project scope into its individual _____________ components. which can be related back to the original breakdown.
Financial view Cost
53
The OBS describes the structure of the project _______ required to complete the work packages in the WBS. This is useful useful particularly when work will be performed by business staff ______ on to the project or by specialist team working on more than one project. It is also important for individuals themselves to know where they are ________ in the structure and their reporting_________.
Organisation Seconded Situated Responsibilities,
54
The WBS and OBS can be combined together to create a communication devise known as ____________
A responsibility assignment matrix (RAM)
55
The RAM ensures ?
That people who are going to Do the work are fully aware of the work they have been assigned together with their position in the project organisation
56
A common coding structure can be applied to the RAM. Where the RAM is coded it can also be referred to as a _________ matrix
RACI
57
RACI stand for
Responsible Accountable Consults Informed
58
The RAM provides a clear and concise summary of _____ or _______ the specific responsibilities defined within the _________ and the level of accountability or contribution expected from named roles or individuals within the project
Tasks or deliverables Project procedure
59
Requirement management: in all cases specific project objectives and requirements are informed by the ________ and _____ desired by the stakeholders. Requirements are the stakeholders wants and needs and must be clearly defined with _______.
Success criteria and benefits Acceptance criteria
60
Everyone involved in carrying out requirements management must also ensure that:
There is linkage between benefits , project success criteria , project objectives and project requirements Requirement are clear , unambiguous and expressed as simply as possible
61
Requirement management: high level requirements are defined during the concept phase these need to be detailed enough to make an _________
Investment decision ( where or not to proceed to the definition phase)
62
Requirement management: requirement management is the process of _____, _______ and _______ stakeholders wants and needs. It requires the capture of requirements via a __________. This process should incrementally breakdown the requirements in a ________ manner considering different conditions and scenarios.
Capturing , assessing and justifying Structured process Hierarchal manner
63
Requirement management: The requirements once defined must be ________ with the project ____ and or key _____ to ensure the full scope has been captured.
Validated Sponsor Stakeholders
64
Requirement management is an ongoing ____ that is maintained through tout the project lifecycle. These requirements becomes the ____________ deliverables. This is helps us define the project scope allowing the project team to understand the exact ______ of the project and how the work will be structured to meet the requirements and deliver the scope
Process Principle project Deliverable
65
Requirement management establishing scope: step one , gathering of requirements
Can be done in a number of ways ranging from personal interviews , workshops , focus groups, surveys etc. some methodologies including agile approaches are designed to enable Continuous gathering and refinement of requirements on the assumption that the stakeholders may not be sure of their needs.
66
Requirement management establishing scope: analysing requirements
Analysing combines information from functions such as schedule management and investment appraisal, with specific value based techniques such function analysis and function cost analysis. Resulting in a thorough understanding of requirements and the value they contribute to the overall objective.
67
Requirement management establishing scope: sometimes more requirement are requested than it is feasiblle To deliver so a ________ Excercise is needed to highlight the most essential requirements and justify why the chosen requirement should the ones that are ______. Such as MoSCoW
Prioritisation Baselined
68
MoSCoW when using an agile methodology…
The could have and should have requirements would be sacrificed if at anytime the project was predicted to over budget or be late . The must have would Only be reduced as a very last resort. Worst case scenario project would deliver only the must have in the form of a MVP. This process ensures that the essential requirements are understood as an input to work to select the optimal solution and then define the detailed scope of work to be delivered with an acceptance criteria.
69
Once the schedule is created it is important to confirm with the resource owners that the resource assumptions around available are ?
Validated If the resources are not available when the work is planned the schedule cannot be achieved